1 / 18

Overview of the L HC RF Operation in 2017

Overview of the L HC RF Operation in 2017. H. Timko, CERN, BE-RF Acknowledgements : P. Baudrenghien , P. Martinez Yanez , M . Therasse, K. Turaj. LHC RF Installations (P4). Klystron gallery , Faraday cages , HV bunkers. LHC RF Installations (P4). 8 RF cavities /beam.

kist
Télécharger la présentation

Overview of the L HC RF Operation in 2017

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview of theLHC RF Operation in 2017 H. Timko, CERN, BE-RF Acknowledgements: P. Baudrenghien, P. Martinez Yanez, M. Therasse, K. Turaj

  2. LHC RF Installations (P4) Klystron gallery, Faraday cages, HV bunkers SRF workshop 31/05/2018

  3. LHC RF Installations (P4) 8 RF cavities/beam SRF workshop 31/05/2018

  4. Typical RF Start-up YEARLY RECOMMISSIONING

  5. Recommissioning Timeline Typicaltimeline after an (E)YETS First beam SRF workshop 31/05/2018

  6. HV and Klystron Tests • Annual teststobeperformed (~3 weeks in total) • Placingshortcircuits • Verificationof HV bunkers • Services, crowbars, modulators • Verificationof HV interlocks • Verificationofklystrons • Klystrons, circulators, focus power supplies, power meters • Services: waterflow, vacuum • Klystron power calibration • Calibrationofklystron DC power againstcollector thermal power (derivedfromwaterflow) • Circulator, interlock level, andmanyotheradjustments SRF workshop 31/05/2018

  7. CavityConditioning • Increasing pulse length from200 µs to CW • Conditionthe operational workingpoints • QL = 20,000 • Flat bottomsettings: QL = 20,000 with 0.75 MV/cavity • QL = 60,000, upto 2 MV/cavity • Flat top settings: QL = 60,000 with1.5 MV/cavity • In dedicatedmeasurements, upto 2 MV/cavitymaybeused • QL = 40,000 (intermediate position) • Criterion for a ‘conditioned’ cavity: no activity for 12 hours SRF workshop 31/05/2018

  8. Cavity Controller Setting-up • Adjustment of cavity feedback loop • Calibration of offsets, delays, phases, and gains in the LLRF modules • Step-by-step procedure, closing different parts of the overall loop one after the other • To make sure the loops are stable and have enough stability margin • In operation, this is done during the switching ON sequence • Automatized using python scripts SRF workshop 31/05/2018

  9. Commissioning Experience • All setting up from high power to LLRF has to be done for 16 lines • Many things can be automatized, but still human intervention is necessary: a few lines will always show unexpected behaviour at some stage of the commissioning  experts needed • Work parallelisation is best done with several trained persons • Everything changes at the same time • Technical stops are shortened to a minimum and often commissioning has to be performed with modified hardware & software, or one has to cope with last-minute modifications during the commissioning • Sometimes difficult to debug faults • Several teams work in parallel; good coordination & communication needed SRF workshop 31/05/2018

  10. Operational Aspectsofthe LHC RF • Reliable system with relatively high availability • Yet, hardware faults occur and are expected to be more frequent with ageing equipment • Software constantly evolves, or is migrated, leading to some faults • LHC requests evolve with time as well, requiring new solutions • For all these, a fast response time from experts/piquet is expected • Deployment of modifications often limited to technical stops • Modifications need to consider machine protection, interlocks… • Extensive remote control & diagnostics • Most faults can be diagnosed and fixed remotely, actual accesses only needed for hardware faults • Maintaining a high availability through preparing solutions in advance and mitigating problems before they occur SRF workshop 31/05/2018

  11. Longitudinal Beam Dynamics • Beam dynamics studies are an integral part of the RF operation • Measurements, theory, simulations • Diagnostics and tools for operation and experts • Keep on developing new tools Simulatedandmeasuredbeam instabilities on flat bottom SRF workshop 31/05/2018

  12. Maintenance of Operational Spare • Module exchangeduring LS1. Toensure a smooth operation: • Spare cavityprogramme • Maintenance of operational spare • E.g. newpumpingcrossestoavoidleaks SRF workshop 31/05/2018

  13. Summary ofFaultsandIssues Interventions 2017

  14. Availabilty in 2017 • The peakoffaultsistypicallyoccuringduringtheintensityramp-up; onedifficultinterventionof 14 h 31 faults 47.3 h downtime From28th April till 10th November SRF workshop 31/05/2018

  15. Faults Hardware Faults Controls Faults FESA process missing or needs restarting (3) FEC needs reboot (1) Crates down (2) Communication issuesbetween different FESA classes(3) • Klystron (4) • Cooling, vacuum level, thyratron oil level, high cathode current • Power supplies (3) • Spurious trips or arcs (6) • Spurious interlocks (2) • Vacuum level, main coupler temperature • LLRF module replacement (1) Other Faults • Loose connection on interlock crate (3 interventions, 14.0 h) • Loose cable on C4B2 main coupler bias (3 events, 4.8 h) SRF workshop 31/05/2018

  16. Antenna Problems • Duringtheconditioning in March 2017, thefieldlevelreading in C1B1 was roughly 10 dB lessthanexpected • Wrong tune andcouplerpositionwereruled out • Traced back to a problemwiththeantenna • Measuringthetransmissionbetween operational and spare antennashowedindeed 10 dB lesssignal on C1B1 than on othercavities • Presentlyoperating on the spare antenna, investigationsongoing SRF workshop 31/05/2018

  17. New since 2017: FullDetuning • Withthefull-detuning beam-loadingcompensationscheme, theflat top power consumptionwas reducedfrom 190 kW to 100 kW • Power required is independent on beam current; smooth operation 03/11/2017 Full detuning Expect 104 kW at 1.5 MV, QL=60k Estimated accuracy on power measurement ±20 % SRF workshop 31/05/2018

  18. Summary • The LHC RF system is working reliably throughout the years • Operation includes • Yearly recommissioning, from klystrons to LLRF • Fast follow-up of issues and problems • Continuous changes, improvements • Studies for the future • Huge amount of work performed also in 2017 to • Maintain the hardware • Commission new tools • Develop software for diagnostics and expert tools Thank you for your attention! SRF workshop 31/05/2018

More Related