1 / 39

Aggregate / Production Planning

Aggregate / Production Planning. Y.-H. Chen, Ph.D. International College Ming-Chuan University. Overview. Introduction Demand and Supply/Capacity Options Aggregate/Production Planning Techniques Master Production Schedule. Planning.

lonato
Télécharger la présentation

Aggregate / Production Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Aggregate / Production Planning Y.-H. Chen, Ph.D. International College Ming-Chuan University

  2. Overview • Introduction • Demand and Supply/Capacity Options • Aggregate/Production Planning Techniques • Master Production Schedule

  3. Planning Organizations make supply and capacity decisions on three levels.

  4. Aggregate/Production Planning • Why do we need it? • Time • Level of accuracy • What decisions are involved? • output rates • employment • inventory • back orders • subcontracting

  5. Aggregate/Production Planning • A “big picture” approach to planning. • Balance supply and demand by minimizing the production cost, adjustment cost, and opportunity cost of a system. • Concerned with the quantity and the timing of both the supply and demand.

  6. Long range Intermediate range Short range Now 2 months 1 Year Aggregate/Production Planning • A rolling planning horizon covers a time horizon of 2 to 18 months. • Special challenge comes from uneven demand within the planning horizon. • Example: Department store space allocation.

  7. Resources Workforce Facilities Demand forecast Policy statements Subcontracting Overtime Inventory levels Back orders Costs Inventory carrying Back orders Hiring/firing Overtime Inventory changes subcontracting Aggregate Planning Inputs

  8. Aggregate Planning Outputs • Total cost of a plan • Production/operation plan • Projected levels of • Inventory • Output • Employment • Subcontracting • Backordering

  9. Demand Options • Pricing: Influence demand pattern. • Problems: insufficient capacity and missing demand. • Examples: discount rates on hotels, airlines, movies, etc. • Promotion: Influence demand quantity. • Problems: worse than initial intention. • Back orders: Take orders in a period but deliver them later. • Problems: lost sales, disappointed customers, and paperwork. • New demand: Develop demand for a complementary product. • Examples: trips of schools, clubs, and seniors;fast food breakfast; landscaping during snow season.

  10. Capacity Options • Hire and layoff workers: union contracts, worker availability, worker morale, quality, and cost. • Recruitment, screening, training, severance pay, workforce realignment. • Overtime/slack time • Overtime: Seasonal demand, crew overtime, productivity, quality, accident, payroll. • Slack time: training, process improvement, problem solving. • Inventories: carrying, holding, insurance, obsolescence, deterioration, spoilage, breakage. • Part-time workers: skill set, union, benefit. • Subcontracting / outsourcing: skill set, availability, quality, cost, demand stability, confidentiality.

  11. Aggregate Planning Strategies • Level capacity strategy with inventories, overtime, part-time workers, subcontracting, and back orders. • Chase demand strategy with overtime, part-time workers, and subcontracting. • Use a combination of both strategies.

  12. Aggregate Planning Strategies

  13. Aggregate Planning Procedures • Determine demand for each period • Determine capacities for each period • Identify policies that are pertinent • Determine units costs • regular time, overtime, subcontracting, holding inventories, back orders, layoffs, and other relevant costs. • Develop alternative plans and compute costs • Select the best plan that satisfies objectives

  14. Aggregate Planning Example

  15. Aggregate Planning Example: Case 1 Case 1: Use a steady rate of output and use inventory to absorb the uneven demand but allowing some backlog. Assume there are 15 workers. Each worker has an output rate of 20 units per period. Start with zero inventory and determine an aggregate plan and its cost.

  16. Aggregate Planning Example: Case 1

  17. Aggregate Planning Example: Case 2 Case 2: After Case 1, planners learned that one worker is about to retire from the company. Rather than replacing that person, they would like to stay with the smaller workforce and use overtime to make up for the lost output. With the maximum amount of overtime output per period to be 40 units, develop a plan and compare it to Case 1

  18. Aggregate Planning Example: Case 2

  19. Aggregate Planning Example: Case 3 Case 3: Another option for Case 2 is to use temporary workers to fill in during months of high demand. Suppose that it costs an additional $100 to hire and train a temporary worker, and that a temporary worker can produce at the rate of 15 units per period (compared to 20 units per period for regular workers). Develop a plan and compare it to Case 1 and Case 2.

  20. Aggregate Planning Example: Case 3

  21. Aggregate Planning Techniques • Graphical / Charting • Linear Programming • Linear Decision Rule • Simulation

  22. Cumulative output/demand Cumulative production Cumulative demand 6 7 1 2 3 4 5 8 9 10 Graphical / Charting

  23. Linear Programming • Goal: minimize the sum of costs related to regular labor time, overtime, subcontracting, inventory holding costs, and costs associated with changing the size of the workforce. • Constraints: capacities of the workforce, inventories, and subcontracting. • Limitations • linear relationships among variables • inability to continuously adjust output rates • single objective

  24. Linear Programming

  25. Linear Programming Example Given the following information, set up the problem in a transportation table:

  26. Linear Programming Formulation

  27. Linear Decision Rule and Simulation • Linear Decision Rule • Minimized combined costs using a set of cost-approximating functions to obtain a single quadratic equation. • Limitations: • A specific type of cost function is assumed. • Considerable effort needed to obtain relevant cost data and develop cost functions for each organization. • Solutions may be unfeasible. • Simulation Models • Develop and test computer models under different scenarios to identify acceptable solutions to problems. Examples: grocery checkouts, banking.

  28. Summary of Planning Techniques

  29. Aggregate Planning in Services • Services occur when they are rendered. • Inventory may not apply to services. • Demand for service can be difficult to predict. • Some customers request prompt service or go elsewhere, if there is a waiting line. • Capacity availability can be difficult to predict. • Depend on skills details required. • Labor flexibility can be an advantage in services. • Can handle wide variety of service requirements.

  30. Disaggregation Breaking the aggregate plan into specific product requirements in order to determine • labor requirements (skills, size of work force), • materials, and • inventory requirements.

  31. Disaggregation Example

  32. Disaggregation • Master schedule • Result of disaggregating an aggregate plan • Show quantity, timing, and orders of specific end items for a scheduled horizon. • Shorter time horizon. • Planned unit may be different. • Rough-cut capacity planning: Approximate balancing of capacity and demand to test the feasibility of a master schedule. • Production, warehouse facilities, labor, vendors, and raw materials.

  33. Inputs Outputs Beginning inventory Projected inventory Master Scheduling Forecast Master production schedule Customer orders Uncommitted inventory Master Production Schedule (MPS) Indicate the quantity and timing of planned production, taking into account desired delivery quantity and timing as well as on-hand inventory. (what, when, how much)

  34. MPS Example • A company that makes industrial pumps wants to prepare a master production schedule for June and July. • Marketing has forecasted demand of 120 pumps for June and 160 pumps for July. • By evenly distributing over the four weeks in each month, we have 30 per week in June and 40 per week in July. • Now, suppose that there are currently 64 pumps in inventory and there are customer orders that have been committed and must be filled. These inputs result in the following table. • Production batch size is 70 units.

  35. MPS Example: Step 1 If no production is planed, projected inventory becomes negative from week 3. This is a signal that production is needed to replenish inventory.

  36. MPS Example: Step 2

  37. MPS Example: Step 2

  38. MPS Example: Step 3

  39. Period frozen firm full open Time Fences in MPS

More Related