FBI HEADQUARTERS

FBI HEADQUARTERS. Renovation of the J. Edgar Hoover Building Washington, D.C. 2004-2008. Project Profile. 12 Story Building Constructed in 1972 1.2 Million SF of Federal Office Space Offices, High Security Floor (SCIF), FBI Tour, Dining, Secure Entrance. ARCHITECT.

oded
Télécharger la présentation

FBI HEADQUARTERS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FBI HEADQUARTERS Renovation of the J. Edgar Hoover Building Washington, D.C. 2004-2008

  2. Project Profile 12 Story Building Constructed in 1972 1.2 Million SF of Federal Office Space Offices, High Security Floor (SCIF), FBI Tour, Dining, Secure Entrance

  3. ARCHITECT Architectural /Interior Design Firm Government/Commercial Office Bldgs. / Interiors Called on firm for 8 Years Consulting Architect / Key Player on Team KCCT Architects

  4. History with Architect McKissack & McKissack McKissack & McKissack Offices (24,000 sf) Mayor’s Office / Washington, D.C Department of the Treasury / Main Briefing and Conference Room KCCT State Dept HQ Renovation FBI HQ Renovation

  5. Lines of Communication

  6. Challenges (2004) Design Phase Established Bldg. Standard Justify Glasswool over Mineral Fiber (Cost / Aesthetics / Acoustic Performance) Specification: Advantage E/15 2x2

  7. Lines of Communication

  8. Challenges (2004) Bidding Phase Armstrong contractor applies pressure to GC regarding availability of Ecophon Made in the U.S. Policy brought to forefront Availability key concern for GC (10 wks to complete Floors 3 and 10)

  9. Lines of Communication

  10. Challenges (2004) Bidding Phase 90,000 SF Advantage E/15 2x2 available in warehouse (120,000 SF total /10 Wks) LML / PSD Meet w/ Wm. H. Walston / Kamco Delivery to Secure Facility (Distributor) Contract Award to CC / Wm. H. Walston & Company

  11. Lines of Communication

  12. Challenges (2005) Design Phase / 11th Fl. SCIF Secure Floor Requires Foil-Backed Ceiling to Aid in Scrambling Electronic Signals (90,000 SF / Phases I-IV) Ecophon Asks for Design Criteria None Available from Client LML / PSD Discuss Resources for Production Advantage E w/Foil Back to be applied in Canada Sample Panels Mfg’d / Excellent Quality Material named “Advantage Security”

  13. Lines of Communication

  14. Challenges (2005) Bidding / Phases I & II Specification: Advantage Security E/15 2x2 P&P (AWI contractor) Awarded Project Material required in 6 wks /Ecophon delivered in 4 wks. Phase I (20,000 SF) Delivered 5/05 Phase II (38,000 SF) Delivered 8/05 Reception Area w/Focus Wing Cloud

  15. Challenges (2006) Bidding / Phases III & IV 9/12/06 P&P (AWI contractor) awaiting notice to proceed Quote Advantage Security E/15 2x2 52,000 SF Material to install late 4th qtr. Cost increases/scheduling (delete distribution) 10/25/06 Material ships to Canada for foil back Awaiting written order from P&P 10/28/06 Order released from P&P 12/20/06 Material arrives in US

  16. Lines of Communication

  17. Future Phases FBI / Director’s Office and Conf Room (3,000 SF Focus DG 2x2) FBI / Tour (55,000 SF Advantage E/15 2x2) Remaining Office Space (1,000,000 SF Advantage E/15 2x2)

  18. Teamwork Communication