API ICP Programs API-580 Practice Questions V9.02 Killtest are usually recognized by our prior users since it assisted them to get able to face the actual API-580 exam with full confidence. They have support on grip regarding how to deal with the API API-580 exam stress and also to handle time for every API API-580 exam question and answer. Killtest aspires to take forth the genuine API API-580 practice exam to pass through API-580 Risk Based Inspection Professional exam to its users.

Télécharger la présentation

API ICP Programs API-580 Practice Questions V9.02 Killtest

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The safer , easier way to help you pass any IT exams. 1.The data validation step stresses the need for a knowledgeable individual. A. To comparing data from the inspections to the expected deterioration mechanism and rates B. To compare the results with previous measurements on that system C. Similar systems at the site or within the company or published data D. All of the above Answer: D 2.Following are the critical variables for deterioration mechanism except A. Material of construction B. Process operating C. Start up and shut down conditions D. Insulation Answer: D 3.If a qra has been prepared for a process unit, the analysis can borrow extensively from this effort. A. Rbi consequence B. Rbi likelihood C. Rbi probability Answer: C 4.If the probability and consequence combination (risk) is high enough to be unacceptable, then A. A mitigation action to predict or prevent the eventis recommended. B. A mitigation action to predict or prevent the event isnot recommended C. Warrant to analyze risks involved Answer: A 5.A Rbi analysis shares many of the techniques and data requirements with a____________. A. Qra B. Pha C. Hazop D. Event tree Answer: A API ICP Programs API-580 Practice Questions V9.02 Killtest 6.CORRECT TEXT ..............Produces inspection and maintenance plans for equipment that shouldbe implemented to provide...............and................ A.Rbi, reliable and safe operation Answer:A 7.Following are some of the recognized risks which cannot be managed by inspection alone except one A. Equipment nearing retirement B. Failure mechanisms (such as brittle fracture, fatigue) where avoidance of failure primarily depends on operating within a defined pressure/temperature envelope C. Consequence-dominated risks 2 / 7

  2. The safer , easier way to help you pass any IT exams. D. The suitability and current condition of the equipment within the current operating envelope will determine the probability of failure (pof) of the equipment from one or more deterioration mechanisms Answer: D 8.Potential hazards identified in a pha will often affect the A. Probability of failure side of the risk equation. B. Consequence of failure side of the equation Answer: A 9.In RBI most of the probability assessment will be A. Only quality assessment B. Only quantity assessment C. Blend of quality and quantity assessment Answer: C 10.The primary audience for rp 580 is A. Inspection and materials engineering personnel B. Maintenance personnel C. Only inspection personnel D. Only materials engineering personnel Answer: C 11.___________is usually not the primaryobjective of a rabiassessment, but it is frequently a side effect of optimization. A. Reducing inspection costs B. Increasing inspection costs C. Increasing frequency of inspection programs Answer: A 12.Probability of failure analysis is made from A. Loss of containment that occurs due to deterioration mechanism B. Consequences of the failure C. Done just with previous experience API ICP Programs API-580 Practice Questions V9.02 Killtest D. All the above Answer: A 13.If multiple inspections have been performed, which inspection may best reflect current operating conditions? A. Most recent inspection B. Base line inspection survey C. Process conditions D. Corrosion survey Answer: A 3 / 7

  3. The safer , easier way to help you pass any IT exams. 14.The type of failure mode that likely to occur due to mechanical and metallurgical deterioration A. Smallholes to ruptures B. Cracks C. Catastrophic ruptures D. Leaks Answer: C 15.Hazard identification in a rbi analysis generally focuses on identifiable failure mechanisms in the equipment (inspectable causes) but does not explicitly deal with A. Other potential failure scenarios resulting from events such as power S failures or human errors B. Other potential failure resulting from events such as flammable fire due to leak from equipment C. Environmental impact caused due to toxic release Answer: A 16.Reliability efforts, such as reliability centered maintenance (rem), can be linked with rbi, resulting in an integrated program to A. Reducedowntime in an operating unit B. Reduce operating time of a unit C. To reduce risk by mitigation activities Answer: A 17.Some failures have potentially serious consequences, but if the probabilityof the incident is low, then A. The risk may not warrant immediate action B. The risk may warrant immediate action C. The risk may warrant appropriate mitigation action Answer: A 18.Fora typical inspection program, if excessive inspectionis applied then, A. Level of risk may go up B. Level of risk may go down C. Level of risk remain the same Answer: A API ICP Programs API-580 Practice Questions V9.02 Killtest 19.Act of mitigating a known risk to a lower level of risk. A. Risk reduction B. Risk mitigation C. Risk evaluation Answer: B 20.When in accurate or insufficient failure data exists on the specific equipment item for quantative probability of failure analysis then A. General industry, company or manufacturer failure data used B. Process hazard analysis failure data may be used C. Process and toxic concentration analysis may be used 4 / 7

  4. The safer , easier way to help you pass any IT exams. Answer: A 21.Process to find, list, and characterize elements of risk A. Risk estimation B. Risk evaluation C. Risk identification Answer: C 22.The models are evaluated_____________to provide both qualitative and quantitative insights about the level of risk and to identify the design, site, or operational characteristics that are the most important to risk A. Probabilistically B. Statistically C. Linearly D. Logically Answer: D 23.When the inspection program is optimized based on an understanding of risk, one or more of the following cost reduction benefits may be realized. Except one A. Ineffective, unnecessary or inappropriate inspection activities may be eliminated B. Effective, necessary or appropriate inspection activities maybe eliminated C. On-line or non-invasive inspection methods may be substituted for invasive methods that require equipment shutdown D. More effective infrequent inspections may be substituted for less effective frequent inspections Answer: B 24.Qualitative analysis is done and the outcome will be A. Exact number B. High, medium and low or range C. Only in report Answer: A 25.Rbi is focused on a systematic determination of API ICP Programs API-580 Practice Questions V9.02 Killtest A. Relative risks B. Absolute risks C. Comparable risks D. Total risks Answer: A 26.If a very aggressive acid is carried over from a corrosion resistant part of a system into a downstream vessel that is made of carbon steel, the result would be A. Rapid corrosion could result in failure in a few hours or days. B. General corrosion over a period of time could result in metal loss C. No deterioration will take place since carbon steel is resistent to aggressive acid 5 / 7

  5. The safer , easier way to help you pass any IT exams. Answer: A 27.Probability side of the risk equation is normally managed by A. Plant inspectors or inspection engineers B. Maintenance planning engineers C. Process safety personnel D. Both a and b Answer: A 28._____________represents the next generation of inspection approachesand interval setting, recognizing that the ultimate goal of inspection is the safety and reliability of operating facilities A. Rbi B. Pha C. Hazop D. Rcm Answer: A 29.No deterioration found in the inspection program but still failure can occur under the following conditions. A. During plant construction period B. As a result of change or process upset condition C. All the above Answer: B 30.Limitation of any negative consequence or reduction in probability of a particular event A. Mitigation B. Reduction C. Residual Answer: B 31.______________ provides a consistent methodology for assessing the optimum combination of methods and frequencies. A. Rbi B. Rem C. Pha D. Hazop Answer: A 32.A physical condition or a release of a hazardous material that could result from component failure and result in human injury or death, loss or damage, or environ- mental degradation A. Hazard B. Loss C. Failure Answer: A API ICP Programs API-580 Practice Questions V9.02 Killtest 6 / 7

  6. The safer , easier way to help you pass any IT exams. 33.Following is the unit of measure of consequence that is least developed among those currently used for rbi assessment A. Affected area B. Cost C. Environmental damage D. Safety Answer: C 34.Risk presented in quantitative risk analysis as a A. Precise numeric value B. Form of risk matrix C. Form of event tree and fault tree Answer: A 35.The program that is focused on understanding failure modes, addressing the modes and therefore improving the reliability of equipment and process facilities. A. Rbi B. Pha C. Rem D. Hazop Answer: D API ICP Programs API-580 Practice Questions V9.02 Killtest 7 / 7