An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CapX 2020 Transmission Plan: Ensuring Reliable Electricity CapX 2020 - 9/15/2014

  2. Need for Reliable Electricity • Projected Population Growth: 1.3 million by 2050 • www.demography.state.mn.us • Projected Job Growth: 500,000 new jobs by 2012 • www.deed.state.mn.us • Projected Electric Demand Growth: 4,500-6,300 MW by 2020 • CapX 2020 projects will ensure the region has reliable electricity to power homes, businesses and farms for decades to come • Transmission will enable more wind and renewable energy to come on-line CapX 2020 - 9/15/2014

  3. Project Groups CapX 2020 - 9/15/2014

  4. Group I Projects • Four lines work together to ensure reliability for the region • Lines meet most urgent need • Lines will serve as outlet for whatever generation resources are built (These corridors are preliminary) CapX 2020 - 9/15/2014

  5. Group 1 Project CapX Brookings, SD –SE Twin Cities • Improves reliability in West Central Minnesota, Minnesota River Valley and Twin Cities; access to new generation, including wind • Scope: approx. 250 miles, 345 kilovolt • Proposed in-service: 2012-2014 CapX 2020 - 9/15/2014

  6. Lyon Cty CapX 2020 - 9/15/2014

  7. Brookings-Twin Cities 345 kV Studies • Based on SW MN→Twin Cities EHV Development Electric Transmission Study • Completed November 2005 • Additional studies • Generation Alternative • System Adjustments: MISO Queue additions – Lake Marion Xfmr Overload • Combined CapX Group I Loss Analysis • Local Load Serving • Marshall, Franklin, Lake Marion, New Ethanol Loads • Underlying system study CapX 2020 - 9/15/2014

  8. Additional CapX Efforts • Cost Allocation: MISO RECB Analysis • MISO: Baseline Reliability Study – MTEP • Communications Team has been presenting the projects at several county & township groups along the potential route. • CapX team filed Exemption Filing, Comments regarding the filing have been received from DOC, NAWO, Windustry, Overland Law Office & Prairie Island Indian Reservation. • Notice Plan filing before CON Filing. 30 Days before CON Filing. Permitting team will determine when to file Notification Plan when CON is nearing completion. CapX 2020 - 9/15/2014

  9. Q3 2006 Q4 2006 Q1 2007 Q2 2007 Q3 2007 Q4 2007 Q1 2008 Minnesota PUC CON Timeline Implement NPs File Notice Plans Notice PlansApproved Opportunities for Public Involvement CON Issued Prepare CON File CON Hearings Briefs Reply Briefs CON Review Data Requests Environmental Review Project Communications Route Development for All Four Projects Agency/Gov’t Consultations Public Meetings Separate but coordinated efforts Oct 4, 2006 CapX 2020 - 9/15/2014

  10. Contacts • Randy Fordice—763-241-2463; rfordice@grenergy.com • www.CapX2020.com CapX 2020 - 9/15/2014