190 likes | 414 Vues
U.S. Customs and Border Protection Infrastructure Update Transportation Border Working Group October 27, 2010. CBP Land Port of Entry Program Conditions at ARRA Ports. Boundary, WA (CBP). Los Ebanos, TX (CBP). Whitetail, MT (CBP). Van Buren, ME (GSA – flooded). Pinnacle Road, VT.
E N D
U.S. Customs and Border ProtectionInfrastructure UpdateTransportation Border Working GroupOctober 27, 2010
CBP Land Port of Entry ProgramConditions at ARRA Ports Boundary, WA (CBP) Los Ebanos, TX (CBP) Whitetail, MT (CBP) Van Buren, ME (GSA – flooded)
Pinnacle Road, VT Existing LPOE Above: Foundation work is 98% complete End State Rendering
Churubusco, NY Above: Bollard concrete pour Below: Utility installation at the Government Garage Above: Sand backfill and stockpile Below: Installation of floor drain
Pittsburg, NH Existing LPOE End State Rendering Above: Erecting steel frame of building
Forest City, ME CBP archaeological specialists excavate the site of the proposed Forest City, ME LPOE.
Walhalla, ND Existing LPOE Above: Stem walls in place End State Rendering
Westhope, ND Existing LPOE Above: View of electrical and plumbing work End State View from South Right: Curbs in place for lanes
Sherwood, ND Existing LPOE End State Rendering Above: Curbs installed prior to asphalt paving
Antler, ND Right: View of LPOE looking North Left: Excavating for electrical in drive islands
Morgan, MT Above: Drive lane looking south at booth Below: Housing module moving into final position Above: Installation of roof sheathing on east side of LPOE Below: Truss installation at south residential unit
Wild horse, MT Left: Fire Suppression distribution lines being installed Right: Asphalt edge clean up and site grading
Carbury, ND Left: View from inside the LPOE Existing LPOE End State Rendering Right: View of newly set roof trusses and exterior of LPOE
Hansboro, ND Existing LPOE End State Rendering from South Above: Foundation work at the port
Neche, ND Left: Foundation work continues Existing LPOE Right: Installation of main building underslab plumbing and electrical End State Rendering
Frontier, WA Above: Vapor Barrier installed at LPOE depressed slab Below: Finishing concrete for slab-on-grade at Main Port Building Above: Spreading crushed base rock for asphalt paving
Willow Creek, MT Control closet, camera, and monitor installed at the Willow Creek, MT LPOE, one of seven LPOEs receiving BSDP equipment.
Noonan, ND Above: Bypass lane with RPM bollards in the background Below: Culvert under Highway 40 Above: View of the LPOE looking North
Slide Title 19 19