St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014 PowerPoint Presentation
Download Presentation
St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014

St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014

91 Views Download Presentation
Download Presentation

St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014

- - - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

  1. St. Peter Claver School Reconstruction & Rehabilitation Project2009-2014

  2. ST. PETER CLAVER SCHOOL: THE NEW VISION! A FIVE YEAR VISION

  3. SCHOOL PROFILE ESTABLISHED: SEPTEMBER 1862 POPULATION PRIMARY SCHOOL: 885 Students 439 Girls 446 Boys PRESCHOOL: 27 Students 17 Girls 10 Boys TOTAL: 912 Students NUMBER OF BOYS: 456 NUMBER OF GIRLS: 456

  4. SCHOOL PROFILE ESTABLISHED: SEPTEMBER 1862 POPULATION PRIMARY SCHOOL: 939 Students 470 Girls 469 Boys PRESCHOOL: 30 Students 19 Girls 11 Boys TOTAL: 969 Students NUMBER OF BOYS: 480 NUMBER OF GIRLS: 489

  5. STAFF 2009-2010 1 Administrative Principal 2 Administrative Vice Principals 2 Preschool Teachers 35 Primary School Teachers (Infant 1-Standard 6)

  6. GOALSOF THEPROJECT

  7. Construct two two- storey concrete buildings with 28 new classrooms . • Construct two fences to secure the infrastructure of the school. • Rehabilitate 2 existing buildings with 13 classroom • Rehabilitate the existing school library • Provide furniture for the whole school • Improve the recreational facilities of the school.

  8. PROJECT OVERVIEW PROJECT #1 PRESCHOOL Rehabilitation $60,000.00 Additional 3 classrooms for the Standard One $30,000.00 *Social Security to Pledge towards the project.

  9. PROJECT OVERVIEW PROJECT #2 Construction of the first two- Storey 14 classroom building with principal’s office and bathrooms. Estimated cost Bze$1.3 M

  10. PROJECT #3 Construction of the second two-Storey 14 classroom building with principal’s office and bathrooms. Estimated cost Bze$1.2 M

  11. PROJECT #4 Construction of two fences Rehabilitation of 2 existing buildings Rehabilitation of existing library Estimated cost Bze$700,000

  12. FURNITURE Estimated cost Bze$500,000 TOTAL........BZE $4,501,000

  13. PHASES OF THE PROJECT

  14. GROUND WORK • PROJECT PROPOSALS forwarded to various agencies • ENGINEER from BNE has visited • DISTRICT EDUCATION MANAGER has pledged support • VENEZUELAN AMBASADOR has visited • MINISTER OF EDUCATION has visited • AREA REPRESENTATIVE has visited • ENGINEER from MOE has visited • STAKEHOLDERS MEETING

  15. PROJECT #1(370 Students)

  16. Reconstruction of 14 classrooms two storey Building with Principal’s Office & Bathrooms Estimated Cost (Including Furniture): BZE $1.3 MILLION Funding Sources Identified : Belize Natural Energy SPCS Parent Teachers Association Management & Ministry of Education

  17. MAIN STREET PRESCHOOL (3 Classrooms)

  18. JOSE MARIA NUNEZ STREET STANDARD ONE (4 Classrooms)

  19. JOSE MARIA NUNEZ STRRET INFANT TWO (4 Classrooms)

  20. RECONSTRUCTION • INFANT TWO BUILDING: 4 CLASSROOMS • STANDARD ONE: 4 CLASSROOMS • PRESCHOOL: 3 CLASSROOMS

  21. SCOPE OF WORK • Demolition of the existing buildings with special care given to the asbestos roof. • Closure of School (1 week) during demolition. • Purchasing of 11 temporary classroom buildings to house 370 students( a third of the total school population) over a one year period. • Construction of a new14 classroom 2 storey building with principal’s office and bathrooms.

  22. Wiring of the new building • Installation of ceiling fans in the new classrooms • Painting of the new building • Furnishing of new classrooms

  23. FURNITURE PRESCHOOL: 3 classrooms 50 armchairs 12 learning centre tables 2 teachers desks & chairs 3 bookshelves 3 cupboards 1 kitchenette with sink

  24. INFANT TWO: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  25. STANDARD ONE: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  26. PRINCIPAL’S OFFICE Teachers’ Lounge & Print Room 1 Principal’s desk and 5 chairs 1 table to seat 20 teachers and 20 chairs for meetings and workshops 1 chalkboard 2 bookshelves 2 file cabinets 2 cupboards 1 kitchenette and sink

  27. PRINT ROOM • 3 WALL TO WALL BOOK SHELVES • 1 COMPUTER STATION • 3 TABLES FOR RISOGRAPHS & PRINTERS • 2 CUPBOARDS TO STORE SUPPLIES

  28. PROJECT #2(226 Students)

  29. Reconstruction of 14 classrooms two storey Building with Principal’s Office & Bathrooms Estimated Cost (Including Furniture): BZE $1.2 MILLION Funding Sources Identified : VENEZUELAN GOVERNMENT SPCS Parent Teachers Association Management & Ministry of Education

  30. MAIN STREET, STANDARD FIVE (6 Classrooms)

  31. MAIN STREET, STANDARD Six (4 Classrooms)

  32. RECONSTRUCTION OF TWO BUILDINGS MAIN STREET • STD V BUILDING: 6 CLASSROOMS • STD VI BUILDING: 4 CLASSROOMS

  33. SCOPE OF WORK • Demolition of the existing buildings • Construction of a new14 classroom 2 storey building to accommodate (226 students) with principal’s office and bathrooms. • Wiring of the new building • Installation of ceiling fans in the new classrooms • Painting and furnishing of the new building

  34. STANDARD FIVE: 6 classrooms 120 armchairs 12 learning centre tables 6 teachers desks & 18 chairs 6 bookshelves 6 cupboards 6 chalk boards

  35. STANDARD 6: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  36. PRINCIPALS OFFICE Teachers Lounge 1 Principal’s desk and chair 1 table to seat 20 teachers and 20 chairs for meetings and workshops 1 chalkboard 2 bookshelves 2 file cabinets 2 cupboards

  37. PROJECT #3(363 Students)

  38. Rehabilitation of three buildings & Construction of fence School Library building Cost: BZE $700,000.00 Funding Partners: Social Investment Funding SPCS Parent Teachers Association Management & Ministry of Education

  39. JOSE MARIA NUNEZ STREET PUNTA GORDA TOWN INFANT ONE (6 Classrooms)

  40. School Library

  41. Standard 2 & 3 (7 Classrooms)

  42. REHABILITATION OF THREE BUILDINGS FRONT STREET • STD 2 & 3 BUILDING: 7 CLASSROOMS • INFANT I BUILDING: 6 CLASSROOMS • SCHOOL LIBRARY

  43. INFANT ONE Total cost $31,524.13 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK Change Windows Electrification Ceiling Fans (6 per class) Painting Installation of burglar bars

  44. INFANT ONE: 6 classrooms 150 armchairs 12 learning centre tables 6 teachers desks & 18 chairs 6 bookshelves 6 cupboards 6 chalk boards

  45. STANDARD 2 & 3 Total Cost $86,323.78 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK • Change Windows • Electrification • Ceiling Fans (6 per class) • Painting • Installation of burglar bars

  46. STANDARD 2 & 3: 8 classrooms 300 armchairs 16 learning centre tables 8 teachers’ desks & 24 chairs 8 bookshelves 8 cupboards 8 chalk boards

  47. SCHOOL LIBRARY Total cost $31,524.13 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK Change Windows Electrification Ceiling Fans (10) Painting of building Installation of burglar bars Replastering of outside walls Furnishing of library