1 / 23

San Diego Gas & Electric Company…

San Diego Gas & Electric Company…. Investor Owned Utility (1 of 3 in CA) Serves 1.35 million customers in San Diego and Orange Counties ~4100 square miles Peak Load: 4636MW. POWER PLANTS. There are four (4) power plants in our territory Southbay Natural gas Encina Natural gas

ophrah
Télécharger la présentation

San Diego Gas & Electric Company…

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. San Diego Gas & Electric Company… • Investor Owned Utility (1 of 3 in CA) • Serves 1.35 million customers in San Diego and Orange Counties • ~4100 square miles • Peak Load: 4636MW

  2. POWER PLANTS • There are four (4) power plants in our territory • Southbay • Natural gas • Encina • Natural gas • Palomar (SDG&E) • Natural Gas • San Onofre • Nuclear

  3. Transmission System • Nominal Voltages • 500, 230, 138, 69 KV • Bulk Transport of power • Interconnections • Arizona • Mexico • Southern California • 1516 miles

  4. Our Loads • Residential • 37% • Commercial • 43% • Industrial • 20% • Lighting • 0.5%

  5. Project Team • Architect • - Electrical Engineer, HVAC Mechanical Engineer • Facilities Project Manager • - Contractor, Subcontractors • Grid Operations • - Project Manager / Technical Leader • - EMS Group Technical Liaison • - Grid Control Group Technical Liaison • - Telecommunications / Networking Group Technical Liaison • Misc. Technical Assistance as needed

  6. Project Timeline July 2008 Operations moves to New Control Room Remodel Begin/End Nov 2007 Operations moved to BCC Fall 2007 Finalized design/building permits 2007 Project funding moved to 2007/2008 2007 Control Room/Vendor site visits 2006 Technical information gathering process begins 2006 Programming with Architect/Users begin 2006 Tentative funding approved for 2006/2007 July 2005 Facilities Request and Concept Designs

  7. Project Goals • Improve Operator Situational Awareness • Improved Backup Data LED Display Wall (Data and Accuracy) • Improved ergonomic operator workstations • Replace Obsolete Technology

  8. Replace Obsolete Technology • Mid-90s Consoles • Original CSI Mapboard (1982) • EMS Sun Workstations (Replaced with Dell PCs & 3 Dell Monitors) • Original Incandescent “Digital” displays for Backup Data • Pilot Project - Four Christie Video Cubes replaced • All new wiring (electric and data) • Halon Fire Protection system replaced with FM200 system

  9. Improve Operator Situational Awareness • Improved mapboard (Mauell) - larger, redesigned layout • New Video Wall * Twelve 67” Mitsubishi DLP XGA-resolution cubes (4x3) * Dual Jupiter video processors * AMX Controlled System with Pre-programmed Video Wall Scenarios * 5 Dedicated PCs for PI displays – 5 Specialized PI Displays * Satellite and Cable TV Tuners, DVD inputs

  10. Improved ergonomic operator workstations (Mauell) • Front and Rear Surfaces separately Raise / Lower • 3 EMS Workstation Monitors (22”) on swivel mounts • 2 PC Workstation Monitors (22”) on swivel mounts

  11. Centralized Conference Room / Training Room / Situation Room • Multimedia (4 Plasma TVs, Overhead Projector) • Dual Satellite inputs, Dual Cable TV inputs, Dual Laptop inputs • Smart Board Overlays on 2 Plasma TVs • Versatile 3-Line Telephone Conferencing system • All controlled by AMX panel • Full EMS Workstation for training purposes

  12. Final Product • The new Control Room went live in mid-July 2008. • Currently working with the main project Vendor and internal staff on final punch list items.

  13. How Operator Input was used • Operators, Grid Control and Office Staff, were interviewed by the Architect and Project Team early on in the process. • The Architect produced a summary of these programming sessions and a design concept came out of those sessions.

  14. Operator Satisfaction • 20 Transmission Switching Operators and Operations Shift Supervisors that work shifts in the new Control Room. • Relatively satisfied with their new room and technology, and have made additional suggestions to help us refine some of the issues with the room.

  15. Operator Surveys 10 Individual Workspace Area Mapboard Video Wall 5 0

  16. Operator Surveys 10 Consoles – Phones Radios Consoles - Lighting Storage White noise HVAC Consoles – Monitor Placement 5 0

  17. Operator Satisfaction 10 Kitchen Situation Room 5 Room Lighting 0

  18. Operator Satisfaction 10 Operator Project Input 5 Back up Control Center 0

  19. Suggestions for a Successful Project • Clearly define the project scope • Scope creep is inevitable, but keep it manageable • Assemble a project team that is committed to a successful outcome • Half-time or better commitment is helpful

  20. Suggestions for a Successful Project (cont.) • Define roles up-front to maximize success • Who makes financial decisions, technical decisions, etc. • Who has final decision making authority in case of non-consensus • Visit other Control Rooms to see what works and what doesn’t work for them • Some ideas sound good on paper, but are not as practical to implement

  21. Suggestions for a Successful Project (cont.) • Visit trade shows, potential vendor sites and customer sites to get a good feel for their products, quality, ability to deliver, etc. • Be cognizant of NERC CIP ramifications during design and construction phases • Celebrate successes

  22. Design Consensus • Grid Control staff members and operators were polled when certain key decisions needed to be made during the final design phases. • Grid Control and Grid Operations management helped make certain decisions when it was difficult to reach a consensus.

  23. Thank You!

More Related