1 / 7

Ben Brownlee, PE Associate Staff Engineer Transmission Expansion Planning Policy Committee

Ben Brownlee, PE Associate Staff Engineer Transmission Expansion Planning Policy Committee. TEPPC Requesting 2013 – 2023 Project List from TSS/SRWG SRWG Meeting July 15-17, 2013. Background. In 2013, TEPPC will create two Production Cost Model (PCM) datasets – 2014 and 2024

rob
Télécharger la présentation

Ben Brownlee, PE Associate Staff Engineer Transmission Expansion Planning Policy Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ben Brownlee, PEAssociate Staff EngineerTransmission Expansion Planning Policy Committee TEPPC Requesting 2013 – 2023 Project List from TSS/SRWG SRWG Meeting July 15-17, 2013

  2. Background • In 2013, TEPPC will create two Production Cost Model (PCM) datasets – 2014 and 2024 • Generation and Load forecasts are available for years between 2014 and 2024 • Electric topology forecasts are NOT available for years between 2014 and 2024 • But these can be obtained by comparing two powerflow cases

  3. 2014/24 PCMs based on 2013/23 Heavy Summer TSS Base Cases TEPPC 2014 Operating Case (PCM) TEPPC 2024 Common Case (PCM) 10-year Generation Forecast 11 Year*, Nodal PCM 2014 Load Forecast 2024 Load Forecast Electric Topology 2013 HS2-OP BASE CASE NOVEMBER 30, 2012 Electric Topology 2023 HS1 BASE CASE SEPTEMBER 18, 2012 *TEPPC studies will remain focused on the 10-year horizon (i.e., year 2024), whereas the other years will be available for all entities in the Western Interconnection as a starting point for studying years 2015-2023.

  4. Need to know the topology changes between the powerflow cases Electric Topology 2013 HS2-OP BASE CASE NOVEMBER 30, 2012 Electric Topology 2023 HS1 BASE CASE SEPTEMBER 18, 2012

  5. Proposed Process Project change files posted for Western Interconnection’s use in studying years 2014-2023 2013HS Case 2023HS Case Compared by TSS/SRWG Dec 2013 / Jan 2014 TSS/SRWG provides project change files (EPCs) Based on 2013HS Case Sept 2013 2013-23 Project List Review by TEPPC Stakeholders to determine projects of interest Oct 2013

  6. Next Steps • August 7-9, 2013 – TSS • ~Aug/Sept 2013 – Email request to SRWG w/ timeline, specifications, etc. • ~Oct 2013 – TEPPC review of projects • ~Oct/Nov 2013 – Request EPC files for notable projects • ~Nov/Dec 2013 – Receive EPC files • ~Dec 2013/Jan 2014 – Post EPC files for stakeholder use

  7. Ben Brownlee, PE Western Electricity Coordinating Council 155 North 400 West Salt Lake City, Utah 84103 801-819-7643 bbrownlee@wecc.biz Questions, Suggestions?

More Related