Cryo Assembly, Cold Mass

Cryo Assembly, Cold Mass. A. Vouris Cryo Assy Meeting May 20, 2019. Cold Mass Tooling & Design Status. Lifting Fixture Sakash - Lifting fixture – Procurement submitted C.O. (+$4877.74 to $88,424.69). R. Gaytan will follow up with actual delivery date.

pearli
Télécharger la présentation

Cryo Assembly, Cold Mass

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cryo Assembly, Cold Mass A. Vouris Cryo Assy Meeting May 20, 2019

  2. Cold Mass Tooling & Design Status • Lifting Fixture • Sakash - Lifting fixture – Procurement submitted C.O. (+$4877.74 to $88,424.69). R. Gaytan will follow up with actual delivery date. • Load testing – unconfirmed, follow up needed. • Work Station Equipment • Order status • Roll Clamp Dwg.F10072149 Qty.22 ea. REQ#295411 – Tech Evaluation complete - Bid update REC’D Fri. from Walco. Best Delivery expected from Precision Boring on Mon. 5-13. Update evaluation sheet and submit for award (ASAP). • End Plate Frame Rail Assembly (PO#654865) – Inspected review of QC Hold – disposition determined. • Roller Assembly, Qty. 20 ea. (10/station) – PO#655878 to Belta-4 Due 07-June-19 • End Cover Alignment Tooling (F10071930) Qty. 2 - PO655323, 2-4 weeks late (June 14) • Other Tooling • Lower Pad Support Welding Fixture – Started redlining tolerances / • Press test Fixtures – in design • Layout Set-up – preparing…. misc. items on order and trickling in. • Work station prep- • Additional leg supports for workstations – found additional right size legs • Roller drive design in process – need 2 legs for mounting, ordered leveling feet for details A. Vouris | CM and Cryo Meeting

  3. Cold Mass Tooling & Design Status • ICB-A • Power & Misc. equipment (FRS) – Comp. air/Vac approved, vendor pricing rec’d – work planned for next fiscal year. • Occupancy – June 17th – June 20th • Cold Mass Design • Weld/Welder qualifications – Test reports rec’d and pass WPS confirmed. Welder qualification approval test report (RT) for second welder received and passed. Welding forms write-up in process • Working with UT vendor (IRIS NDT) – rec’d written PAUT procedure but waiting for procedure verification quote. Redline/modifications of Procedure in process prior to sending for CERN approval. • Requested updated MQXFA Magnet model from LBNL – model being updated with various misc changes including Pizza Box location – Expected last week per Dan Cheng. • Prototype Traveler – Process engineering working on first traveler for bus assy. • Engr Note & Tack Block re-design – Engineering Note in process - waiting for additional loading information. • Mock up of End Cover - drawing created & out for bid - order for circ weld test • Bus – Rodger Bossert report A. Vouris | CM and Cryo Meeting

  4. Cold Mass Tooling & Design Status (Extra Slides) A. Vouris | CM and Cryo Meeting