1 / 19

Production Activity Control

Production Activity Control. When the plan has been developed, the next step is execution of the plan Production Activity Control (or often called Shop Floor Control) is to have activities performed as planned Techniques for scheduling different for various manufacturing systems: Project

rkillion
Télécharger la présentation

Production Activity Control

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Production Activity Control

  2. When the plan has been developed, the next step is execution of the plan • Production Activity Control (or often called Shop Floor Control) is to have activities performed as planned • Techniques for scheduling different for various manufacturing systems: • Project • Job shop • Batch • Flow shop

  3. Scheduling Batch Flow Line • A group of similar items is manufactured on the batch line • The focus is to minimize changeover time • The smaller the changeover time, the greater the scheduling flexibility • It is becoming very complicated when you have sequence-dependent setup

  4. How much to produce? Or How long the run time will be? • Depends on: • Available on hand • Demand rate • The changeover time • Production rate • The sequence, if any, in which items should be run • When the setup times are relatively small and independent of the sequence  produce first the item with smallest runout time • Runout time is the period existing inventory will last given forecast usage (= units in inventory / demand rate)

  5. Example

  6. Another Example Do you see any problem here? What would be the solution?

  7. Job Shop Scheduling • Job shop production is characterized by: • Process layout • Many orders with different sequence of processes • Scheduling is assigning of starting and completion times to orders (jobs) and frequently includes the time when orders are to arrive and leave each department. • Sequencing is the assigning of the sequence in which orders are to be processed.

  8. Priority Control • To determine the sequence in which orders should be processed • Common Priority Rules: • First come first served (FCFS) • Short processing time (SPT) : results in lowest WIP, lowest MLT, and lowest average job lateness • EDD (Earliest due date): works well when processing times are approximately the same • Slack time (ST): supports the achievement of due date objectives • Critical ratio (CR)

  9. Example Day 125 (all times are in days) ST = Due Date – Present Date – Total Operations Time Remaining Due Date – Present Date CR = ------------------------------------------- CR = 1 means the order is on schedule MLT Remaining

  10. Sequencing Results • EDD : A – B – C – D • SPT : B – A – C – D • ST : A – B – D – C • CR : B – A – C – D • Observation: • A and B always scheduled earlier than C and D • Important: • The status of WC to which each order goes next should be considered. (If A will go to a work center overloaded with high priority orders, there is little point of scheduling it first in the current WC)

  11. Queue Length Management • Affect WIP and manufacturing lead times • Queues are planned to compensate uneven flow of incoming work and the variations in work center processing times • The objective of QLM: • To reduce WIP • To shorten MLT • To better utilize bottleneck resources

  12. Operations Overlapping • Dividing a lot into two or more batches • Used to reduce MLT To avoid idle of operation B, SU2+TAB+Q1PB>=Q2PA+TAB Where Q = Q1+Q2

  13. Savings in Lead Time Without overlapping With overlapping Lead time savings

  14. INPUT/OUTPUT CONTROL • Short-range control technique (normally daily) • Compare scheduled input and output to actual input and output • Effective for controlling queue, WIP, and MLT • Enable the planner to determine the actions necessary to achieve the desired output , WIP, and MLT

  15. Single Work Center Processes

  16. Input / Output Control

  17. Normal Situation (Under Control) • PWIP is less than 3 or 4 times of std of the ending WIP • Acceptable deviation is about twice the standard deviation • Typical out of control situations: • Queues exceed upper limit due to equipment failure, inefficient processing, and excessive input. Solution: decreasing input or increasing process output. • Output is below the lower limit due to equipment failure, inefficient processing, inadequate input, or wrong input at assembly work centers.

  18. WIP Reduction

  19. Inadequate Input

More Related