An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Project Planning CS169 Lecture 6 Prof. Aiken CS 169 Lecture 6

  2. Example: Denver Airport • Opening delayed entirely by software bugs in baggage handling system • After 9 month delay, admitted they did not know when the airport would open • Delay cost $1.1M/day • Initial development of baggage system $193M Prof. Aiken CS 169 Lecture 6

  3. Example: Air Traffic Control System • FAA contracted with IBM • IBM blamed for poor management • FAA blamed for altering requirements • Four part project • Two parts cancelled after $144M spent • Unreliable and over budget • Fourth part $1B over budget and 5 years late • And still not completed Prof. Aiken CS 169 Lecture 6

  4. IBM Survey of Distributed Systems • 55% of projects over budget • 68% over schedule • 88% had to be redesigned • Note: Distributed systems are harder than many other systems to build Prof. Aiken CS 169 Lecture 6

  5. Back To Reality • It’s hard, but we can’t ignore it • We still need to make plans . . . Prof. Aiken CS 169 Lecture 6

  6. Talent • What about programmer productivity? • Productivity differences of 10-1 to 100-1 • Some programmers simply much better than others • These differences can swamp all others • Especially in small teams Prof. Aiken CS 169 Lecture 6

  7. Recommendations for Planning Prof. Aiken CS 169 Lecture 6

  8. One Approach • Recommend one approach • Because I believe it is reasonably realistic • And widely practiced Prof. Aiken CS 169 Lecture 6

  9. Planning in Four Easy Parts • Break project into tasks • Requires a good design with good interfaces • Allows tasks to be correctly enumerated • Allows places for parallel development to be identified • Again, interfaces have to be right or unexpected dependencies will be discovered later! • Realism in estimating task length • Observable completion • Tasks are clearly done or not done • Prioritization Prof. Aiken CS 169 Lecture 6

  10. Plan from Design • Start with the design • Break project into tasks • Indivisible units of work for one person • Rules of thumb: • Nothing less than a day is a task • Anything more than a week is at least two tasks • Longer tasks harder to estimate • Need to think about how to break it into logical pieces Prof. Aiken CS 169 Lecture 6

  11. Dependency Graph • Write down dependencies for each task • What tasks already must have been done? • Build a dependency graph • Nodes are tasks: This is not right, see next viewgraph • Edge (A,B) if A must be completed before B Prof. Aiken CS 169 Lecture 6

  12. PERT chart (Program Evaluation and Review Technique) • Nodes: Milestones = Events • Edges: Tasks = Activities = Jobs • Edge weight: Task duration • If edge (u,v) enters vertex v and edge (v,x) leaves v, then task (u,v) must be performed prior to task (v,x). Prof. Aiken CS 169 Lecture 6

  13. Example Graph E Done D A I F C B H G Prof. Aiken CS 169 Lecture 6

  14. Estimating Time • Assign tasks to people • Individuals estimate time for their own tasks • They know their own abilities best • Genuine commitment to their own promises Prof. Aiken CS 169 Lecture 6

  15. Example Graph 2 days E 4 days Done 3 days D 1 day 4 days A I F 2 days 1 day C 2 days 3 days 5 days B 5 days H G 2 days Prof. Aiken CS 169 Lecture 6

  16. Example PERT chart for a DAJ project AS1 s2 50 Done cd 20 UCE1 V3 start V2 80 60 AS3 V1 30 UC1 AS2 AM1 10 s1 70 40 AM2 Prof. Aiken CS 169 Lecture 6

  17. Notes • Durations go on the edges, not the nodes • Some dependencies may be satisfied before a task is complete • Dummy Done node • Shows when everything is completed • Graph is useful for analysis • E.g., what is the critical path? Prof. Aiken CS 169 Lecture 6

  18. Critical Path 2 days E 4 days Done 3 days D 1 day 4 days A I F 2 days 1 day C 2 days 3 days 5 days B 5 days H G 2 days 19 days Prof. Aiken CS 169 Lecture 6

  19. Resources • Each task requires resources • Particular people • Money • Perhaps special hardware, etc. • Make sure these will be available • E.g., one person isn’t expected to be doing two tasks at the same point in the schedule Prof. Aiken CS 169 Lecture 6

  20. Fudge Factor • Scale estimated time by a fudge factor • Allows for the inevitable unexpected problems “I take the time estimated to complete all the tasks and double it.” - Silicon Valley VPE Prof. Aiken CS 169 Lecture 6

  21. Measuring Progress • Checking off tasks gives illusion of progress • Real progress only if task completion is observable • Bad • Task 1: 10% of feature, task 2: 20% of feature • What does 10% mean?! • Good • Task 1: All menus implemented and respond correctly to mouse clicks. Prof. Aiken CS 169 Lecture 6

  22. Measuring Progress: A Key Principle Move from working system to working system Prof. Aiken CS 169 Lecture 6

  23. Make the Plan a Sequence of Builds • Get the first build up as soon as possible • After that, always maintain a working system • System grows as tasks are checked off • Move from build to build Prof. Aiken CS 169 Lecture 6

  24. Why? • Can observe true progress • If nothing runs, hard to know if we are close to running • Makes changes in plan easier • Each build provides a natural point for changes • Allows priorities • Put most critical features in first build • If schedule slips, just don’t get to lower-priority builds late in the schedule Prof. Aiken CS 169 Lecture 6

  25. Builds Build 3 Build 1 Build 2 2 days E 4 days Done 3 days D 1 day 4 days A I F 2 days 1 day C 2 days 3 days 5 days B 5 days H G 2 days 19 days Prof. Aiken CS 169 Lecture 6

  26. Summary • Tasks are unit of work • But tasks need to make sense • Realistic duration, know when they are done • Group tasks into builds • Guarantees we aren’t completing lots of tasks without checking that everything works together! • Another form of false progress Prof. Aiken CS 169 Lecture 6