An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Floats in the AoA network Project management (lecture)

  2. Activity and event times • Activity times: • EST • LST • EFT • LFT • Event times: • EET • LET

  3. Float • Time available for an activity or path in addition to its duration. • It can be positive or negative • It is a property of activities (and available only at given activities) • In case of more succeeding activities, the minimum have to be taken. • Types of float: • Total float • Free float

  4. Total float ? 0 ? ? 3 4 1 2 • The total float possessed by an activity. • Calculation for activity j: Total floatj = LFTj – EFTj • Identify the activity possessing float below, and calculate the total float. ? 35 ? ? 10 12 c a 15 8 b d

  5. Total float • The total float possessed by an activity. • Calculation for activity j: Total floatj = LFTj – EFTj = LFTj – (ESTj + Dj) • Identify the activities possessing float below, and calculate the total float for each. Total float = = 11 – (0+5) = 6 Total float = 23 – (5+12) = 6 5 2 12 5 11 c a 0 23 1 4 15 8 0 23 b 15 d 3 15

  6. Calculating free float • The float possessed by an activity which, if used, will not change the float in leater activities. • Free floatj = ESTj+1 – EFTj = EEThead – EETtail - D Free float = = 5 – 0 – 5 = 0 Free float = 23 – 5 – 12 = 6 5 2 12 5 11 c a 0 23 1 4 15 8 0 23 b 15 d 3 15

  7. Negative float 0 ? ? 1 2 3 • If the target time (deadline) for the project (or for a part of the project) is grater than TPT, than the float will appear on the critical path or even on some other paths. • Negative float = the time by which activities on the path or paths concerned must be reduced if the TPT is to be met. • Negative float is a type of the Total Float. ? ? ? 30 10 10 a c

  8. Negative float 0 10 20 1 2 3 • If the tartget time (deadline) for the project (or for a part of the project) is grater than TPT, than the float will appear on the critical path or even on some other paths. • Nagative float = the time by which activities on the path or paths concerned must be reduced if the TPT is to be met. • Negative float is a type of the Total Float. 15 -5 5 15 10 10 a c Total float: -5 Total float: -5

  9. Slack • Refers to events and not to activities. • Slack = LET - EET Slack: 6 Total float = = 11 – (0+5) = 6 Total float = 23 – (5+12) = 6 5 2 12 5 11 c a 0 23 1 4 15 8 0 23 b 15 d 3 Slack: 0 Slack: 0 15 Slack: 0

  10. Readings • Lockyer – Gordon (2005) Chapter 13

  11. Thanks for the attention!

  12. 7 2 10 7 11 c a 0 23 1 4 15 8 0 23 b 15 d 3 15