ASAS GENERAL CONTRACTING CO.

ASAS GENERAL CONTRACTING CO. Visit us at www.AsasContractingQ8.com. Index. 1. General Brief. 2. Team & Organization Chart. 3. Current Projects. 4. Company Projects. General Brief. ASAS Was Established in1983 . ASAS is primarily involved in civil construction. Being an active

nay
Télécharger la présentation

ASAS GENERAL CONTRACTING CO.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ASAS GENERAL CONTRACTING CO. Visit us at www.AsasContractingQ8.com

  2. Index 1. General Brief 2. Team & Organization Chart 3. Current Projects 4. Company Projects

  3. General Brief • ASAS Was Established in1983 . • ASAS is primarily involved in civil construction. Being an active • participant in the construction market for more than 27 years, the • company has obtained a reputation of a stable and reliable partner, • having necessary technical knowledge, experience in fulfilling • complex and crucial tasks and uniting a team of active and highly • qualified employees • ASAS consists of a team of highly skilled engineers and • architects with the innovative and dynamic approach required to • develop state-of-the-art projects in the construction field. • ASAS has a highly qualified crew of Surveyors and Draftsman. • The company’s economical and technical potential allows it to carry out several contracts in construction of civil objects simultaneously.

  4. General Brief • Our goals are to: • Provide the client with a project that fulfills their requirements to the highest standard in a reasonable time frame and within their budget. • Be a company where employees are proud to work. • Be an internationally recognized executor of quality construction. • Goal fulfillment will be accomplished by: • Recruiting highly qualified professionals that are able to perform their required tasks to the best standards. • Providing our team with continuous training to increase their abilities to understand our clients’ needs.

  5. General Brief ASAS Offices are located at: Ahmed Al Jaber St., Kuwait City Salem Al Mubarak St., Salmyia ASAS employs more than 100 employees. General Manager: Engineer Gobran Saba

  6. Index 1. General Brief 2. Team & Organization Chart 3. Current Projects 4. Company Projects

  7. Our Technical Team Zelda Ziegelbaum Interior Designer Head of Z.Design (Interior Design Dept.) Gergis Aziz Civil Engineer (since 1987) Project Manager Mohsen Adeeb Civil Engineer (since 1995) Project Manager Gobran Saba General Manager Gamal Boshra Civil Engineer (since1989) Project Manager Mousa Fahmy Mena Architect (since 1986) Senior Site Engineer

  8. Our Technical Team Rasha Samy Architect (since 1997) Senior Technical Office Engineer Mahalakshmi Architect (since 1999) Technical Office Engineer Mustafa Abdul Salam ,PMP Civil Engineer (since 2000) Planner & Quality Control Gobran Saba General Manager Mahmoud Abdul Rahman Civil Engineer (since 2002) Senior Projects Coordinator Hany Helmy Gad Civil Engineer (since 2002)

  9. Our Technical Team Wafiq Melad Rezk Civil Engineer (since 2003) Yousef Melk Architect (since 2003) Site Engineer Fady Gamil Civil Engineer (since 2008) Junior Site Engineer Gobran Saba General Manager

  10. Our Technical Team Magdy Wasfy Maken Senior Surveyor Ra’afat Belal Executive Secretary Aziz Frej General Foreman Gobran Saba General Manager Kamel Attia General Foreman Moneer General Foreman

  11. Reporting Diagram General Manager BMT Hospital Adasani Villa Coptic Church KIB Bank

  12. Organizational Chart General Manager Eng: Gobran Interior Design Dept. Architect: Zelda Technical Depart. Eng: Rasha Management Depart. Eng: Mustafa BMT Hospital PM Eng: Girgis Church PM Eng: Mohsen Adsani Villa PM Eng: Mohsen KIB PM Eng: Gamal Senior Site Eng. Eng: Mousa Senior Site Eng. Eng: Wafiq Site Eng. Eng : Hany Foreman Monir Junior Site Eng. Eng: Fady Junior Site Eng. Eng: Yousef Foreman Kamel

  13. Index 1. General Brief 2. Team & Organization Chart 3. Current Projects 4. Company Projects

  14. Current Projects ASAS currently has four construction projects with a total value of KD7,500,000 equipped with specialized construction facilities, staffed with highly qualified personnel, capable of building, reconstructing, trimming and equipping new objects independently. The Current Projects are: Yacoub Behbehani Hospital. Kuwait International Bank. Adsani Villa. Egyptian Church.

  15. Index 1. General Brief 2. Team & Organization Chart 3. Current Projects 4. Company Projects

  16. Company Projects BMT Hospital Coptic Church Adsani Villa Company Projects West End Tower KIB Bank Private Chalet

  17. Yacoub Behbehani Bone Marrow Transplantation Shuwaikh Educational Jamal Abd elnasser (85) Jahez ST. Shuwaikh Medical Jahra Road (80) BMT is Located at Shuwaikh Medical Area on Al Jahra road (Road 80)

  18. Yacoub Behbehani Bone Marrow Transplantation

  19. Yacoub Behbehani for BMT Owner: Mr. AqeelBehbehani on behalf of “THIRD OF THE LATE YACOUB YOUSUF BEHBEHANI” Owner: Ministry of Public Health Consultant: Option One International

  20. Yacoub Behbehani for BMT Project Information: Contract Start Date : 27-10-2009. Contract End Date : 27-06-2011. Contract Period : 610 Days Contract Value : 4,728,419 KD. Variation Order : None SCHEMATIC DESCRIPTION OF ZONES

  21. Yacoub Behbehani for BMT BMT

  22. Yacoub Behbehani for BMT South Perspective North East Perspective North West Perspective

  23. Yacoub Behbehani for BMT

  24. Yacoub Behbehani for BMT

  25. Yacoub Behbehani for BMT

  26. Yacoub Behbehani for BMT • Project Facilities: • The Medical Center is a three storey building, covering a gross area of 8000 m2 and comprises the following facilities:- • Outpatient: • - Outpatient Department of 6 Clinics. • Medical Records. • Pharmacy. • Inpatient Wards: • One Day Ward (Three Bedded Patient Rooms). • BMT Isolation Ward (9 Single Bed Patient Rooms). • Normal Inpatient Wards (6 single bed rooms for female & pediatrics patients, 5 single bed rooms for male patients). • Bone Marrow Bank

  27. Egyptian Coptic Orthodox Cathedral Tunisia ST. Beirut ST. The Church is located behind the Hawally fire station

  28. Egyptian Coptic Orthodox Cathedral

  29. Egyptian Coptic Orthodox Cathedral Owner: Egyptian Coptic Orthodox Cathedral Architect Design: Wagdy El Meri Consultant: Fadel Tefony

  30. Egyptian Coptic Orthodox Cathedral Project Information: Contract Start Date : 30-11-2007. Contract End Date : 31-11-2009. Contract Period : 730 Days Contract Value : KD 2,650,000 Variation Order : KD 300,000 SCHEMATIC DESCRIPTION OF ZONES

  31. Egyptian Coptic Orthodox Cathedral Perspective

  32. Egyptian Coptic Orthodox Cathedral

  33. Egyptian Coptic Orthodox Cathedral

  34. Egyptian Coptic Orthodox Cathedral

  35. Egyptian Coptic Orthodox Cathedral

  36. Egyptian Coptic Orthodox Cathedral The total built-up area of the Project exceeds 25,000 square meters, which includes a 6,500 square meters basement covering the whole plot area. The complex is a multi-purpose building housing a diversified range of activities among them; a Banquet Hall with all related services. The Project includes a housing building, libraries, computer halls, a gymnasium, a kindergarten, a cafeteria, a central kitchen, administration offices and exterior car parks. The Cathedral is furnished to accommodate around 9,000 worshipers

  37. Kuwait International Bank Costal Road Fintas Co-operative Society KIB KIB is located in Fintas beside The Fintas Co-operative Society

  38. Kuwait International Bank (Funtas) Owner: Kuwait International Bank Project Manager: Gulf Consultant Consultant: Dar Osama Bukhamseen Design

  39. Kuwait International Bank

  40. Kuwait International Bank

  41. Kuwait International Bank

  42. Kuwait International Bank

  43. Kuwait International Bank (Fintas) • Project Information: • Contract Start Date : 30-05-2010. • Contract End Date : 28-02-2011. • Contract Period : 272 Days • Contract Value : KD 449,459 • Variation Order : None SCHEMATIC DESCRIPTION OF ZONES

  44. Adsani Villa (Salwa) Ta’awan Road (25) Adsani Villa is located at Salwa Sea Side

  45. Adsani Villa

  46. Adsani Villa Owner: Marzok Al Adsani Consultant: OPTION ONE INTERNATIONAL

  47. Adsani Villa

  48. Adsani Villa

  49. Adsani Villa

  50. Adsani Villa Project Information: Contract Start Date : 01-09-2009. Contract End Date : 01-07-2011. Contract Period : 660 Days Contract Value : KD 473,000 Variation Order : None SCHEMATIC DESCRIPTION OF ZONES