1 / 19

Renewable Energy Transmission Task Force (RTTF)

Renewable Energy Transmission Task Force (RTTF) . RTTF Chairman: Peter Krzykos November 3 2009. Overview. Past Meetings 5/12/2009 – Created three transmission maps 5/20/2009 – Created a single transmission map. Single Transmission map with Mileage and estimated costs Queue Update

miller
Télécharger la présentation

Renewable Energy Transmission Task Force (RTTF)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Renewable Energy Transmission Task Force(RTTF) RTTF Chairman: Peter Krzykos November 3 2009

  2. Overview • Past Meetings • 5/12/2009 – Created three transmission maps • 5/20/2009 – Created a single transmission map. • Single Transmission map with Mileage and estimated costs • Queue Update • BTA Process • Next Steps

  3. Past Meetings 2009 • Two meetings conducted (May 12th and 22nd) • May 12th meeting • Attended by ~40 utility, developer, and agency representatives • Divided into three groups to develop state-wide renewable transmission options based on ARRTIS data, interconnection requests, etc. • May 22nd meeting • Assimilated options into a single set of potential renewable transmission corridors • Discussed next steps/technical flow studies, etc.

  4. Assimilated Map – 5/20/2009

  5. Segment Mileage and Estimated Cost • WGA WREZ model used for construction and right of way costs. • Construction cost: $1.8 Million per mile • Right of Way cost: $0.23 Million per mile

  6. Segment Mileage and Estimated Cost (1/3)

  7. Segment Mileage and Estimated Cost (2/3)

  8. Segment Mileage and Estimated Cost (3/3)

  9. (8/11/2009)

  10. APS Queue (1/2)

  11. APS Queue (2/2)

  12. SRP Queue

  13. TEP Queue

  14. WAPA Queue

  15. BTA-Utility Evaluation Process Individual Utility Evaluation of Renewable Resource and Transmission Options • Example Inputs to Economic Evaluation: • Resource Cost • Water Availability • Resource Capacity Available • Capacity & Energy Benefits • Transmission Cost • Timing Utility Coordination & Common Projects Identification • Policy Issues: • Funding Mechanisms • Cost Recovery • Siting Constraints • Export Markets File “Top 3” along with plans and funding mechanisms (Due 10/31/09) RTTF Group Work RTTF Finance Group Work Input from Workshops RTTF ARRTIS Group Work 2008 BTA Order 70635 2006 BTA Order 69389

  16. BTA-Utility Evaluation Process Individual Utility Evaluation of Renewable Resource and Transmission Options • Example Inputs to Economic Evaluation: • Resource Cost • Water Availability • Resource Capacity Available • Capacity & Energy Benefits • Transmission Cost • Timing Utility Coordination & Common Projects Identification • Policy Issues: • Funding Mechanisms • Cost Recovery • Siting Constraints • Export Markets File “Top 3” along with plans and funding mechanisms (Due 10/31/09) Currently in these phases RTTF Group Work RTTF Finance Group Work Input from Workshops RTTF ARRTIS Group Work 2008 BTA Order 70635 2006 BTA Order 69389

  17. Next Steps • No later than October 31st – Utilities will present their projects to the ACC. • RTTF will develop study plan to evaluate reliability of Arizona transmission system based on proposed projects to the ACC.

  18. October Filing • APS took into consideration the input from the two workshops, the ARRTIS’s work, the Finance Subcommittee's work, and RTTF’s work. • Based upon its analyses ,APS identified the three RTPs ;

  19. October Filing • A. Delaney to Palo Verde 500kV line • B. Palo Verde to North Gila 500kV #2 • C. Palo Verde to Liberty and Gila Bend to Liberty • D.Additionaly, APS included the Delaney to Blythe project (Arizona Portion of DeversII)

More Related