patch
Uploaded by
11 SLIDES
252 VUES
110LIKES

Testing and Power-Up of Module 72 at Fermilab – Progress and Next Steps (April 2011)

DESCRIPTION

On April 14, 2011, the primary goal was to power up Module 72 and obtain IV curves while interfacing with the KEK ADC system. During the visit by Osamu, Koji, and Makoto, all active devices on Module 72 were confirmed operational at room temperature, with internal noise signals and signals from the Gunn oscillator detected successfully. Challenges included adjusting the diode polarity. The following week’s objectives include moving the system to the cryostat and initiating cooling procedures for a KEK 64-channel ADC system.

1 / 11

Download Presentation
Télécharger la présentation

Testing and Power-Up of Module 72 at Fermilab – Progress and Next Steps (April 2011)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Testing at Fermilab April 14th 2011 Goal for this week: - Power up Module 72 (warm) - Get IV curves - Interface to KEK ADC system - Try to see a signal at Room T Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer)

  2. Quiet 1 Module 72 All LNA’s have individual Gate Control Summary All Active Devices on Module 72 appear to be alive at room T Success: We see the internal noise signal We see signal from Gunn Oscillator Goal for Next Week: - Move system to Cryostat - Do cool down

  3. KEK 64-channel ADC system Bias Board and MAB and Gunn Diode KEK Preamp

  4. Leg A Drain Current versus Gate Voltage Drain Voltage for all LNA’s = 250 mV We did NOT do I-V curve for V-drain = 750 mV (afraid of pushing too much drain current) LNA1 LNA3 LNA2

  5. Leg B Drain Current versus Gate Voltage Drain Voltage for all LNA’s = 250 mV We did NOT do I-V curve for V-drain = 750 mV (afraid of pushing too much drain current) LNA1 LNA3 LNA2

  6. Warm IV curve of U2 Detector Diode We found that the Detector Diode Polarity in module 72 is OPPOSITE of what we expect. We adapted by reversing our low voltage lines. Result shown AFTER reversing voltage lines

  7. Module is ALIVE: Receiver Noise is seen by KEK ADC system Total Power signal x 100 seen by KEK ADC system Phase switch Diode PA1 is turned ON and OFF

  8. Toggling Phase Switch Power All Phase Switch Diodes are alive Note: Plotted is total power seen by KEK ADC x 100

  9. Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz

  10. Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz Zoomed in time

More Related
SlideServe
Audio
Live Player
Audio Wave
Play slide audio to activate visualizer