An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Filip Starzyński Łukasz Wilczyński Project Planning

  2. A project can be considered as consisting of several phases: DEFININGPLANNINGIMPLEMENTING COMPLETING Client’s needs; Work breakdown Doing or delegating; Deliver; Objectives; Specifications Monitoring; Wrap up; Strategy. ScheduleAdjusting. Evaluate; Budget Celebrate.

  3. Why is PP so important? With a good plan you can avoid most common reasons why projects collapse. Reasons like: • Time • Optimism • Human resources arrangement • No Full-Control

  4. PROJECT PARAMETERS or TRIPLE CONSTRAINTS: -> QUALITY -> TIME -> COST One of these will be the driver, the most important. Another will be the secondary constraint; The third will be the weak constraint. The driver needs to be carefully determined by asking the client questions.

  5. Project Planning STEPS: • Estimate the duration of each activity. • 2. Determine the sequence of activities and assign them.

  6. STEP ONE: • Estimate the duration of each activity. • WBS

  7. The WBS was initially developed by the U.S. Defence estabilishment, and it is described in Military Standard (MIL-STD) 881B (25 Mar 93): "A work breakdown structure is a product-oriented family tree composed of hardware, software, services, data and facilities .... [it] displays and defines the product(s) to be developed and/or produced and relates the elements of work to be accomplished to each other and to the end product(s)."

  8. What WBS really is? WORK BREAKDOWN STRUCTURE • Main idea is to divide the project into • smaller, managable parts • Many levels • Division types examples: • Lifecycles • Work types • Requirements

  9. Each part has to be: Manageable specific authority and responsibility assigned to each Independent minimum interfacing with and dependence on other tasks Integratable the total project is accounted for by the set of tasks Measurable results measured in terms of progress by completion of tasks.

  10. Some simple math: To = an optimistic estimate of how long the task will take Tp = a pessimistic estimate of how long the task will take Tm = the most probably estimate of how long the task will take Then determine the expected time Te (time expected) by using the following formula Te = (To + 4 Tm + Tp ) / 6

  11. Trap: • Don’t get TOO excited! • Why? • Partitioning your into micro-parts may: • Kill creativity • Kill your(PM) free time • When micro-planning is ok? • Lack of motivation • AI below avagare

  12. What next? • Pick One: • Gantt chart • PERT chart • CPA

  13. Gantt chart: The Gantt chart, developed by Charles Gantt in 1917, focuses on the sequence of tasks necessary for completion of the project at hand.Each task on a Gantt chart is represented as a single horizontal bar on an X-Y chart

  14. Task Possible start Length Type Dependent on... 1. High level analysis week 1 5 days sequential 2. Selection of hardware platform week 1 1 day sequential 1 3. Installation and commissioning of hardware week 3 2 weeks parallel 2 4. Detailed analysis of core modules week 1 2 weeks sequential 1 5. Detailed analysis of supporting utilities week 1 2 weeks sequential 4 6. Programming of core modules week 4 3 weeks sequential 4 7. Programming of supporting modules week 4 3 weeks sequential 5 8. Quality assurance of core modules week 5 1 week sequential 6 9. Quality assurance of supporting modules week 5 1 week sequential 7 10.Core module training week 7 1 day parallel 6 11.Development of accounting reporting week 6 1 week parallel 5 12.Development of management reporting week 6 1 week parallel 5 13.Development of management analysis week 6 2 weeks sequential 5 14.Detailed training week 7 1 week sequential 1-13 15.Documentation week 4 2 weeks parallel 13

  15. What is CPA? In 1957, DuPont developed the Critical Path Method (CPM) for managing shutting down chemical plants. • CPM provides the following benefits: • Provides a graphical view of the project. • Predicts the time required to complete the project. • Shows which activities are critical to maintaining the schedule and which are not.

  16. How to make CPA chart? 1. List all activities in the plan->earliest start date, ->estimated length of time it will take, -> is it parallel or sequential. If tasks are sequential, show which stage they depend on.

  17. Task Possible start Length Type Dependent on... 1. High level analysis week 1 5 days sequential 2. Selection of hardware platform week 1 1 day sequential 1 3. Installation and commissioning of hardware week 3 2 weeks parallel 2 4. Detailed analysis of core modules week 1 2 weeks sequential 1 5. Detailed analysis of supporting utilities week 1 2 weeks sequential 4 6. Programming of core modules week 4 3 weeks sequential 4 7. Programming of supporting modules week 4 3 weeks sequential 5 8. Quality assurance of core modules week 5 1 week sequential 6 9. Quality assurance of supporting modules week 5 1 week sequential 7 10.Core module training week 7 1 day parallel 6 11.Development of accounting reporting week 6 1 week parallel 5 12.Development of management reporting week 6 1 week parallel 5 13.Development of management analysis week 6 2 weeks sequential 5 14.Detailed training week 7 1 week sequential 1-13 15.Documentation week 4 2 weeks parallel 13

  18. 2. Plot the activities as a circle and arrow diagram CPM models the activities and events of a project as a network. Activities  nodes Events arcs or lines

  19. Identify the Critical Path The critical path is the longest-duration path through the network. The critical path can be identified bydetermining the following four parametersfor each activity: ES - earliest start time: EF - earliest finish time, LF - latest finish time: LS - latest start time,

  20. The critical path is the path through the project network in which none of the activities have slack, that is, the path for which ES=LS and EF=LF for all activities in the path. A delay in the critical path delays the project.

  21. What is PERT? The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. PERT was developed in the late 1950's for the U.S. Navy's Polaris project having thousands of contractors. It has the potential to reduce both the time and cost required to complete a project.

  22. PERT is a variation on Critical Path Analysis that takes a slightly more skeptical view of time estimates made for each project stage. To use it, estimate the shortest possible time each activity will take, the most likely length of time, and the longest time that might be taken if the activity takes longer than expected.

  23. Example of a PERT chart:

  24. Gantt Reloaded • Shows inter-relationships between activities • Can show the results of work at given time • Can assign roles to workers