Radiation Protection info update

Radiation Protection info update. 17 th LTEX Meeting 21 .03.2013. C. Adorisio (DGS/RP). Radiological Classification. Radiological Classification. Radiological Classification. Radiological Classification. RP Training Courses. Is DIMR needed?. Is DIMR needed?.

minowa
Télécharger la présentation

Radiation Protection info update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Radiation Protection info update 17th LTEX Meeting 21.03.2013 C. Adorisio (DGS/RP)

  2. Radiological Classification LTEX Meeting, March 21st - 2013

  3. Radiological Classification LTEX Meeting, March 21st - 2013

  4. Radiological Classification LTEX Meeting, March 21st - 2013

  5. Radiological Classification LTEX Meeting, March 21st - 2013

  6. RP Training Courses LTEX Meeting, March 21st - 2013

  7. Is DIMR needed? LTEX Meeting, March 21st - 2013

  8. Is DIMR needed? LTEX Meeting, March 21st - 2013

  9. TREC (Traceability of Radioactive Equipment at CERN) • The TREC system is present in each buffer zone: • Touch screen and bar-code reader • Bar-code stickers • TREC training course on SIR: http://sir.cern.ch LTEX Meeting, March 21st - 2013

  10. TREC (Traceability of Radioactive Equipment at CERN) • All the materials, included waste, coming out from the LHC tunnel, have to be registered in TREC and left in the buffer zone to be controlled by RP • The equipment too big to be left in the buffer zone they could be temporary left outside the buffer zone (but this has to be previously agreed by RP) • All the transports of radioactive material have to be done with the RP authorization (fiche jaune) LTEX Meeting, March 21st - 2013

  11. Radioactive material transport • All the radioactive material internal transport (intra and intersites): • EDH transport request (TNRQ) or • material stackage request (STOCK); • RP authorization is mandatory (fiche jaune) • CERN car is mandatory • If the dose rate at contact is higher than 5 µSv/h, the transport has to be done by EN/HE • Rules: EDMS 1198577 LTEX Meeting, March 21st - 2013

  12. New DMC reading system • Automatic reading and logging in a new RP database with new electronic DMC readers (LDM) • Link between IMPACT and the Operational Dosimetry system: the IMPACT number will have to be typed on the LDM • In addition to be logged in the RP database, the doses will be kept in the IMPACT database LTEX Meeting, March 21st - 2013

  13. DMC: Pool Mode Assigned dosimeters Pool dosimeters • The dosimeter is assigned to a worker, when the dose is read it is automatically logged into the RP database (DB) under his/her name • The user only have to type the IMPACT number on the reader. • The dosimeter is not assigned to a worker, when he/she access he/she needs to type first his/her CERN ID and then he/she has to type the IMPACT number on the reader. • At the reading, the dose is automatically registered under his/her name in the DB Before accessing Type the IMPACT number Type your CERN ID Ready to access At exit: after reading LTEX Meeting, March 21st - 2013

  14. DMC: second phase In future • Second step of the project: during LS1, in compliance to the recommendations from the Host States Authorities (ASN/OFSP), the DMC will become mandatory in the Simple Controlled Radiation Areas. Meanwhile: usually no need to borrow a DMC for the work in Simple Controlled Radiation Area or in Supervised Radiation Area (except DIMR II/III) • At the beginning, a list of the active IMPACT numbers will be displayed next to each DMC reader and will be kept up to date by RP (weekly). At a later stage we will investigate the possibility to simplify this feature. LTEX Meeting, March 21st - 2013

  15. In case of problem? • Alarm: leave the area immediately and contact the Radiation Protection Service for the concerned area: • Meyrin, tel. : +41 22 76 72504 • Prévessin, SPS & LHC, tel. : +41 22 76 75252 • Technical problem (battery, DMC HS, LDM HS, etc….), please contact the Operational Dosimetry Service: • Tel. : +41 22 76 70538 • operational.dosimetry@cern.ch LTEX Meeting, March 21st - 2013

  16. Optimization during design Material choice Goal: • Minimize doses received by personnel during maintenance and repair • Reduce costs for waste disposal • Consider radiological hazards in the choice of construction materials Tool to optimize material choices: ActiWiz (Authors: C.Theis and Helmut Vincke) • Computer code based on a risk model using pre-calculated FLUKA results. Considers external exposure and radioactive waste disposal • Provides radiological hazard assessment for arbitrary materials within a few seconds • Catalogue, produced with ActiWiz, listing pre-processed risk factors for typical accelerator construction materials as well as natural elements • Web-based catalogue (ActiWeb) allowing user friendly comparison of pre-processed materials • Materials not available in the catalogue can be processed with ActiWiz Web-site: https://actiwiz.web.cern.ch/ LTEX Meeting, March 21st - 2013