SlideServe
Menu
Préférences
© SlideServe · v2026

Waimea Community Dam (Lee Valley) - Tasman

renata avatar
12 diapositives · 425 Views · Sep 15, 2014

Waimea Community Dam (Lee Valley) - Tasman. Irrigation New Zealand Conference – Napier 7 – 10 April, 2014 Murray King Joseph Thomas Waimea Water Augmentation Committee. Lower Waimea River Drought (dry river)& Flood (1500 m3). Background.

Waimea Community Dam (Lee Valley) - Tasman - slide 1
01 / 12Waimea Community Dam (Lee Valley) - Tasman
1 / 17

Télécharger la présentation

Waimea Community Dam (Lee Valley) - Tasman
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Waimea Community Dam (Lee Valley) - Tasman Irrigation New Zealand Conference – Napier 7 – 10 April, 2014 Murray King Joseph Thomas Waimea Water Augmentation Committee

  2. Lower Waimea River Drought (dry river)& Flood (1500 m3)

  3. Background • The Waimea Plains is acutely water short - water rationing 7 out of the last 10 years. • Shortfall 22 – 70% (~600 – 1900 l/s) depending on what the low flow requirements in the Waimea River are set at. • Committee (WWAC) brief “To find a solution to acute water shortage on the Waimea Plains” • Limited high value land • Diverse land use • Long irrigation history • Well understood water resource • A multifunction dam proposed

  4. Reservoir location

  5. The Proposed Scheme Concrete faced rockfill dam (CFRD) Size of reservoir 13.4 million m3 Lake size 65.9 ha Dam height 52 m Construction time ~2 years Est. cost @ 2009 (excl hydro) ~ $42 million* *Cost likely higher when CCI and final design/peer work completed – also subject to final tender price Time to fill 1 -3 months Irrigable area 5850 ha(eq.) Tasman(now/future) 1400 ha (eq) Future Regional 515 ha (eq)

  6. Dam Centreline

  7. Scheme Ownership Structure • Scheme would be owned by water users (community-owned co-operative scheme) • Operated on a cost recovery basis • Proportion of cost should be borne by community as a whole to cover the environmental flows (incremental cost of building a larger scheme) – 30% • Other costs shared between users on basis of water demand

  8. Where are we • Regional Plan progressed since late 2012 Dam & No dam Option provided & Hearing completed late 2013 • Commissioners decision notified in early March 2014 – important benchmark re no dam restrictions – significant water cuts kick in 15/16 if no dam - cuts up to 50 % every year and more beyond this - EDA findings next slide • Consent preparation underway – 95 % complete, prelodgement/lodgement of consent ~ April 2014

  9. EDA - GDP Findings – Cost of No Augmentation This equates to GDP of $800,000 per hectare over 25 years

  10. Design • Detailed design 85 % complete • Hold until consent notified and any relevant submission evaluated • Complete detailed design and tender • Using rating mechanism require SCP and LTP planned 2014/2015

  11. Challenges • Both Regional Plan and Consents – Statutory processes • Consents – agreement on mitigation • Land acquisition • Timing SCP/LTP – Political • Funding vs. financing – sources/options/CII • Efficient tender and costing

  12. Discussion Q & A