An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Completion Report

  2. Project Summary Client: MTU Detroit Diesel Australia Contract No.: 1161873

  3. Project Overview • The generator package formed part of the CSBP initiated NAAN3 project which aimed to increase production in their Kwinana facility. • Aerison’s scope of supply included the following main components……… • Painted skid base with integral double skinned fuel tank (3500L) • Stainless steel acoustic enclosure • Inlet and outlet ventilation system • Removable roof • Roof mounted muffler • Fitting of free issue generator set and radiator to skid base • Full mechanical assembly of acoustic enclosure package

  4. Project Overview • Parties Involved • Primary Stakeholder: CSBP • EPCM: MTU Detroit Diesel Australia • Supply Contractor: Aerison • Aerison’s Scope • Design, fabricate, assemble & transport to site…… • One off acoustic diesel generator package with integrated fuel tank

  5. Project Overview

  6. Design

  7. Design • Aerison • Similar to units previously supplied • Double skinned tank changed in regards to previous designs to • incorporate double skin at sides also • Stainless steel panels • Removable roof • Semrad fuel control system

  8. Fabrication – In House • Base frame and tank • Structural frame work • Inlet ventilation system • Outlet ventilation system Base Frame

  9. Fabrication – In House Structural Framework Inlet / Outlet Ventilation System

  10. Fabrication – Sub Contractor • Stainless steel panels Cohesive • Stainless steel doors Cohesive • Flashing Cohesive • Muffler Universal • Weather louvreBradflow • Surface treatment RPC

  11. Fabrication – Sub Contractor Insulation Fit Out Complete Panels Door Trial Assembly

  12. Fabrication – Sub Contractor Muffler Elbow & Weather Cowl Weather Louvre

  13. Project Pictures-Complete Assembly Outlet End Inlet End Fuel Connections Exhaust Duct & Blankets

  14. Project Pictures-Complete Assembly Fuel Interface Genset Installation Genset Removable Roof

  15. Project Pictures-Complete Assembly CSBP Generator Package

  16. Project Summary Safety and Environment • Target – Nil Incident Actual – Nil Incident • Comments • Safety and environment record for project excellent • No reported incidents from sub contractors

  17. Project Summary Scope of Works • Target - Original Contract Scope of Works Total Number of SCN’s 4 • Total Approved 3 • Comments • Project completed on time • $10,260 in variations

  18. Project Summary Schedule

  19. Project Summary Schedule • Original Contract Delivery 31/01/2013 Actual Practical Completion – March 2013 • (Contractual obligations fulfilled – Extension due to external client issues) • Comments • Schedule extremely tight from the beginning • A lot of initiative and assisting of client required to keep the project on track

  20. Project Summary Budget and Margin

  21. Project Summary Budget and Margin • Original Contract Sum $189,200 Expected Final $199,460 • Original Contract Margin $37,925 (20%) Expected Final $15,698 (8%) • Comments • Over budget items were:- • Drafting (-$11,408) • Management (-$20,017) • Fabrication Labour (-$7,315) • Assembly Labour • Under budget items were:- • Materials ($1,700) • Panels and Doors ($8,156) • Variations

  22. Project Summary Quality • Target – Nil Quality Issues or NCR’s Actual – Nil • Comments • Internal fabrication checks • Sub contractor quality review documentation • Sub contractor external expections

  23. Issues Budget • Comments • Drafting • - Significantly underestimated (~$9,000 estimated / ~$20,000 used) • Workshop hours • - Underestimated in regards to ventilation inlet/outlet system • - 370 hours used in total (290 allocated to work shop – Additional 80 hours • allocated due to shortfall with inlet/outlet ventilation system) • Assembly hours • - 140 hours estimated • - 80 additional hours used • ~ 45 hours covered by variation • ~ 10 hours caused by direct work shop error • Management and Engineering • - Significantly underestimated (~$18,000 estimated / ~$38,000 used)

  24. Issues General • Subcontractors • - Subcontractors internal quality inspections poor • - Subcontractors external quality inspections not adequate • Drafting • - Missing detail led to additional work and time expended • Engineering • - Lack of consideration for a few assembly items (grid mesh / silencer • connection to radiator) • - Bolt take offs not efficient or correct • Management • - Greater control needed to be taken of design process at an earlier stage • - Due to the lack of document control and an organised process on the clients • side a lot of gentle persuasion and recording required to maintain forward • momentum of project while maintaining contractual obligations and cover.

  25. Project Summary Human Resources • Comments • Expeditor – Good • - Expediting very good where required • QA – Internal Good / External Poor • - All internal issues identified and rectified in at work shop stage • - Muffler quality and panel quality documentation poor • Engineering – Good (Needs to flow more from the start) • Document Control – Restricted due to no client document control • Safety – Excellent • Management – Good • - Management was required to be very tight due to lack of budget in critical • areas

  26. Project Summary Communications • Comments • Internal • Sub contractor • Client

  27. Project Summary Client Satisfaction • Client and CSBP happy to date with final product – Commissioning and noise test yet to take place

  28. Project Summary Lesson Learnt • Transport • Quality • Contract management • At source inspections

  29. Project Summary Project Completion • Unfinished Business • Comments • Thank You Letter • Bank Guarantees • Future Business or Related Projects • Aerison Procedures