120 likes | 315 Vues
Avoiding disputes to deliver success What types of problem can escalate into disputes?. Richard Bayfield FICE FCIArb (www.richardbayfield.com). Ice.org.uk. Adjudicators Workshop – Jan 2008.
E N D
Avoiding disputes to deliver success What types of problem can escalate into disputes? Richard Bayfield FICE FCIArb (www.richardbayfield.com) Ice.org.uk
Adjudicators Workshop – Jan 2008 • Construction now familiar with “lessons learned workshop” but 2012 will be too late – T5 / Wembley / Emirates will be relevant • Workshop - approx 40 ICE Adjudicators present – following questions asked: • Who has NEC experience – as a Construction Professional? – and as an Adjudicator / Disputologist? • What disputed issues have you been involved with as an Adjudicator and / or Advisor under NEC? • What advice would you give to reduce potential disputes before 2012? • What do you think are the key 2012 risks?
Feedback What issues have you been involved with as an Adjudicator and / or Advisor under NEC? - 1 • Extension of time • Programme Information (Absent) • Resource Information (Absent) • Contract Data (Missing / Incomplete) • Works Information (Missing / Incomplete) • Non-compliance with Compensation event procedures – time limits • Non-compliance with Compensation event procedures – Project Manager • Valuation of Compensation Event • i.e. Lack of knowledge by all parties
Feedback What issues have you been involved with as an Adjudicator and / or Advisor under NEC? – 2 • PM absents him/her self (i.e. does not get involved, avoids issues / problems – e.g. does not approve a programme or else rejects a programme without any reason) • Non adherence to “time limits” for reply within contract – 7 days Does not carry out his / her role under the contract • i.e. - Project Manager Failure • Contract assumes design is complete when it is not – result is 1000’s of compensation events –c.f. global claim • Mis-apply / mis-understand Targets (e.g. lane rental bonus) • Contract amendments (e.g. use of “contract data 3”) • Effect of decision of external auditor • i.e. - Strategic Failure
Feedback What issues have you been involved with as an Adjudicator and / or Advisor under NEC? – 3 • Valuation of Compensation Event (after disagreement between Contractor and Project Manager) • Matters which were not addressed within the contract negotiation and contract documents – matters not anticipated by either party • Falling out between 2 key individuals • Financial difficulty • External Factors – Politics / Environment / Economics / Social / Technical (PEST Factors) • i.e. – “Unavoidable” dispute issues above • Whereas “lack of knowledge, PM failure and strategic failure” disputes are all largely preventable
Adjudicator workshop Key Risks 1 • Modifying contract without understanding effect • Lack of resources • Competence (lack of) – importance of good people / teams / project management • Design changes (not managed / wrong contract form) • Insufficient time before 2012 – poor programme management • Ground conditions (adverse) • Poor quality • Supply chain – not “back to back” – not “integrated” • i.e. INTERNAL (to construction delivery team)
Adjudicator workshop Key Risks 2 • Change of Mayor (and change of Policy) – Politics • Terrorism • Oil shortage / price £ / $ – economy – inflation • Stake Holder Management • Industrial Action • Change in Law • i.e. EXTERNAL (to construction delivery team)
Advice to ODA • Countermeasures to key risks: • Invest in training the professionals (some estimate 75% never worked under NEC before) – recognise NEC is a culture (early warning / pre-empting etc) as well as a contract (e.g. 7 day period) – lack of knowledge dispute • Strong / robust / competent Project Management (avoid PM inaction disputes) – c.f. Adjudication – answer the right question – Project Manager failure dispute • Avoid contract amendments • Avoid “creeping” design into construction period (if contract assumes design is complete) – potential of multiple Compensation Events (c.f. global claim) • - Strategic failure dispute
Competence – c.f. “lack of knowledge” disputes • Reference HSE (WWW.HSE.GOV.UK): • To be competent, an organisation or individual must have: • Sufficient knowledge of the specific tasks to be undertaken and the risks which the work will entail; and • Sufficient experience and ability to carry out their duties in relation to the project; to recognise their limitations and take appropriate action in order to prevent harm (c.f. damage) to those carrying out construction work, or those affected by the work • Competent designers eliminate hazards and reduce risks – manage the risk, not the paperwork
Overview • What types of problem did escalate into disputes? • Many different types of problem but common thread is lack of knowledge (NEC is sophisticated contract – parties go into it with “eyes open”) • Internal Factors (pre-empt or countermeasure): • Competence / Competence / Competence • Experience / Education / Training • External Factors (respond to or anticipate) • Politics / Environment / Economics / Social / Technical • (i.e. PEST Factors)