Bridge Owners’ Forum Code of Practice for Bridge Management Research Opportunities

Bridge Owners’ Forum Code of Practice for Bridge Management Research Opportunities. Graham Cole. s. Contents of Presentation. Bridge Management Influences Code of Practice for The Management of Highway Structures. Implementation of the Recommendations. Review of Progress.

mckile
Télécharger la présentation

Bridge Owners’ Forum Code of Practice for Bridge Management Research Opportunities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bridge Owners’ ForumCode of Practice for Bridge ManagementResearch Opportunities Graham Cole s

  2. Contents of Presentation • Bridge Management Influences • Code of Practice for The Management of Highway Structures. • Implementation of the Recommendations. • Review of Progress. • Research Opportunities.

  3. Bridge Management Influences Asset Valuation Asset Management Planning Code of Practice Performance Measures

  4. The Code

  5. Code of Practice for the Management of Highway Structures plus research initiatives The Asset Management Rainbow… We know what we have got. We know what it is worth. We know what condition it is in. We know what condition it should be in. We know the optimal way to close the performance gap. We know our long term forward programme. We know that we will be able to secure the necessary funding. We know that we have a BMS to manage the data.

  6. Contents • Foreword • Executive Summary • Introduction • Management Context • Asset Management Planning • Financial Planning and Resource Accounting • Maintenance Planning And Management • Inspection, Testing And Monitoring • Assessment Of Structures • Management Of Abnormal Loads • Asset Information Management • 10. Framework for a Bridge Management System • 11. Implementation of the Code The Code 2. Management Context

  7. ENGINEERING PROCESSES SHORT TERM PLANNING LONG TERM PLANNING 2. Management Context 6. Inspection, Testing and Monitoring 3. Asset Management Planning 5. Maintenance Planning and Management 7. Assessment of Structures 4. Financial Planning and Resource Accounting 8. Management of Abnormal Loads 9. Asset Information Management 10. Framework for a Bridge Management System

  8. Implementation

  9. Implementation • There is a statutory obligation on highway authorities to maintain the public highway (Highways Act, 1980) • Safe for Use requires a highway structure to be managed in such a way that it does not pose an unacceptable risk to public safety (31). • Milestone One – March 2006. • Fit for Purpose requires a highway structure to be managed in such a way that it remains available for use by traffic permitted for the route (32). • Milestone Two – March 2007.

  10. Implementation Good Management Practice (17) • Customer focused asset management approach. • Deliver required Levels of Service. • Minimise whole life costs. • Make optimum use of resources. • Provide a sustainable programme of work • Milestone Three – March 2008 to March 2010

  11. Review of Progress

  12. Review of Progress • CSS Bridge Management System Survey • CSS Code of Practice Implementation Survey.

  13. We comply with Milestone One, with only a few gaps left to be filled. We partially comply with Milestone Two. We do not comply with Milestone Three. No idea until I study Code of Practice. (Not familiar with this document as yet!) We have a lot of what is recommended in place at the moment. We are just completing our first attempt at a transportation asset management plan, and we will now begin to look at the areas where we have gaps in our data and management systems e.g. valuation, prediction models, whole life costing and some aspects of performance monitoring. We are currently working with SERCO regarding abnormal load vetting using ESDAL and so will be interested to see how their system develops in 2006.

  14. Review of Progress Average Rating Ratings < 2 Milestone None 4.09 One 10 3.21 Two 7 2.94 Three The need has been recognised and a plan for implementation is currently being developed.

  15. Milestone 3 • 2. Management Context 3.67 • 3. Asset Management Planning 2 • 4. Financial Planning 3 • 5. Maintenance Planning 2.75 • 6. Inspection, Testing & Monitoring 4

  16. Milestone 3 • 7. Assessment of Structures 4 • 8. Management of Abnormal Loads 2 • 9. Asset Information Management 3 • 10. Framework for a Bridge Management System 1

  17. ENGINEERING PROCESSES SHORT TERM PLANNING LONG TERM PLANNING 2. Management Context 6. Inspection, Testing and Monitoring 3. Asset Management Planning 5. Maintenance Planning and Management 7. Assessment of Structures 4. Financial Planning and Resource Accounting 8. Management of Abnormal Loads 9. Asset Information Management 10. Framework for a Bridge Management System

  18. Research Opportunities

  19. Research Opportunities • Establish a regime for the asset valuation of highway structures in accordance with the CSS document • Develop and implement components of the AM Regime needed to deliver the Advanced AM Planning process for highway structures • Develop and implement lifecycle plans for all groups and sub-groups of highway structures

  20. Contents • Foreword • Executive Summary • Introduction • Management Context • Asset Management Planning • Financial Planning and Resource Accounting • Maintenance Planning And Management • Inspection, Testing And Monitoring • Assessment Of Structures • Management Of Abnormal Loads • Asset Information Management • 10. Framework for a Bridge Management System • 11. Implementation of the Code The Code 3. Asset Management Planning

  21. Excellent Good Fair Poor Critical Failed = Maintenance Costs = Total Costs = Capital Costs = User Costs Finding the Right Level of Funding Costs Condition Index

  22. Contents • Foreword • Executive Summary • Introduction • Management Context • Asset Management Planning • Financial Planning and Resource Accounting • Maintenance Planning And Management • Inspection, Testing And Monitoring • Assessment Of Structures • Management Of Abnormal Loads • Asset Information Management • 10. Framework for a Bridge Management System • 11. Implementation of the Code The Code 4. Financial Planning

  23. Valuation • Whole of Government Accounts • Gross Replacement Cost • Dimension x unit rate • Depreciation • Condition related • Asset Valuation

  24. Valuation

  25. Contents • Foreword • Executive Summary • Introduction • Management Context • Asset Management Planning • Financial Planning and Resource Accounting • Maintenance Planning And Management • Inspection, Testing And Monitoring • Assessment Of Structures • Management Of Abnormal Loads • Asset Information Management • 10. Framework for a Bridge Management System • 11. Implementation of the Code The Code 5. Maintenance Planning

  26. Lifecycle Plans

  27. How will the structure deteriorate from here? Structure Condition Metal Bridge Concrete Bridge Masonry Bridge Time

  28. Summary • Engineering Processes are Satisfactory • ESDAL for Management of Abnormal Loads • Existing Decision Support Tool for BMS • Lifecycle Plans • Depreciation • Levels of Service for Highway Structures • Highway Structures Asset Management Planning

  29. Thank You