An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROGRESS REPORT ON ON MAPB TEMPUS PROJECT PREPAREDBY YSU AND ASAU

  2. Specific Objective 1 To design and introduction the ECTS modular based New MSc Program end of the Year 1 - Structure (modular paths, courses to be updated, new courses) /Month 6, Year1 • Content (syllabi, materials) /Month 6, Year 2

  3. MSc program sub programs Food biotechnology

  4. MSc program sub programs Food biotechnology

  5. MSc program sub programs Food biotechnology

  6. MSc program sub programs Food biotechnology

  7. MSc program sub programs Food biotechnology

  8. MSc course development 1. modular structure 2. brief content of the modules 4. module specification 5. detailed syllabus 6. Programme specification

  9. Modular structure

  10. Specific Objective 1 • Modular structure • Number of courses to be updated (approx 30 %) • Number of new course (approx 70%) 2. Brief contents of the modules

  11. MSc modular program management, Quality assurance end of the year 1 Specific Objective 2 New Program Management Scheme (definition of position and relevant terms of Reference: PMB composition, tutors, field Leaders, representative unit at Program management Board, etc). QA procedures, and all related documentation

  12. Specific Objective 2 Draft -programme management scheme, developed by TSU -QA scheme, developed by TSU and YSU Should be discussed

  13. Specific Objective 2

  14. Specific Objective 3 • Development of new teaching methods • end of the Year 1 • upgrading of technical resources, library, equipment • new pedagogy and teaching methods • three lingual web-portal developed and fully operational (program management tools, e-learning)

  15. Specific Objective 3 • upgrading of technical resources, library, equipment • Assessment of existing library resources have been done • YSU and ASAU libraries • Library of National Academy of Sciences • Public library

  16. Specific Objective 3 • upgrading of technical resources, • library, equipment The list of required recourses to be purchased within Project updated. The procurement process started.

  17. Specific Objective 3 • new pedagogy and teaching methods improvement pats have been identified lecture form and time type of active learning required resources desired resources required classroom

  18. Specific Objective 3 three lingual web-portal developed and fully operational (program management tools, e-learning) DEMO VERSION OF THE WEB SITE HAVE BEEN ALEDY DEVELOPED BY TSU http://www.biosciences-tempus.org/ NOW THE TIME TO SUBCONTRACT INDIVIDUAL FROM ARMENIAN SIDE TO FOLLOW UP THE ARMENIAN PART OF THE WEB SITE

  19. Specific Objective 4 Partnership with Industry • Review and analysis of possible collaborative • national/international Companies, survey of companies‘ • demands, specific needs, survey of labour market, visits • and discussion with possible collaborating Georgian/ • European companies • Possible scheme/strategy should be identified.

  20. Partnership with Industry Developedby YSU Institute of Molecular Biology, Center of Ecological Monitoring, “Ashtarakkat” milk factory, “Ararat”brendy-wine factory, ‘’Kilikia” beerfactory, “Tree project” research area Ongoing activity

  21. Partnership with Industry DevelopedbyASAU 1. MARIANNA- MILK FACTORY  2."BACON" MEAT PROCESSING FACTORY 3. "ATENK" MEAT PROCESSING AND PACKING FACTORY 4."ASHTARAK-KAT 5. "ECHMIADZIN KAT” 6."MAP" Closed Joint-Stock Company 7. ‘’VEDI ALCO’’ Co Ltd 8.LUSAKERT PEDIGREE POULTRY PLANT

  22. Partnership with Industry AGREEMENT ON ECTS CREDITS TRANSFER BETWEEN ASAU AND YSU IS BEING DEVELOPED

  23. Specific Objective 5 Student mobility programme between PC and EU with guaranteed academic recognition through ECTS) as an integral part of their degree programs/with guaranteed academic recognition through ECTS) as an integral part of their degree programs. Preparatory works – end of the year 2. (selection of students, identification of host EU Universities, scheduling etc). Criteria for selection of students is being developed

  24. Specific Objective 6 Initiation of joint degree scheme between the EU and PCs end of Year 3 The Joint degree legislation and requirements in PCs are being evaluated. Main points for discussion in Alicante workshop have been already developed.

  25. Specific Objective 6 • Main points for discussion in Alicante workshop have been already developed. • The possibilities of initiation of Joint degree in case of absence of appropriate legislation in PCs. • The number of ECTS student should collect from the joint University. • The level of similarity of the programme structure and content between Universities.

  26. Specific Objective 7 • Dissemination • Program promotion campaign, open days, presentations, publications /starting middle of Year 1 -during the whole project • - Other HEIs nationally and regionally/ starting middle of Year 1 -during the whole project

  27. Specific Objective 7 Dissemination Project have been presented in Tbilisi during the International Conference organized by CRDF in 7-9 June, 2010 Publication of leaflets and other promotional materials will be discussed during Alicante workshop.

  28. PREVENTIVE MONITORING VISIT OF EC PROGRAMME OFFICER AND NTO OF ARMENIA Alba Chiara Tiberi TEMPUS Project Officer Lana Karlova Armenia NTO coordinator 1ST DAY – visit YSU team 2nd DAY- visit ASAU team More then 25 participants including administrative staff, academic and technical staff from YSU and ASAU

  29. PREVENTIVE MONITORING VISIT OF EC PROGRAMME OFFICER AND NTO OF ARMENIA • The activities according the timeline • Management tasks with project managers • The collaboration • Between project grant holder and PCs • Between PCs and European countries • Between the Universities In PC country • 3. Duties of project team members and the level of their integration into project overall activities • 4. University – Industry links • 5. Sustainability of the project • 6. Difficulties

  30. PROGRESS OF THE PROJECT ACCORDING THE EC OFFICER IMPRESSION Project is one of the TEMPUS projects which have the base for success in all partner countries Collaboration between Grant Holder, PCs and European countries is on good level Logistics of the organization of activities within the country and between PCs is on good level THE MAIN OUTCOME OF THE MONITORING VISIT WILL BE THE REPORT WITH RECOMMENDATIONS WHICH WILL BE SEND TO OUR GRANTHOLDER.