Project Scheduling Problems

Project Scheduling Problems. Paul Sorenson Department of Computing Science University of Alberta. CMPUT 401 Software Engineering. What is a Schedule?. That part of the plan that deals with - milestones - deliverables - resources

mariavick
Télécharger la présentation

Project Scheduling Problems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Scheduling Problems Paul Sorenson Department of Computing Science University of Alberta CMPUT 401 Software Engineering CMPUT 401 - Project Scheduling Problems

  2. What is a Schedule? • That part of the plan that deals with - milestones - deliverables - resources • Success of project is often judged on how well you stay to the schedule as opposed to how well you are executing the plan. CMPUT 401 - Project Scheduling Problems

  3. Bad Schedules • Microsoft Word for Windows 1.0 • 5 years to develop, 660 person-months, 249 KLOC Report Estimated Estimated Actual Days Relative Date Ship Date Days to Ship to Ship Error Sep-84 Sep-85 365 1887 81% Jun-85 Jul-86 395 1664 76% Jan-86 Nov-86 304 1400 78% Jun-86 May-87 334 1245 73% ………….. Jun-89 Sep-89 92 153 40% Jul-89 Oct-89 92 123 25% Aug-89 Nov-89 92 92 0% CMPUT 401 - Project Scheduling Problems

  4. Causes of Overly Optimistic Schedules • external, immovable deadline (Y2K, Christmas, tax time) • managers only accept “best case” estimate • deliberately underestimated to get a “winning bid” • interesting project and developers want to do it even if under-funded • workers are more effective if “under the gun a little” • project is simply poorly estimated • managers/developers want a challenge • project begins realistically but new features are piled on and before long the schedule becomes overly optimistic CMPUT 401 - Project Scheduling Problems

  5. More Schedule Slips More Stress More Mistakes Beating Schedule Pressure • McConnell says “you can’t solve a problem using Rapid Development until you know how to handle schedule pressure schedule pressure More CMPUT 401 - Project Scheduling Problems

  6. Beating Schedule Pressure • Three factors that make up bulk of problems associated with optimistic schedules: • Wishful thinking • Ignorance • Poor negotiation skills Principled Negotiation - separate the people from the problems - focus on interests, not positions - invent options of mutual benefit - insist on using objective criteria CMPUT 401 - Project Scheduling Problems

  7. Inventing Options for Mutual Gain Product Options • move some desired functionality to the next version • deliver the product in stages (e.g, ver 0.7, 0.8, 0.9, 1.0) • cut features altogether • polish some features less • relax detailed requirements for some features until later Project Resources • add more developers, if it’s early in the schedule • add higher-output developers (e.g., subject-area experts) • add more testers • add more admin support (e.g., project documentation & tracking) • improve developer support environment (e.g., offices, coke machine) • increase level of end-user involvement and executive commitment CMPUT 401 - Project Scheduling Problems

  8. Inventing Options for Mutual Gain Project Schedule Options • set a schedule goal but no an ultimate project deadline until product design is done (or at least requirements defn.) • if it’s early in the project, agree to reduce development time as you refine product specifications and design • agree to use estimation ranges and to refine these as the project progresses Politically Charged Options (to be used only if you know who you are negotiating with) • provide exceptional support so developers can focus more easily on development task - shopping service, catered meals, limo • provide increased motivational perks - paid overtime, all expense paid trip to Hawaii, profit sharing CMPUT 401 - Project Scheduling Problems