PIP Schedule Summary

PIP Schedule Summary. February 7, 2012 ELMIE Peoples- evans. Schedule Highlights. Roll-up at level 4 of WBS PIP Start – 10/3/2011 PIP Finish – 12/15/2016 Total M&S - $44.63M Total FTEs – 182 SSU Complete 7/15/2013 Based on funding profile Schedule baselined 1/31/2012

mele
Télécharger la présentation

PIP Schedule Summary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Schedule Summary February 7, 2012 ELMIE Peoples-evans

  2. Schedule Highlights • Roll-up at level 4 of WBS • PIP Start – 10/3/2011 • PIP Finish – 12/15/2016 • Total M&S - $44.63M • Total FTEs – 182 • SSU Complete 7/15/2013 • Based on funding profile • Schedule baselined 1/31/2012 • M&S Total includes overhead

  3. Linac Details - Cost

  4. Linac Details - Labor Comments: Labor for HLRF in the outer years still needs to be flushed out. Current schedule assumes klystron option selected.

  5. Booster Details – Cost

  6. Booster Details - Labor

  7. What’s Next??? • Status the schedule. • Why? Track progress and labor effort. Want to ensure PIP receiving all the labor it needs to meet the schedule goals/milestones. Help L3/L4 managers see discrepancies in current schedule estimates. • How? Status/turn-around reports will be used to update current/future tasks as laid out in the schedule. • Who? The L3/L4 managers update tasks in status report. The L2 managers verify and I update the schedule. • When? Want to start ASAP. How often we update is open for debate. Proposals are weekly, bi-weekly or monthly. • Update full schedule. • Why? To uncover details that weren’t thought of before. • When? April? • Who? All. • How? Individual meetings, yes, again. • Track Schedule/Progress Schedule

  8. Summary We have a baseline schedule (reference point). Be prepared to fill out/submit status reports on a regular basis (up to you how often). Full schedule review after a few status updates performed to help recognize true issues in current schedule estimates, then real baseline. We will try to present schedule updates on a monthly basis at these meetings. STATUS REPORTS ARE MANDATORY!!!