Over the last two years, the campus has experienced 22 outages totaling 304 hours due to failing feeder lines, substations, and electrical components. This project aims to address these issues through repairs, upgrades, and replacements across various campus facilities, including the stadium and medical substations. The schedule spans from March 2013 to December 2014, impacting power outages, equipment deliveries, and parking operations. Stay informed with construction updates and contact Scott Jefferson for more information.
E N D
Last Two Years – 22 outages for total of 304 hours (12+ days)
Feeder lines are over utilized and failing Cable, conduit, and vaults are failing Too many buildings Share the same lines
SUBSTATIONS - Old/Obsolete - Fail to meet standards of access - Not compatible with RMP
BEFORE EXAMPLES OF SWITCH REPLACEMENTS BEFORE AND AFTER AFTER
BEFORE AFTER EXAMPLES OF SWITCH REPLACEMENTS BEFORE AND AFTER
Stadium substation construction schedule March 2013 – October 2013 Impacts: Power outages, equipment deliveries, and work around parking lots
Campus-wide electrical distribution schedule March 2013 – December 2014 Phase 1: Lower & Upper Campus
Electrical Distribution Lower Campus Ductbank Routing
Electrical Distribution Upper Campus Ductbank Routing