1 / 7

LEADER: WP6 – LEAD Technology Status of WP6 activities as of May 2013

LEADER: WP6 – LEAD Technology Status of WP6 activities as of May 2013 PCC meeting - GENOVA May 2013. LEADER WPs. 6.5 Scientific and technology collaboration with ROSATOM institutions. 6.1 Material for heat transfer components. 6.2 Materials for mechanical pump.

Télécharger la présentation

LEADER: WP6 – LEAD Technology Status of WP6 activities as of May 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LEADER: WP6 – LEAD Technology Status of WP6 activities as of May 2013 PCC meeting - GENOVA May 2013

  2. LEADER WPs 6.5Scientific and technology collaboration with ROSATOM institutions 6.1 Material for heat transfer components 6.2Materials for mechanical pump 6.3Oxygen control and purification strategy 6.4Damping pressure waves inside the SG

  3. WP6: Lead Technology (KIT) Start Month: 1 – End month: 36 + 6 Lead participant: KIT Participants: CEA, CIRTEN, ANSALDO - MERIVUS, ENEA, KIT, UJV Total effort: 79 PM The work concentrates on topics to ensure the basic technologies of the project and to establish programs and priorities of co-operation with partner of GENIV and ROSATOM. The WP is organized in 5 Tasks: 4 Tasks address several specific technological issues directly linked to the coolant Task No 5 is or was? dedicated to knowledge exchange with ROSATOM

  4. Objectives of WP6 Task 1: Material for heat transfer components (A. Weisenburger / KIT-G, ENEA, UJV) Determine important mechanical properties of T91 with and without surface protection like creep and stress in combination with Pb of materials for heat transfer components Task 2: Materials for mechanical pump (M. Tarantino / ENEA, KIT-G) Test promising pump materials under realistic conditions Task 3: Oxygen control and purification strategy (C. Latge / CEA, ENEA, KIT-G) Collection and assessment of available information concerning monitoring and control of the oxygen activity in a pool type reactor and purification of lead during plant operation Task 4: Damping pressure waves inside the SG (I. Di Piazza / ENEA, CIRTEN, MERIVUS, ANSALDO) Investigate and asses the damping of pressure waves by SGTR event Task 5: Scientific and technology collaboration with ROSATOM institutions (P. Turroni / ENEA, KIT, CEA) Cooperation (exchange of knowledge and joint technological efforts) with the ROSATOM project in specific topics.

  5. M06, T09, T13 LEADER WP6 Gant Chart / extendedfor 6 months D12 D, T andMssheduleduntil Karlsruhe meeting M24- D12(6.3) Compilationofexistingdata on the liquid leadoxygencontrolstrategy – CEA, ENEA, KIT – actualplanningDraft– Mid ofJune byChristian to Alessandro andAlfons (proposedby Christian) - Final version– August 2013?? M30- T09 (6.1) Heattransferproperties – KIT – draftreportalmostfinished - final additional measurementis still ongoing (Laser flash) - Final versionJune 2013 - mainlydone M30 - T13(6.1) Surfacealuminizingofsteamgeneratorcomponents–translationofcompactversionofmasterthesis KIT - availaberight after thismeeting May 2013 – mainlydone Milestone: M24 - M06(6.4) SG test facility commissioned – ENEA, CIRTEN, MERIVUS shifted to M 36 Milestone achieved

  6. LEADER WP6 extendedfor 6 months D, and T sheduledat end ofproject M06 T09, T13 T17, D16, D33, D23, D4 D12 M36 - D16 – Task 6.2 - Erosion stabilityofmaterials in fast flowinglead – ENEA, KIT Task extended - 1sttestresults 900h in CORELLA available/ KIT contributionuntilJuly 2013 ENEA: budgetissuesdelaywork - will report 300h in Sept 2013 M36 - D33 – Task 6.1 - Summary of HLM reactors materials – KIT – mainly done (results reported at Petten Workshop and at Fr13 in Paris) draft available – Final version June 2013 M36 - T17 – Task 6.1 - Influence of lead on mechanical properties – KIT, ENEA, UJV - UJV delivered their contribution – ENEA will do Mid of May – KIT will add and submit mid of July 2013 M36 - D23 – Task 6.4 - Tests report on the performance of the proposed pressure wave damping system – ENEA, CIRTEN, ANSALDO - shifted to M36 + 6! – confirmed by ENEA M36 - D24 – Task 6.5 - Summary of the complementary and common work of EU – partners and ROSATOM institutions based on the deliverables containing the ROSATOM contribution - ENEA, CEA, KIT - ?????????????

  7. PlanningofDeliverablesand Technical reports

More Related