Review on Deliverables and forward look. André van Es. Review of deliverables. Three levels of deliverables: Level 3: Deliverable at Tasks Level 2: Deliverable at Design Study Level 1: Deliverable at Project Level 0: Deliverable at Board Level
E N D
Review on Deliverablesand forward look André van Es
Review of deliverables • Three levels of deliverables: • Level 3: Deliverable at Tasks • Level 2: Deliverable at Design Study • Level 1: Deliverable at Project • Level 0: Deliverable at Board Level • We present progress in terms of the Level 0 deliverables
DS-2 Rijks Universiteit Groningen ASTRON INAF-IRA MPIfR Universidad de Valencia CSIRO Swinburne Leiden Observatory Chalmers Oxford University of Manchester Observatoire de Paris Cambridge University of Melbourne Natal University PRAO-LPI University of Leeds University of Glasgow University of Adelaide DS-5 ASTRON University of Manchester Observatoire de Paris JIVE INAF-IRA MPIfR Oxford University CSIRO National Research Foundation UMK University of Cambridge OMMIC DS-4 University of Manchester ASTRON Observatoire de Paris INAF-IRA FG-IGN University of Oxford CSIRO National Research Council University of Cambridge University of Orléans CNRS OMMIR DS-3 University of Cambridge ASTRON University of Manchester CSIRO INAF-IRA University of Oxford Cambridge University Observatoire de Paris National Research Foundation DS-1 ASTRON University of Manchester Observatoire de Paris DS-6 INAF-IRA ASTRON JIVE CSIRO Univ. Sydney DS-7: University of Manchester, Observatoire de Paris
Planned Achieved Deliverable/Milestone Name Deliverabl (in (in e/ months) months) Milestone No DS1 1. 1 - oct - 05 Nov - 05 Organize kick - off DS1 2. 1 - oct - 05 1 - jan - 06 Implement adequate management tools DS1 - ongoing Continuous coordination and management DS1 - ongoing Continuous assessment and control DS1 3 1 - Nov - 05 30 - June - Document on outreach policy 06 DS1 4 1 - Apr - 05 1 - Oct - 05 Establish web - page DS1 5 1 - Nov - 05 1 - Feb - 06 Document on IPR Policy DS1 6 1 - Apr - 06 4 - Sep - 06 SKADS international workshop 2006 DS1 7 1 - Apr - 07 10 - Oct - 07 SKADS international workshop 2007 DS1 8 1 - Apr - 08 Sep 08 SKADS international workshop 2008 DS1 9 1 - Apr - 09 Sep 09 SKADS international workshop 2009 Review on deliverables: DS-1
Nominal Planned Milestone Completion Completion Date done DS4 1 30 - dec - 06 SiGe band pass filter using PIC technology prototype 31 - dec - 08 DS4 2 30 - dec - 07 ADC performance e valuation 1 - jul - 08 DS4 3 1 - jul - 07 Hybrid LNA first devices Inventory of RFI mitigation techniques and applicability to 1 - jul - 08 DS4 4 1 - jul - 06 SKA 1 - jul - 08 DS4 5 1 - jul - 07 Evaluation of impact of moving interference sources on SKA 1 - mrt - 08 DS4 6 31 - okt - 07 Characterised antenna element 1 - jul - 08 DS4 7 1 - mrt - 08 antenna element with integrated MMIC prototype 1 - mrt - 08 DS4 8 1 - jul - 07 Simulated Digital beamformer for 2 - PAD done DS4 9 30 - dec - 06 Prototype low cost SiGe analogue beamformer 2 - f eb - 09 DS4 10 29 - dec - 08 Prototype complete 2 - PAD digital tile Final reports on semiconductor technologies, RFI mitigation strategies, antenna element design, digital beamformer design 30 - jun - 09 DS4 11 30 - jun - 09 2 - PAD performance (T1 - T6) Review on deliverables: DS-4
Nominal Planned Completion Milestone Completion Date 1 30 - dec - 05 30 - dec - 05 Completion of System Requirements DS5 DS5 2 1 - mrt - 06 15 May - 06 Design Review of First Tile 3 1 - jul - 06 1 - jul - 06 Delivery of first manufactured tile DS5 DS5 4 1 - mrt - 07 1 - okt - 0 7 completion of 10 tile system 5 31 - mei - 08 1 - sept - 200 8 completion of first 100 tiles DS5 DS5 6 1 - jan - 09 1 - jan - 2009 completion of m anufacturing of all tiles Review on deliverables: DS-5
Nominal Planned Completion Milestone Completion Date DS5 1 30 - dec - 05 30 - dec - 05 Completion of System Requirements DS5 2 1 - mrt - 06 15 May - 06 Design Review of First Tile DS5 3 1 - jul - 06 1 - jul - 06 Delivery of first manufactured tile DS5 4 1 - mrt - 07 1 - okt - 0 7 completion of 10 tile system DS5 5 31 - mei - 08 1 - sept - 200 8 completion of first 100 tiles DS5 6 1 - jan - 09 1 - jan - 2009 completion of m anufacturing of all tiles Review on deliverables: DS-5
Nominal Planned Milestone Compl etion Completion Date DS6 1 1 - jul - 06 done Design Report on Analog Optical link DS6 2 30 - apr - 07 done Design Report on Analog and digital optical link DS6 3 31 - aug - 08 31 - aug - 08 Report on data handling for large telescopes Wide band high dynamic range A/D FX correlator, small DS6 4 30 - sep - 0 8 30 - sep - 08 prototype DS6 5 30 - sep - 08 30 - sep - 08 Software beamforming and multibeaming on BEST - x DS6 6 30 - sep - 08 30 - sep - 08 Algorithms for RFI mitigation DS6 7 1 - jul - 08 1 - jul - 08 Calibration methods for large array DS6 8 30 - sep - 08 30 - sep - 08 report on High sensitivity astronomical tests Review on deliverables: DS-6
Task number Deliverable Deliverable Name Planned Achieved No (in months) (in months) DS7 - T1 1 SKADS Quarterly 19 19 Report Q4/2006 DS7 - T1 2 SKADS Quarterly 22 22 Report Q1/2007 DS7 - T1 3 SKADS Quarterly 25 25 Report Q3 /2007 DS7 - T1 4 SKADS Quarterly 19 19 Report Q4/2007 DS7 - T1 5 SKADS Quarterly 22 22 Report Q1/2008 DS7 - T1 6 SKADS Quarterly 25 25 Report Q3/2008 DS7 - T1 7 SKADS Quarterly 19 19 Report Q4/2008 DS7 - T 1 8 SKADS Quarterly 22 22 Report Q1/2009 DS7 - T1 9 2007 Annual 24 25 Report to International SKA Project Office DS7 - T1 10 2008 Annual 24 25 Report to International SKA Project Office DS7 - T1 11 2009 Annual 24 25 Report to International SKA Project Office Review on deliverables: DS-7
Updated Plan • Prior to 2nd Annual Report project planning was updated • All Design Studies submitted new milestone/deliverable table • New milestone dates were discussed and agreed with DS leaders • SKADS on track to finish on 30th June 2009
Next 18 months (major milestone for each DS) • DS2: Final Report on SKA configurations • DS 3: • Implementation of Cost and Functional simulator tool • Selection of networking and computing technologies • DS 4: Completion of 2-PAD design • DS 5: Build and first testing of EMBRACE at Westerbork and Nancay (100 tiles) • DS 6: BEST demonstrating beamforming and Hl sensitivity astronomical tests • DS 8 : First iteration of Overall System Design and Project plan
Review on deliverables: DS 8 • Design Study 8 produces the major deliverables of the project (the focal and cohering point of SKADS): • Overall System Design • Preliminary SKA Plan • White Paper for the ISSC • It is the collection of all activities and will show and establish the direction towards the SKA