1 / 15

S. EVRARD – thanks to J-L Grenard and A. Pardons

XTAX repair & T9 target modification. S. EVRARD – thanks to J-L Grenard and A. Pardons. Content. Challenging situation Optimisation steps Sequence of actions Collective & individual dose Lessons learnt. XTAX repair: a challenging situation. Failure of motors

nili
Télécharger la présentation

S. EVRARD – thanks to J-L Grenard and A. Pardons

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. XTAX repair & T9 target modification S. EVRARD – thanks to J-L Grenard and A. Pardons

  2. Content • Challenging situation • Optimisation steps • Sequence of actions • Collective & individual dose • Lessons learnt S. Evrard, XTAX repair & T9 target modification

  3. XTAX repair: a challenging situation • Failure of motors • The XTAX are made of massive blocks put on motorized tables that can move up/down. • They act as primary beam dump or beam aperture limiter. • High radiation environment • The TAX blocks intercept about 10E19 protons/year  about 6 mSv/h outside the shielding and probably 30 to 40 mSv/h at the blocks and even higher near the beam impact point S. Evrard, XTAX repair & T9 target modification

  4. XTAX repair: Optimisation steps • PR537 remote control • Increase PR537 lifting height • Lateral shielding stays in place • Bunker for mechanical work • 2 level bunker • Shielding of 100 mm thick steel plate • Pre-defined holes for reducing exposure to hot elements S. Evrard, XTAX repair & T9 target modification

  5. XTAX repair: Sequence of actions 1 Bunker assembly 2 service disconnection 3 shielding roof removal 4 table handling S. Evrard, XTAX repair & T9 target modification

  6. XTAX repair: Sequence of actions 5 springremoval 6 oldmotorremoval 7 new motor installation 8 table back handling S. Evrard, XTAX repair & T9 target modification

  7. XTAX repair: on-line monitoring • The RP supervisor follows in real time more than one person and can react to any alarm • Especially useful during high dose rate job (like proximity work, service connection,…). Graphical interface On-line cumulative dose and dose rate monitoring S. Evrard, XTAX repair & T9 target modification

  8. XTAX repair: collective & individual dose Dose estimates Remote handling • Motor repair procedure very well studied and optimised  real dose <<<< estimates • Proximity intervention lessoptimised  real doses = estimates • Ways of improvement : use of robot, cold cell or new connection design • Individual dose: self-commitment 600 uSv respected Shielding S. Evrard, XTAX repair & T9 target modification

  9. T9 target modification: a challenging situation • T9 target station • Inner part of copper blocks : 1 Sv/h • T9: transformation to HiRadMat beam dump: 1. Remove target, all collimators & monitor 2. Replace upstream collimator with new collimator 3. Replace other items with TED-type beam dump 4. Close shielding and complete HRM beam dump ν-production target Copper downstream collimator blocks Steel upstream collimator Downstream monitor S. Evrard, XTAX repair & T9 target modification

  10. T9 target modification:Optimisation steps • Challenges: • Each block (2.7t) is not fitted with lifting point and has hot outer surface • Axis of 2 blocks is outside range of overhead crane • Items not designed for remote handling(installed with forklift on 1993, 4 threaded holes per block) • Solutions: • Lifting & shielding plates fixed manually on copper blocks • Custom-made lifting beam takes 2 blocks at the time • Shielding in place for all manual interventions • Extensive tests on mock-up (tools, training, camera) S. Evrard, XTAX repair & T9 target modification

  11. T9 target modification: sequence of actions Moving upper blocks with fixed lifting plates Sarcophagus with containers ready Blocks in temporary storage location Dismantling work took ~10 days, collective dose of ~1.2mSv for Copper block removal Fixing plates on lower blocks Separating blocks 21 Placing block in container Lifting test before closing roof S. Evrard, XTAX repair & T9 target modification

  12. T9 target modification: collective dose • Optimisation, tools, training brings WANF dismantling from est. 210 man.mSv to 60 man.mSv. T9 target modification amounted to 2.7 man.mSv. • The main contributions are from low dose rate but long-lasting activities, impossible to do remotely (by design) or carried out by less experienced personnel. WANF dismantling S. Evrard, XTAX repair & T9 target modification

  13. lessonslearnt • Design of High Radiation Areas • Take into account dismantling needs as from the design stage • Include dedicated areas in TA for remote handling operation, RP supervision (preparation, monitoring,…) • Equip underground areas with most recent technology means (optical fibers, cable network for cameras, Wi-Fi network) • Remote controlled crane with positioning system S. Evrard, XTAX repair & T9 target modification

  14. lessonslearnt • Intervention in High Radiation Areas: • preparation and organization are essential • Training on mock-up • Planning and resources management • Systematic dose rate check (remote device or RP technician) before intervention • On-line & daily dose monitoring • QAP S. Evrard, XTAX repair & T9 target modification

  15. lessonslearnt • Repair& dismantling procedure: some valuable concepts • Keep inaccessible the most activated parts • Avoid time-consuming activities • Mitigate time-consuming activities by shielding • Standardize repetitive actions • Enhanced personnel safety by camera monitoring • Improve reliability of key resources (overhead crane) S. Evrard, XTAX repair & T9 target modification

More Related