Performance of New England During the Blackout of 2003

Performance of New England During the Blackout of 2003. Presented by David Bertagnolli, Principal Engineer ISO-New England To the Restructuring Roundtable Boston, MA – September 19, 2003. Initial Conditions - 4:00 pm, 8/14/03. 1400 MW. 50 MW. 500 MW. 200 MW. Citizens. 396. Highgate.

mina
Télécharger la présentation

Performance of New England During the Blackout of 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Performance of New England During the Blackout of 2003 Presented by David Bertagnolli, Principal Engineer ISO-New England To the Restructuring Roundtable Boston, MA – September 19, 2003

  2. Initial Conditions - 4:00 pm, 8/14/03 1400 MW 50 MW 500 MW 200 MW Citizens 396 Highgate 400 MW NE to NY PV-20 K37 K6 E205W Phase II HVDC 393 New England Load 23,370 MW 690 398 1385 Cable Cross Sound Cable-Out of Service 0 MW

  3. Surge Toward New York - 4:10:45 pm 1400 MW 50 MW 100+ MW 200 MW Citizens 396 Highgate Transient2500+ MW NE to NY PV-20 K37 K6 E205W Phase II HVDC Frequency falls to 59.4 HZ 393 690 398 1385 Cable Cross Sound Cable-Out of Service

  4. Norwalk-Northport Trip - 4:11:45 pm 1400 MW 50 MW 150 MW 0 MW Citizens 396 Highgate PV-20 K37 K6 E205W Phase II HVDC 393 690 Total New England Load lost: 2500 MW 398 1385 Cable Cross Sound Cable-Out of Service 0 MW

  5. Restoration Event Sequence • 8/14/03 • 23:45 – all New England Bulk system restored except NY ties • 23:50 – US DOE issues order authorizing use of Cross Sound Cable • 8/15/03 • 01:53 – First NY tie restored: Northfield, MA to Alps, NY in service • 12:00 – Cross Sound Cable energized • 8/16/03 • 03:45 – Discontinued emergency restoration procedure • 8/17/03 • 07:00 - Cross Sound Cable curtailed to zero. • 8/18/03 • 8/23/03 – US DOE issues a second order authorizing use of Cross Sound Cable

  6. ISO-NE and Satellite Control Centers • ISO New England • Full Operational Control • “One Set of Hands on • the Wheel” Maine New Hampshire REMVEC ISO-NE CONVEX

  7. MISO Study Regions

  8. Policy Recommendations • Operational Authority and RTO Status • Mandatory Reliability Standards and Standardized Operating Procedures • Transmission Infrastructure Planning and Improvements • Siting Approval Authority