1 / 27

Treatment of Slaughterhouse Wastewater

Treatment of Slaughterhouse Wastewater. Mike Lawrence NDSU Fall 2006. Overview. Challenges Wastewater Parameters Treatment Options Process Modifications Typical On-site Treatment Options Design Problem. Challenges of Slaughterhouse Wastewater.

kimama
Télécharger la présentation

Treatment of Slaughterhouse Wastewater

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Treatment of Slaughterhouse Wastewater Mike Lawrence NDSU Fall 2006

  2. Overview • Challenges • Wastewater Parameters • Treatment Options • Process Modifications • Typical On-site Treatment Options • Design Problem

  3. Challenges of Slaughterhouse Wastewater • Wastewater contains large amounts of blood, fat, and hair • Wastewater is above municipal standards which leaves two options; on site treatment or pay to be treated elsewhere • On site treatment with low capital and maintenance costs is desirable

  4. Wastewater Parameters • BOD approx. 1,000 to 4,000 mg/L • COD approx. 2,000 to 10,000 mg/L • SS approx. 200 to 1,500 mg/L • High Oil and Grease content • Possible high chloride content from salting skins

  5. Treatment Options • Discharge to sewer to be treated by municipal treatment plant • Land application of wastewater for irrigation • Reduce amount of wastewater and/or concentrations with the wastewater by changing the processes • On site Treatment • Flow Equalization, Screening, Dissolved Air Flotation, Primary Sedimentation • Aerobic Treatment • Anaerobic Treatment

  6. In-Plant Modifications to Reduce Pollution • Main goal should be to prevent product from entering the waste stream and using the least amount of water possible • Reduce the amount of water used, saves money in two ways • Use high pressure and just enough • Proper detergents • Lower volume of water helps equipment • Reuse as much water as possible

  7. Line Separation • Separating the various waste streams as much as possible • Sanitary lines should be discharged directly to the city sewer • Grease waste streams and non grease waste streams can help reduce treatment costs • Separate Blood line

  8. Blood Recovery • Blood has ultimate BOD of 405,000 mg/L • One head of cattle contains 49 lbs. of blood which equals 10 lbs. BOD, compared to 0.2 lbs. discharged per person per day • All blood should be recovered in a separate line draining to a tank • Blood is then dried, commonly a continuous drier is used • Profitable end product

  9. Stockpen Area • Stockpen waste and other manure should be hauled away as a solid • Cleaned periodically with as little water as possible • Ideally this water would go to a separate tank • From the tank it would be emptied into a truck and land applied

  10. On-Site Treatment • Costs of treating on site or letting the municipality treat the waste should calculated • Maintenance and operation should be also put into cost analysis • Flow equalization is usually a very good first step in on-site treatment

  11. Hydrasieve • BOD Removal 5-20% • TSS Removal 5-30%

  12. Hydrasieve

  13. SS and Grease Removal • Grease removal could be very profitable • Skimming operations • 20 to 30 % BOD removal • 40 to 50 % SS removal • 50 to 60 % grease removal • Dissolved Air Flotation, DAF • 30 to 35 % BOD removal • 60 % SS removal • 80 % grease removal

  14. Skimming Operation (Primary Sedimentation) • Detention time 1.5 to 2.5 hr • Overflow Rate 800 to 1200 gal/ft2*d

  15. Dissolved Air Flotation (DAF) • Hydraulic Loading Rate • 1.5 to 5.0 gpm/ sq. ft. • Solids Removal Rate • 1.0 to 2.0 lbs/hr/sq. ft.

  16. Anaerobic Lagoons • Ideally the lagoon would be covered, odor & gas production contained, heat retention • Not well suited for colder climates • Detention time 20 to 50 days • BOD5 loading= 200 to 500 lb/ac.-d

  17. Anaerobic Contact Reactor (ACR) • Hydraulic Retention time 0.5-5 days • Organic Loading rate of 1.0-8.0 kg COD/m3-d Flocculator or

  18. Anaerobic Sequencing Batch Reactor (ASBR) • HRT 6 to 24 hours • SRT 50 to 200 days • 98% removal with 1.2kgCOD/m3-d • 92% removal with 2.4kgCOD/m3-d • Possibly rates to 5 kgCOD/m3-d • Effluent SS range between 50 – 100mg/L depending on HRT

  19. Upflow Anaerobic Sludge Blanket (UASB) • Proteins and fats may cause problems in formation of granules. • Loading rates of 4-12 kg sCOD/m3-d • Retention times of 7-14 hours

  20. Design Problem • Flowrate:120,000 gpd, 83 gpm, Max 300 gpm • TSS=1500 mg/L • COD=5000 mg/L • sCOD=3000 mg/L • BOD5=2,000 mg/L • Reduce levels to municipal levels and discharge into sewer

  21. Screening • Hydrasieve • Use prior to flow equalization to save on pumps and buildup in the tanks • Design for max flow of 300 gpm • 4.5 by 7 foot model will handle flow • Approximate cost of $8,000

  22. Primary • Loading Rate of 600 gal/ft2-d • Final Design • 8 ft. wide, 25 ft. long, 10 ft. deep • 8 ft. of weir w/ loading rate of 15,000 gpd/ft • HRT = 3 hours 10 ft 8 ft 25 ft

  23. Anaerobic Lagoon • Covered for heat retention • Side depth = 8 feet • Final Design 540 lb BOD5/ac-d • HRT=80 days Plan View 400 ft 400 ft

  24. Anaerobic Contact Reactor • Final Design HRT=5 days • Loading Rate 1.0 kg COD/m3-d • Clarifier design based on 24m/d settling velocity 56 ft 16ft 10 ft Anaerobic Contact Reactor, Completely Mixed Clarifier 30 ft Flocculator, Deglassifier

  25. Aerated Sequencing Batch Reactor • Two reactors of same size • Feed 8 hr, react 37.5 hr, settle 2 hr, drain .5 hr • Feed 8 hr, react 13.5 hr, settle 2 hr, drain .5 hr 24 ft 46 ft Supernatant Drain 11.5 ft above bottom Sludge waste at bottom

  26. Upflow Aerated Sludge Blanket Reactor • Loading Rate of 10 kg sCOD/m3-d • Two tanks, operated in parallel • Diameter = 4.5 m, Height= 7 m, 2.5 m for gas storage 4.5 m 7 m

  27. Final Design • Include Hydrasieve: effectiveness and low capital, O & M costs • Upflow Anaerobic Sludge Blanket Reactor • Tank is smaller than most of the others due to high organic loading rate • Provides constant source of methane gas

More Related