1 / 12

COBRA Magnet

COBRA Magnet. Platform. Platform. 2002. 2003. 2004. 2005. Design. Winding & Cryo. Ass. Test. Deliv. PSI. Test. Field Measurement. Can only be made after beam line commissioning. Design. Winding & Cryo. Ass. Test. Deliv. PSI. Test. Mapping device.

larrywelch
Télécharger la présentation

COBRA Magnet

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COBRA Magnet Platform Platform 2002 2003 2004 2005 Design Winding & Cryo. Ass. Test Deliv. PSI Test Field Measurement Can only be made after beam line commissioning Design Winding & Cryo. Ass. Test Deliv. PSI Test Mapping device Calibration Final field mapping during shutdown Design Manufactoring Assembly Test Milestone

  2. Beam 2002 2003 2004 2005 Triplet I + II Studies Solenoid BTS New Separator Target Beam Line Commissioning Part 1 Part 2 Studies Triplet I + II Solenoid BTS New Separator Target Sep+BTS+COBRA COBRA+Target Platform Part 1 Pi beam? Beam Line Commissioning Prak. Gotta Gotta ? Design Manufactoring Assembly Test Milestone

  3. Drift Chamber 2002 2003 2004 2005 Full Prototype Beam test Medium Prototype Charge division & Cosmics Full Prototype Full Detector (18 DC) Medium Prototype Charge division & Cosmics COBRA inside Full Size Prototype outside Inside COBRA Full Prototype Full Detector (18 DC) Design Manufacturing Assembly Test Milestone

  4. Design Manufactoring Assembly Test Milestone Timing Counter 2002 2003 2004 2005 PMT Evaluation Beam Test PMT procur. APD Evaluation APD procur. APD test Design Procur & Manuf. Assembly PMT Evaluation Beam Test COBRA Test PMT procur. New APDs APD Evaluation APD procur. APD test APD procur. Design Procur & Manuf. Mechanical matching BG test Full installation

  5. Photon Detectorrealistic schedule 2002 2003 2004 2005 Crane problem Large Prototype Beam Test Beam Test Engineering runs Cryostat Vessel PMT Assembly Test Refrigerator Neutron background measurement Base circuit design must be finalized Liq. Purification Heater replaced Neutron Shield? Design Manufacturing Assembly Test Milestone

  6. Trigger 2002 2003 2004 2005 Prototype Board Final Prototype Full System Prototype Board Final Prototype Full System part. inst. full. inst. Design Manufactoring Assembly Test Milestone

  7. DRS (DAQ) 2002 2003 2004 2005 DRS1 Tests DRS2 2nd Prototype Boards & Chip Test DRS1 DRS2 DRS2 test board DRS3 Mass Production 400 chn 400 chn 3000 chn VME boards Full System installation Milestone Design Manufactoring Assembly Test

  8. Xenon Delivery “promised” Japan

  9. External Constraints Two non-MEG beam times in ’04/’05 + “Praktikum” Can turn on COBRA only on Wed. until fall ‘04 Beam Transport Solenoid and Separator not ready before ’05 Shutdown Internal Constraints “Exclusive” tasks: Drift Chamber – Timing Counter – Field Mapping – Beam Line Commissioning Schedule for different parts Combined Area Schedule Goal: Detector assembled before start of beam in 2006