1 / 9

Electric Power Utility Motor Case Study

Electric Power Utility Motor Case Study. Diagnostics & Resolution Power utility contracted to perform off-line circuit and insulation testing of critical motors during major planned outage. Tests included MCA, IR & overvoltage hipot and impulse.

plato-diaz
Télécharger la présentation

Electric Power Utility Motor Case Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electric Power Utility Motor Case Study • Diagnostics & Resolution • Power utility contracted to perform off-line circuit and insulation testing of critical motors during major planned outage. Tests included MCA, IR & overvoltage hipot and impulse. • New 4 kV motors are impulse tested to 11.4 kVpk (IEEE). Recommended maintenance test is 9 kVpk. Impulse test discovered a 4 kV pump motor with phase insulation breakdown voltage of 7.2 kVpk. No indication of problem during MCA, IR and hipot tests. • Utility opted to start the motor repeatedly to study failure of weak motor insulation system. Insulation failed catastrophically on fifth startup. • Motor was rewound during planned shutdown • Cost of Diagnostics to Utility: <$10,000 including travel • Savings to Utility • No lost production: Potentially $100Ks • No emergency repair costs: $10Ks

  2. Common Off Line Electrical PdM Motor Tests { Under Voltage { Over Voltage

  3. Electric Power Utility Motor Case Study • Diagnostics & Resolution • Power utility contracted to perform off-line circuit and insulation testing of critical motors during major planned outage. Tests included MCA, IR & overvoltage hipot and impulse. • New 4 kV motors are impulse tested to 11.4 kVpk (IEEE). Recommended maintenance test is 9 kVpk. Impulse test discovered a 4 kV pump motor with phase insulation breakdown voltage of 7.2 kVpk. No indication of problem during MCA, IR and hipot tests. • Utility opted to start the motor repeatedly to study failure of weak motor insulation system. Insulation failed catastrophically on fifth startup. • Motor was rewound during planned shutdown • Cost of Diagnostics to Utility: <$10,000 including travel • Savings to Utility • No lost production: Potentially $100Ks • No emergency repair costs: $10Ks

  4. High Voltage Surge or Impulse • IEEE 522 & EASA • Simulates the transients on power lines which can cause insulation failure. Rise time = 0.1 µsec • Impulse test of turn and phase insulation where test voltage is incrementally increased in a stepped mode from 0V voltage to target test voltage looking for change in response frequency • Final impulse test voltage typically at 2 x line voltage + 1000 V (peak) • Only test capable of complete predictive testing of turn and phase insulation

  5. Steps of Degrading Insulation Electrical Failure • New insulation has high break down voltage • Motor insulation experiences aging • Thermal aging • Chemical or moisture contamination • Mechanical wear • Corona/Partial Discharge • Turn, phase or ground insulation break down voltage degrades resulting in arcing due to transients, start up coil movement, etc

  6. Steps of Degrading Insulation Electrical Failure • Induced arcs cause insulation to deteriorate much faster • Turn to turn or ground insulation breakdown voltage drops below operating voltage effectively causing a short between turns or a short to ground. • Shorted turns transformer action causes a large induced current in the short which creates a hot spot • Heat causes rapid insulation failure (typically minutes to hours)

  7. Breakdown Voltage Degradation v. Time

  8. Electric Power Utility Motor Case Study • Diagnostics & Resolution • Power utility contracted to perform off-line circuit and insulation testing of critical motors during major planned outage. Tests included MCA, IR & overvoltage hipot and impulse. • New 4 kV motors are impulse tested to 11.4 kVpk (IEEE). Recommended maintenance test is 9 kVpk. Impulse test discovered a 4 kV pump motor with phase insulation breakdown voltage of 7.2 kVpk. No indication of problem during MCA, IR and hipot tests. • Utility opted to start the motor repeatedly to study failure of weak motor insulation system. Insulation failed catastrophically on fifth startup. • Motor was rewound during planned shutdown • Cost of Diagnostics to Utility: <$10,000 including travel • Savings to Utility • No lost production: Potentially $100Ks • No emergency repair costs: $10Ks

  9. Contact Info:Torq EngineeringRandy Keenercell: 970-412-9337randy.keener@teamtorq.comField ServicesTrainingData Analysis

More Related