40 likes | 181 Vues
On April 4, 2012, the PIP meeting discussed several critical updates regarding the project, including recent progress on the L13 Absorber and the status of various RFQ issues. Key updates included the reconnection of the RFQ and preparation for upcoming beam conditioning, with a scheduled long shutdown just four weeks away. The meeting also highlighted ongoing studies and discussions about beam operations in early May, with budget updates to be presented in management discussions. A focus on ensuring progress in cavity work and future scheduling was emphasized.
E N D
PIP Wednesday April 4th ,2012
4/4/12 Agenda • Project Update(s) Pellico - PIP Status Talk(s) • SalahChaurize: Review of the L13 Absorber and Recent Progress
Updates - • RFQ/LEBT • RFQ energy issue continues – Spectrometer Measurement Next Week • RFQ reconnected – starting to recondition and run beam • New Buncher being conditioned • Long Shutdown just 4 weeks away! • Lots of PIP related studies underway • Phase Lock • Cogging Tests • Transverse Beam measurements (single BPM data analysis) • Another SS cavity (cavity 8 re-installed) will not happen • Work continues on RLS/Tracking of effort • Elmiesent out “a slightly-revised report template” for the schedule update worksheet • This is for past two months • Will now show budget numbers for tasks….. • Will be used in discussion with lab management to show progress and what we need (ieCavity Work) • Discussions of Shutdown Work/Beam Studies • Proton Source Shutdown Schedule Meeting Today (14:30 in Dungen) • Discussion of beam operations during first couple of weeks in May - underway
Talks • SalahChaurize: Review of the L13 Absorber and Recent Progress