270 likes | 391 Vues
The Regional Planning Group, led by Warren Lasher, is conducting a Long-Term System Assessment to inform near-term planning while addressing long-range system needs. This study focuses on long-lead-time and large projects that can solve immediate issues and ensure future reliability. Key areas of analysis include economic evaluations, contingency assessments, and capacity evaluations under peak load conditions across various regions. A comprehensive report will be submitted by the end of 2008, aiding in the selection of alternatives for congestion and reliability solutions.
E N D
Long-Term System AssessmentProject Update Warren Lasher Manager, System Assessment Regional Planning Group
Purpose • To Inform Near-Term Planning with Potential Solutions that Meet Long-Range System Needs • Intent is not to select new circuits to recommend • Rather, the intent is to provide a selection of alternatives through scenario analysis that can be considered when developing solutions for near-term congestion or reliability needs Regional Planning Group
Specific Focus • The focus of this study is to look for: • Long-Lead-Time Projects – projects that may require 5 or more years to bring on-line • Large Projects – projects that both solve short-term issues but also meet long-term system needs. Regional Planning Group
Scope • Study Year: 2018 • All generation currently on-line (and expected to maintain operation) plus all units with signed IAs as of 7/1/2008 • Base Case will include the CREZ Scenario 2 (selected by PUCT on 7/17/08) • Generation Expansion – by scenario • Gas price – by scenario • Emissions allowance prices – by scenario • A report will be submitted to PUCT by end of 2008 • Analysis will continue next year Regional Planning Group
Methodology • Study Consists of Two Components • Evaluation of Regional System Needs • A/C contingency steady-state analysis • SC-UC Model Development • Evaluation of Economic Projects Regional Planning Group
A/C Contingency Analysis • Evaluated Five Areas • Northeast Region • Houston • South-Central • Valley • Using different local generation dispatches, evaluated the reliability needs of these areas under increasing amounts of import • Looked for thermal limit and voltage violations under contingency, primarily on the 345-kV network • Did not evaluate transient stability limits Regional Planning Group
A/C Contingency Analysis Example: Northeast Region Under peak load conditions, generation availability was reduced by up to 2,800 MW to determine import constraints (resulting in a net import of 2,550 MW) Regional Planning Group
A/C Contingency Analysis • Example: Houston Region Under peak load conditions, generation availability was reduced by up to 1,100 MW to determine import constraints (resulting in a net import of 6,760 MW) Regional Planning Group
A/C Contingency Analysis • Example: South-Central Region Under peak load conditions, generation availability was reduced by up to 1,900 MW to determine import constraints Regional Planning Group
A/C Contingency Analysis • Example: Valley Region Under peak load conditions, generation availability was reduced by up to 1,000 MW to determine import constraints (resulting in an import of 2,700 MW) Regional Planning Group
A/C Contingency Analysis • Results: • No reliability need for additional import capacity in the Northeast and South-Central Regions • At high levels of unavailable generation, import restrictions are noted in these areas • A new import pathway into Houston will be required by the summer peak season of 2018 • Current connections to the Valley region appear to be adequate although imports over existing interconnections with CFE may be required Regional Planning Group
SC-UC Analysis • In order to build a 2018 model for economic analysis, small load-serving projects had to be added to the SCUC base-case model • Projects required to reliably serve load • Analyzing 8,760 hours using DC loadflows • These projects are not in the base-case, which is built off of the last year of the latest 5-Year Plan • In areas where several of these projects were required, a more cost-effective solution might be to build one larger (345-kV) project, rather than several smaller 138-kV upgrades Regional Planning Group
SC-UC Analysis • Based on this analysis, four areas were selected for further analysis: • Houston Import • Western Williamson County • West of Waco • North of Dallas (Cooke and Grayson County) • In addition, these areas were reviewed for reliability needs: • Brenham Area • Columbus Area Regional Planning Group
Options for Houston Import • The following options were evaluated for new pathways into the Houston area: • Fayette to Zenith • Salem to Zenith • Lufkin to Canal • Hillje to Parish, O’Brien or Zenith • Choice may depend on future base-load generation additions • Options further evaluated in the analysis of economic projects Regional Planning Group
North Dallas Area • Area around Cooke and Grayson Counties (north of Dallas near the Oklahoma border) • Load growth may stress existing 138-kV service • 345-kV Option: Tap into the CREZ line connecting Oklaunion and West Krum, and build a new 345-kV right-of-way to the Valley substation. Potential new 345-kV substations at the Payne and Valley View substations with 345-kV/138-kV autos. Regional Planning Group
West Waco Area • Area west of Waco, in McLennan, Coryell, and Bosque County • Again, limited 345-kV service in this area • 345-kV Option: New 345-kV right of way from Comanche Peak, south to the new Newton substation included in the CREZ plan. This would allow a new connection(s) into this area from the west. This option provided significant economic benefits if additional nuclear generation is developed at Comanche Peak. Regional Planning Group
Western Williamson County • Load growth around Leander up to Lampasas will require several 138-kV upgrades • Flow is generally from 345-kV lines in the east and southeast • Potential solution: • New 345-kV substation at Lampasas, connecting to the CREZ line from Gillespie to Newton • Upgrade the 138-kV circuits from Lampasas to Burnet13 • New 138-kV right-of-way from Burnet13 to Leander Regional Planning Group
Other Areas • The Brenham area is generally served radially from the Fayette to the Salem substations. Options were evaluated to provide network service for the Salem substation, including new right-of-way from Salem to Zenith, or from Salem to Sandow. These solutions were generally not cost-effective. • There is congestion in the Columbus area due to flows on the 69-kV system. One possible solution would be to convert some of the 69-kV circuits to 138-kV. This solution appears to be effective in eliminating congestion in the base-case, but with added base-load generation to the south (such as new nuclear units at STP or Victoria), a better solution may be to break the 69-kV system, reinforce the two ends and add reactive support. Regional Planning Group
Economic Analysis • Using Scenario Analysis, evaluate projects that increase system efficiency under potential future conditions. Scenarios include: • Additional Nuclear Generation (3 units, 6 units) • Natural Gas Prices ($7, $11, $15/MMBtu) with Coal Gasification/IGCC • Carbon Constraints (Up to $100/ton) • Changes in Load Shape (Plug-In Hybrids, Energy Storage) • Additional Renewable Generation (Wind, Solar) Regional Planning Group
Economic Analysis – Generation Expansion • Generation development will be driven by profit expectations. • Bus-bar analysis shows type of generation options that will be most cost-effective. Regional Planning Group
Economic Analysis – Generation Expansion • Impact of Carbon Tax shown on this chart. Regional Planning Group
Economic Analysis – Generation Expansion • ERCOT system has a significant amount of intermediate generation Regional Planning Group
Economic Analysis – Generation Expansion • At gas prices of $11/MMBtu or $15/MMBtu, additional base-load generation will likely be profitable. • Additional generation expansion, to meet 12.5% target reserve margin, will likely come from quick-start combustion turbines or very flexible combined-cycle plants. • Hourly marginal cost unit-commitment models will often underestimate the benefits from quick-start combustion turbines • Ancillary services (Non-spin) • Short-term price spikes Regional Planning Group
Economic Analysis – General Observations • Evaluating two levels of nuclear and coal (IGCC) expansion indicates that economic projects were generally not cost-effective unless they were specifically designed for scenario generation expansion (except in certain scenarios) • Backbone projects (such as 765-kV Navarro to Hillje, and Fayette to Zenith) were generally not cost-effective unless new generation was directly connected to the backbone • Carbon constraints did not significantly alter the locations of system congestion, although they change the congestion costs and likely generation expansion options Regional Planning Group
Economic Analysis – General Observations • No large projects in ERCOT between Dallas and Houston were found that were economically justified due to presence of CREZ wind. Import pathway into Houston from the west was cost-effective. • Analysis of up to 2,000 MW of solar generation in the McCamey area indicates limited increase in curtailment to wind or solar projects • Analysis of conventional Compressed Air Energy Storage indicates that 2,000 MW of CAES capacity can increase wind generation by 830 GWh (reducing wind generation curtailment by 1%); production costs reduced by $10 million Regional Planning Group
Conclusions • Reliability analysis indicates a need for additional import pathway into Houston area by 2018. Selection of most cost-effective solution will likely depend on generation expansion. • Options have been presented for additional reliability projects north of Dallas, near Waco, and north of Austin • Scenario analysis indicates that cost-effectiveness of economic projects depends heavily on locations of future generation development • Long-term analysis will continue in the new year: • CREZ implementation • > 10 year analysis Regional Planning Group
Questions? Regional Planning Group