Project Scheduling

Project Scheduling. Critical Path Method Based on material from Chapter 6 of Project Management and Teamwork , by Karl Smith. How do you schedule complex projects?. Make a list of things to do? Use an outline? Draw a concept map? Focus on those things we know how to do first?

quinto
Télécharger la présentation

Project Scheduling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Scheduling Critical Path Method Based on material from Chapter 6 of Project Management and Teamwork, by Karl Smith

  2. How do you schedule complex projects? • Make a list of things to do? • Use an outline? • Draw a concept map? • Focus on those things we know how to do first? • Use project management software?

  3. Dinner & ConcertHow much time do you need to prepare and consume the meal? • Menu consists of soup and baked chicken • Soup must be boiled 35 minutes and will allow 15 minutes to serve and consume • Chicken dish requires 30 minutes to boil rice, 15 minutes to brown chicken in frying pan, 15 minutes to bake rice and chicken in baking dish • Sauce takes 5 minutes to prepare in frying pan and 15 minutes to boil peas • Only have two pots and one frying pan • Wine takes 5 minutes to uncork and 30 minutes to let breath before serving • Allow 25 minutes to serve and consume entrée and wine

  4. Meal Planning ExerciseWork Breakdown Structure Boil Soup (Pot 1) Eat Soup (Pot 1) Eat Entree Boil Peas (Pot 2) Boil Rice (Pot 2) Bake Entree Brown Chicken (Fry Pan) Prepare Sauce (Fry Pan) Activity Name (Resource) Open Wine Wine Breathes

  5. Critical Path Method • Work breakdown structure ok for simple task with few activities • When number of task large, a systematic solution is to use the Critical Path Method (CPM) • to use CPM must know the duration of each activity and the predecessors of each

  6. CPM - Forward Pass Early Start (ES) - Earliest time that each activity can start - obtained by adding the earliest start of its latest starting predecessor to the that predecessor’s duration - when two or more activities must be competed before the next one can start, then the maximum must be used Early Finish (EF) - Determined by summing the early start (ES) and duration

  7. Meal Planning ExerciseCritical Path Method - Forward Pass 35 50 0 35 Boil Soup 35 Eat Soup 15 50 75 Eat Entree 25 30 45 Boil Peas 15 0 30 30 45 Boil Rice 30 Bake Entree 15 0 15 15 20 Brown Chicken 15 Prepare Sauce 5 0 5 5 35 ES EF Open Wine 5 Wine Breathes 30 Activity Name duration

  8. CPM - Backward Pass Late Start (LS) - Latest possible starting time that each activity can have - calculated as the earliest starting successor, less the duration of the activity under consideration Late Finish (LF) - The resulting finish time based on late start (LS)

  9. Meal Planning ExerciseCritical Path Method - Backward Pass 35 50 0 35 Boil Soup 35 Eat Soup 15 35 50 50 75 0 35 Eat Entree 25 30 45 50 75 Boil Peas 15 0 30 30 45 35 50 Boil Rice 30 Bake Entree 15 5 35 35 50 0 15 15 20 Brown Chicken 15 Prepare Sauce 5 15 30 30 35 0 5 5 35 ES EF Open Wine 5 Wine Breathes 30 Activity Name duration 15 20 20 50 LS LF

  10. CPM - Critical Path & Floats Critical Path - The path for which activities cannot be delayed - activities on critical path will have equal earliest and latest times and are call critical Floats - The amount the termination of an activity can be delayed before delaying a successor is called free float(FF). FFi = (ESi+1) min - ESi - Di The amount of slack an activity has before it would cause the path on which it lies to become critical is called the total float(TF). TFi = LFi - EFi

  11. Meal Planning Exercise Critical Path 35 50 0 35 Boil Soup 35 Eat Soup 15 35 50 50 75 0 35 Eat Entree 25 30 45 50 75 Boil Peas 15 0 30 30 45 35 50 Boil Rice 30 Bake Entree 15 15 35 35 50 0 15 15 20 Brown Chicken 15 Prepare Sauce 5 FF = 50 - 30 - 15 = 5 15 30 30 35 0 5 5 35 ES EF Open Wine 5 Wine Breathes 30 Activity Name duration 15 20 20 50 LS LF

  12. CritPath Programhttp://www.ce.umn.edu/~smith • Allows easy entry of activites • Provides critical path calculations (ES, EF, LS, LF, Float) and algorithm stepper • Calculates critical path • Gives associated Gantt Chart - a time-scaled network (Gantt Chart does not show interdependence)