Project Management Context (Part 3)

Project Management Context (Part 3). Dr.Çağatay ÜNDEĞER Instructor Bilkent University, Computer Engineering Middle East Technical University, Game Technologies & General Manager SimBT Inc. e-mail : cagatay@undeger.com. Bilgisayar Mühendisliği Bölümü – Bilkent Üniversitesi – Fall 2009.

morela
Télécharger la présentation

Project Management Context (Part 3)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Context(Part 3) Dr.Çağatay ÜNDEĞER Instructor Bilkent University, Computer Engineering Middle East Technical University, Game Technologies & General Manager SimBT Inc. e-mail : cagatay@undeger.com Bilgisayar Mühendisliği Bölümü – Bilkent Üniversitesi – Fall 2009

  2. Project Management Context • Project Stakeholders • Introduction • Who are stakeholders? • Organizational Structures • Introduction • Functional Organization Structure • Projectized Organization Structure • Matrix Organization Structure • Project Management Office (PMO) • Standards and Regulations • What is a standard? • What is a regulation? • Life Cycle of a Tender • Introduction • From the view point of Employer & Tenderer • Summary

  3. Project Stakeholders • A project is started because of having someone interested in • Outcome of a project, • Which is required to satisfy their organizational needs. • Stakeholders are; • Individuals who cause a project be initiated • Those who are most directly affected by the project’s completion.

  4. Project Stakeholders • Actively involved in the project; • Have influence over project and its results.

  5. Possible Stakeholders • Customers, • Who require outcome of project, • Sponsors, • Who support project financially, • Project manager, • Project team members, • Project management office, • Other influencers, • Who has influence on project due to their organizational position and power.

  6. Project Management Context • Project Stakeholders • Introduction • Who are stakeholders? • Organizational Structures • Introduction • Functional Organization Structure • Projectized Organization Structure • Matrix Organization Structure • Project Management Office (PMO) • Standards and Regulations • What is a standard? • What is a regulation? • Life Cycle of a Tender • Introduction • From the view point of Employer & Tenderer • Summary

  7. Organizational Structures • Organizational structures can differ dramatically from one company to another. • Organizations may or may not be project based. • Those that are not project based; • Usually lack management systems necessary for efficient and effective project management.

  8. Common Organizational Structures • Functional Organization Stucture • Projectized Organization Stucture • Matrix Organization Stucture

  9. Functional Organization Stucture • A traditional hierarchical organization (like a pyramid) with; • Top management at the peak, • Direct workers at the bottom, • And middle managers in between. Chief Executive Project coordination Functional Manager Functional Manager Functional Manager Staff Staff Staff Staff Staff Staff

  10. Functional Organization Stucture • Each employee has; • One clearly designated supervisor. • Employees are grouped by their specialization such as; • Accounting, marketing, information systems, and manufacturing.

  11. Functional Organization Stucture • People within different functional areas work separately on different parts of the project. • One group takes their part of the project, • Edits it, and • Throws it to the next group. • In IT projects, because of weak coordination between departments, • This structure causes more work for everybody, • Results with a product less than what it could be.

  12. Projectized Organization Stucture • At the other extreme. • A structure where people from different functional backgrounds work together through life time of a project. Chief Executive Project coordination Project Manager Project Manager Project Manager Staff Staff Staff Staff Staff Staff

  13. Projectized Organization Stucture • Designed specifically to provide necessary resources for the project work. • In IT projects, • Because of weak coordination in project groups, • Experienced personnel, possibly required for multiple projects, are not effectively used among projects.

  14. Matrix Organization Stucture • In the middle spectrum. • A structure that typically crosses; • Functional design on one axis and • Some other design characteristic (e.g. project managers) on the other axis. Chief Executive Project coordination Manager of Project Managers Functional Manager Functional Manager Functional Manager Project Manager Staff Staff Staff % % % Staff Staff Staff Project Manager

  15. Matrix Organization Stucture • Project staffs are designated to more than one supervisor; • Report to both; • Project managers and • Head of their functional areas.

  16. Types of Matrix Stuctures • Weak matrix structures • Strong matrix structures

  17. Weak matrix structures • More near to functional organizations. • Project managers; • Have less authority on projects, • Act like as coordinators than as independent managers.

  18. Strong matrix structures • More near to Projectized organizations. • Project managers are dedicated to projects with full authority.

  19. Strong matrix structures • More difficult to manage a matrix organization.

  20. Project Management Office (PMO) • An organizational unit created; • To centralize and coordinate the projects within an organization. • Matrix structures often have a PMO. • Projectized structures almost always have a PMO.

  21. Project Management Context • Project Stakeholders • Introduction • Who are stakeholders? • Organizational Structures • Introduction • Functional Organization Structure • Projectized Organization Structure • Matrix Organization Structure • Project Management Office (PMO) • Standards and Regulations • What is a standard? • What is a regulation? • Life Cycle of a Tender • Introduction • From the view point of Employer & Tenderer • Summary

  22. Standard • A document approved by a recognized body; • Provides, for common and repeated use, rules, guidelines, or characteristics • For products, processes or services, • With which compliance is not mandatory. • e.g. some software development standards such as; • IEEE Software development stds. • High Level Architecture (HLA) M&S std.

  23. Regulation • A document that; • Specifies product, process or service characteristics, including applicable administrative provisions, • With which compliance is mandatory. • e.g. some safety regulations for production of public goods.

  24. Project Management Context • Project Stakeholders • Introduction • Who are stakeholders? • Organizational Structures • Introduction • Functional Organization Structure • Projectized Organization Structure • Matrix Organization Structure • Project Management Office (PMO) • Standards and Regulations • What is a standard? • What is a regulation? • Life Cycle of a Tender • Introduction • From the view point of Employer & Tenderer • Summary

  25. Life Cycle of A Tender(Definitions) • Tender/Awarding : • A process for purchasing a service or material • Employer/Administration/Client : • Organization or person that requests to purcase a service or material • Tender Document : • A set of documents prepared and issued by the Employer for Tender purpose.

  26. Life Cycle of A Tender(Definitions) • Tenderer : • Company submitting a proposal to the Tender • Tender Proposal : • The proposal of the Tenderer to meet the required service or material of the Employer

  27. Life Cycle of A Tender(Definitions) • Tender Board/Commitee : • A group of people authorized by Employer • To select the best tender proposal among the submitting ones • According to Employer policies. • Contractor : • Company elected for providing the service and materials specified in the Tender document.

  28. Life Cycle of A Tender(Definitions) • Contract : • Written agreement between Employer and Contractor • Setting forth the obligations of the parties thereunder, • Including, but not limited to; • The performance of the work, • The furnishing of labor & materials and the basis of payment.

  29. Employer (Stage 1) • The Employer determines his needs. • Prepares a written document for his needs • (Project Definition Document). • Prepares a document for tendering process, • Including conditions and formalities of purchasing • (Conditions of Contract, and Accompanying Documents). • Determines tender closing date. • Prepares a guideline for the Tenderers • (Instructions to Tenderers). • Issues the Tender.

  30. Employer (Stage 2) • Employer issues the tender by • Publishing it in the official gazette, and/or • Sending invitation letters: • To eligible companies or • If it is a confidential project, • To eligible companies having some; • Quality Levels (e.g. ISO, CMMI) • Security certificates (e.g. National, NATO).

  31. Employer (Stage 3) • Until the tender closing date, the Employer : • May revise tender documents, • May postpone tender closing date, • May answers questions of Tenderers. • Collects proposals until tender closing date and • Pricing envelopes are only opened after this date. • Examines proposals for procedural convenience, and • May request Tenderer for correction of inconvenience. • Tenderers whose proposals do not satisfy procedural requirements are eliminated from the tender.

  32. Employer (Stage 4) • Employer starts evaluating valid proposals and assigning points to them: • Technical Evaluation, • Company Qualification, • Administrative Evaluation, • Price Evaluation. • Employer orders companies with respect to their points. • Employer selects: • Either a winner company or • A few winner companies (short list)

  33. Employer (Stage 5)CASE 1 : A Winner Company • In Case of a single winner company: • Winner company is announced • Employer; • May bargain price, • May request Best and Final Offer (BAFO), and • Discuss administrative and technical conditions and specifications with the winner. • An agreement is made. • A contract is signed by both parties. • Project is initiated. • In case of disagreement, • Employer may call second eligible company for contracting.

  34. Employer (Stage 5)CASE 2 : A Short List • In Case of multiple winner companies: • Employer; • May bargain prices, • May request BAFO, and • Discuss administrative and technical conditions and specifications with each winner • (This could be done in a meeting open to all winners or in seperate meetings with individual winners). • Employer aim at obtaining best with lowest price. • Employer selects the most beneficial winner. • An agreement is made. • A contract is signed by both parties. • Project is initiated.

  35. Tenderer (Stage 1) • Obtains Tender documents; • If Emloyer requests a price for applying, pays it. • Starts preparing a proposal: • Examines project requirements and risks; • Prapares a coarse project management plan; • Decides on the architecture (or alternatives); • Builds a work breakdown structure; • Estimates resources (e.g. time, cost) required; • Prepares a schedule if not given by the employer • Prepares a price breakdown structure; • Answers technical matters; • Answers administrative matters; • Prepares; • Official letters, Tender forms, Guatantee letters.

  36. Tenderer (Stage 2) • Asks Employer for clarifications of unclear issues. • Revises his proposal. • Attaches; • Hardware and software specification documents, • Company qualification documents: • References, • Certifications (e.g. ISO, CMMI), • Any other related document. • Finalize Tender proposal.

  37. Tenderer (Stage 3) • Submits Tender proposal, • Before Tender Closing Date; • Tries to submit it as late as possible; • Gets a verification document from Employer for his submission. • Waits for requests and decisions of Employer. • In case called by Employer, • Holds several meetings for agreement, • May reduce the price, or • Increase/decsrease specifications. • Upon agreement, • Signs a contract with the Employer, and • Project is initiated.

  38. Summary EMPLOYER gets support of a consultant TENDERER gets tender documents EMPLOYER prepares tender documents Tender closing date (deadline for proposals) EMPLOYER collects and evaluates proposals EMPLOYER answers questions EMPLOYER gets support of a consultant EMPLOYER publishes tender documents TENDERER prepares tender proposal TENDERER submits tender proposal EMPLOYER may request correction of inconveniences from TENDERERS EMPLOYER may call the second winner EMPLOYER calls a winner for bargain EMPLOYER orders the proposals EMPLOYER & TENDERER prepare contract Project is initiated EMPLOYER & TENDERER signs the contract EMPLOYER annonces winner EMPLOYER makes a decision (continue or cancel) EMPLOYER selects the most benefical proposal EMPLOYER calls elected winners for bargain