KNOX COUNTY DIESEL EMISSIONS REDUCTION PROGRAM

KNOX COUNTY DIESEL EMISSIONS REDUCTION PROGRAM. Matt Donovan Environmental Specialist Knox County (TN) Department of Air Quality Management February 12 th , 2009. Project Overview. Entire county diesel fleet that qualifies for the grant will be retrofitted.

lola
Télécharger la présentation

KNOX COUNTY DIESEL EMISSIONS REDUCTION PROGRAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KNOX COUNTY DIESEL EMISSIONS REDUCTION PROGRAM Matt Donovan Environmental Specialist Knox County (TN) Department of Air Quality Management February 12th, 2009

  2. Project Overview • Entire county diesel fleet that qualifies for the grant will be retrofitted. • 27 on-road vehicles will receive diesel particulate filters (DPFs). • 26 off-road pieces of equipment will receive diesel particulate filters (DOCs). • Cost difference between ultra low sulfur diesel (ULSD) and low sulfur diesel (LSD) will be financed. • Total amount of federal funding: $163,815 • Knox County will pay for labor and for a DPF cleaning machine: counts as $23,056 match • Total project cost: $186,871

  3. First Actions- Before Grant RFP • Educated myself about the diesel emission reduction “world” • Southeast Diesel Collaborative (SEDC) events • EPA Region 4 Grant Workshops • Web research • Contacted fleet services to get info on diesel fleet • Advice: BEGIN IMMEDIATELY! • Used EPA Diesel Emissions Quantifier tool to know what info was important; saved lots of time and work • Web research to fill in info gaps; possible in-person visits • School buses left out because they are contracted • Other regional partners?

  4. First Actions- Before Grant RFP • Fleet information I collected: • Make • Model • Model Year • Engine Manufacturer • Engine Model • Engine Model Year • Horsepower • Annual Mileage • Annual Hours of Operation • Type of Fuel Used (i.e. biodiesel) • Annual Fuel Usage • Existing Emissions Control Device? • Engine Close to Rebuild? • Equipment Type (see Diesel Emissions Quantifier tool)

  5. First Actions- Before Grant RFP • Spoke to two emission control device manufacturers and received some broad budgetary numbers • Created a rough estimate of total project cost • Researched a few grant programs for possible local cost-matching requirements • Presented possible cost-matching dollar amounts to my superiors • *Important step! They need to know. • Spoke to fleet services department to gauge their ability or desire to install the equipment

  6. Preparing the RFP • First step: Looked at the evaluation criteria in the back of the RFP package. • Match? • Followed EPA’s advice to adhere closely to their requirements. • Studied two previous winning grant packages from other entities.

  7. Preparing the RFP • Two EPA requirements for the grant cut in half the number of vehicles that could be retrofitted in the Knox County fleet. • Medium duty or heavy duty trucks only • Only EPA or California Air Resources Board (CARB) verified equipment can be used. • Diesel fleet info critical for this step! • Diesel Emissions Quantifier consumed a large amount of time due to many types of vehicles and equipment • Don’t forget to account for a fuel change

  8. Preparing the RFP • Needed others’ expertise to complete certain sections • Final grant proposal reviewed by all stakeholders

  9. Current Status • All EPA agreements finalized at the end of last month • Just beginning the process of planning the bid package • September 31, 2010 completion date

  10. Questions? Have you started collecting fleet information yet??