1 / 11

“Remediation of Historically Polluted Areas in S arkandau g ava”

“Remediation of Historically Polluted Areas in S arkandau g ava”. Progress from April 201 3 till March 201 4. Topics of Presentation. The territories of the Project Project Budget Progress - Site I and Site II Progress - Site I I I

michaelf
Télécharger la présentation

“Remediation of Historically Polluted Areas in S arkandau g ava”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “Remediation of Historically Polluted Areas in Sarkandaugava” Progress from April 2013 till March 2014

  2. Topics of Presentation • The territories of the Project • Project Budget • Progress - Site I and Site II • Progress - Site III • Proposal for 2nd TrancheFactors impacted Project implementation • Publicity and Swissness

  3. The territories of the Project • Site I (2,6 ha) - territory of “WOODISON TERMINAL” Ltd, “Ovi” Ltd and “Eko Osta” Ltd • Site II (2,9 ha) - territory of “VL Bunkerings” Ltd • Site III (2,5 ha)- territory of “OVI Riga” Ltd

  4. Project budget according to actual Project Proposal (November, 2013) Project Budget

  5. Till June, 2013 technical design for pilotproject accomplished In July, 2013 construction permit received, pilotprojectconstruction works done, technological equipment supplied and installed Till December, 2013 pilotproject works were done In December report about pilotproject was received by Contractor On 28th December Engineer approved submitted pilot stage final report and recommended to continue the preparation for the further implementation of the remediation project According to agreement and FIDIC regulations construction supervision was performed all period Till March, 2014 remediation work technical design accomplished Progress - Site I and Site II

  6. Prepared Project Proposal amendments according works in Site III (Ovi Riga Ltd territory) On 13th November the amendments nr.1 for individual project CH05 were signed On 13th November there was signed an agreement with "PB Inženiertehniskais birojs" Ltd about the project procurement documentation development for works in Site III In February there was announced procurement for remediation works and in 10th May there was announced winner. Period of possible complaints ends on 20th May In March there was announced procurement for remediation work supervision and in 29th April there was announced winner. No complaints were received Progress - Site III

  7. Alternative proposal for 2nd Tranche Additional researches and pilotprojects in Sarkandaugava and Vecmilgravis polluted areas

  8. Factors impacted Project implementation • Procurement for remediation works in Site I and II is closed tender • Complain about procurement for remediation works in Site I and II was submitted by participant which was rejected in first phase • It is planned that remediation work agreement for Site III will be signed till June, 2014

  9. Publicity and Swissness • There was TV story in Swiss TV about the Project • In April, 2013 – Swiss Environmental Engineering students visited the Project site • Publications made in SES’s and MoEPRD web page • Swiss expert provided consultations about procurement documentation of remediation works

  10. Thank You for attention! Contact informationKlāvs BrangulisState Environmental ServiceE‐mail: klavs.brangulis@vvd.gov.lv

More Related