1 / 9

Lessons Learned October 14 , 2014

Lessons Learned October 14 , 2014. St. John’s Regional Medical Center. Impact on St. Johns. Direct Hit Windows and Walls blown out Portions of roof pulled off Building infrastructure severely damaged Generators destroyed All communication lost

Télécharger la présentation

Lessons Learned October 14 , 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lessons Learned October 14, 2014

  2. St. John’s Regional Medical Center

  3. Impact on St. Johns • Direct Hit • Windows and Walls blown out • Portions of roof pulled off • Building infrastructure severely damaged • Generators destroyed • All communication lost • Water, sprinkler, gas and sewer pipes disrupted • Liquid O2 tanks damaged • Massive debris throughout building • 86 Medical Staff Member’s Offices destroyed or severely damaged

  4. Mercy Hospital Joplin • 100 Acre Site / 9 stories • 900,000 SF Hospital / Clinic • 200 beds with expansion to 260 beds • 39 months to design and build • 2,300 parking stalls • 15 OR's/Cath expandable to 20 • 32room Emergency Department • Emergency, Radiology and OR suite aligned • NICU, LDRP and C-Section on same floor • Cath labs, CVOR's, OR's and minor procedures in same suite • Flexible ICU / Med surgrooms • Dedicated elevators for decontamination and sterile to OR's

  5. Campus Aerial

  6. “Storm Hardened" Features • Concrete roofs vs. metal deck • Precast siding vs. EIFS • Concrete/Buried utility plant vs. outside • Utilities tunnel • Lowered levels below grade • Back up Centralized UPS on data • Safety windows standard/140mph/250mph vs. regular glass • Reinforced protected areas/stairs with battery lighting • Life safety equipment UPS • Equipment in hurricane hardened penthouses vs. exposed on roof • Redundant electric, water & fiber • Hurricane rated entrance doors

  7. Central Utility Plant • Completed April 2014

  8. Project Timeframes: Utility plant moved in April 2014 Lower level support moves in September 2014 Temporary occupancy of all areas January 2015 Final Occupancy permit February 2015 Training co-workers January 2015 - March 2015 Patient move March 22, 2015 Physician clinic move TBD Mercy Hospital Joplin

More Related