An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vacuum System How to Get Ready for Beam ? V. Baglin on behalf of the team in charge of cleanning the beam vacuum in sector 3-4 CERN TE-VSC, Geneva 1. Final numbers 2. Status of sector 3-4 cleanning 3. Conclusions V. Baglin - Chamonix 2009

  2. 1. Final Numbers V. Baglin - Chamonix 2009

  3. Sector 3-4 : Final numbers • All beam lines in the tunnel have been inspected • All visual and endoscopic inspections of the beam tubes and interconnects are documented V. Baglin - Chamonix 2009

  4. MLI • MLI : • DFBAR3 => A10R3 • ~ OK : • B10R 3 => A19R3 • Soot : • B19R3 => Q31R3 SOOT ~ OK ~ OK V. Baglin - Chamonix 2009 SOOT

  5. ~ OK MLI • ~ OK : • A32R 3 => B34L4 • MLI : • A34L4 => DFBAL4 MLI MLI V. Baglin - Chamonix 2009

  6. Beam Screens of 3-4 Declared Cleaned C20L4.V1 Q13L4.V2 C14R3.V1 B8L4.V2 V. Baglin - Chamonix 2009

  7. Beam Screens with MLI and Fibers QBQI 8L4.V2 A10L4.V2 B9R3.V1 QBQI 14L4.V2 A13L4.V1 QBQI 12L4.V1 V. Baglin - Chamonix 2009

  8. Beam Screens with Soot Traces left by the endoscope • Different types of results V. Baglin - Chamonix 2009

  9. Electron Microscopy • Investigation report SEM-EDS analysis of particles (EDMS 972804) • QBBI.21R3 line V2: Abundant presence of particles, they aggregate in macroscopic clusters. Sizes range from less than 1 µm up to 80 µm. Many have droplet shape. A “dust” of sub micrometric particles covers the bigger ones. • The composition corresponds to the materials melted in the interconnect; two main groups of particles can be established: • - Cu-rich particles with mainly Cu and some Sn and Si (possibly from brazing filler and glass fibre in the G11 around the busbar junction?) • - Stainless steel-like particles, with mainly Fe, Cr, Ni, Mo but usually also Cu that could be due to submicrometric particles covering the bigger ones. • In the overall analysis the Cu is the major element. QBBI-21R3 - V2 V. Baglin - Chamonix 2009

  10. 2. Status of Cleaning in Sector 3-4 V. Baglin - Chamonix 2009

  11. What remains to be cleanned in the tunnel ? • 53 cold masses are back to the surface from Q20R3 to Q33R3 (14 MQ, 39 MB) • V2 line : 6 cold masses with soot (B19R3 -> C20R3) V. Baglin - Chamonix 2009

  12. Soot Removal V. Baglin - Chamonix 2009

  13. Beam screens with soot in tunnel : Cleanning Method • Two plugs : one for horizontal and one for vertical parts of the beam screen • Use of a foam-plug wet with alcohol • Use of a dry foam-plug • Up to 50 passages in each direction with wet foam-plug • Up to 15 passages with dry plug V. Baglin - Chamonix 2009 Example of C19R3.V2

  14. Beam screens with soot in tunnel : C19R3 C19R3.V2 before cleanning After cleanning end entrance mid V. Baglin - Chamonix 2009

  15. Beam screens with soot in tunnel : Q19R3 Q19R3.V2 before cleanning After cleanning end entrance mid V. Baglin - Chamonix 2009

  16. Beam screens with soot in tunnel : C20R3 C20R3.V2 before cleanning After cleanning end entrance mid V. Baglin - Chamonix 2009

  17. Beam screens with soot in tunnel : Summary • B19R3, C19R3, Q19R3, A20R3, B20R3 and C20R3 have been sweept • Two vacuum systems are oxydised (C19R3 & Q19R3). The oxyde layer cannot be removed by the mechanical process. However, it is expected to have negligible impact on the vacuum performance since the outgassing rate scales like ~ exp(1/T) • Four vacuum systems have been mechanically cleanned (see samples circulating in the room). • Now, these 6 vacuum chambers will follow the protocol for the MLI removal (see next slides) V. Baglin - Chamonix 2009

  18. MLI Removal V. Baglin - Chamonix 2009

  19. MLI removal : 1st step • Based on automatic pumping/venting of a half-cell (52 m) • A cycle : 20 s pumping, 18 s plateau, 2 second vent • The pressure in the beam tube is reduced from 1 atm to 0.8 atm in 2 s • (to be compared to the arc pump down of 200 mbar/h) • Air speed of 20 m/s • This process is applied for 30 min (40 pumping/venting cycles) V. Baglin - Chamonix 2009

  20. MLI removal : 1st step • This procedure give good results i.e no more MLI are observable by endoscopy inside the beam screen • Example : • - Q8R4 till Q13R4 line V1 (~ 250 m) 3.2 g i.e 0.4 m2 1.2 g i.e 0.1 m2 ~ 100 bits V. Baglin - Chamonix 2009

  21. MLI removal : 2nd step • Based on aspiration with local pertubation controlled by endoscope • A nozzle blows filtered air, the MLI residues left behind the beam screen and the RF fingers are directed towards the beam aperture where they are aspired away. • Time : 5 min per PIM, speed of 3 m/min along the beam screen • A passage along abeam tube in a half-cell requires about half an hour V. Baglin - Chamonix 2009

  22. Nozzle demonstration : QQEI.11L4 V. Baglin - Chamonix 2009

  23. MLI Harvest : Beam Screen Alone Example of A8L4.V2 1st passage ~ 100 bits 2nd passage ~ 100 bits 3rd passage ~ 20 bits • The efficiency decrease with the number of passages • The 1st method is not efficient anymore • Debris size range from 1 x 1 to 2 x 2 mm2 V. Baglin - Chamonix 2009

  24. MLI Harvest : PIM Alone Example of QBBI.8L4.V2 QBQI 12L4.V1 1st passage ~ Too many bits (500) • Debris size range from 1 x 1 to 5 x 5 mm2 • Time ~ 5 min / PIM • Most of the debris recovered by the nozzle are coming from the PIM V. Baglin - Chamonix 2009

  25. MLI Harvest : A8L4+QBBI+B8L4 2 passages ~ 250 bits 5 passages 20 bits 9 passages 4 bits 2 per dipole ! • The tooling efficiency decrease with the number of passages V. Baglin - Chamonix 2009

  26. MLI Harvest : Tooling Efficieny Preliminary • 4-5 passages will allow to remove 95 % of what can be removed by the tool • 8-10 passages will allow to remove 99 % of what can be removed by the tool V. Baglin - Chamonix 2009

  27. MLI Harvest : How many and where remain the debris ? • Statistic was performed in the lab on 20 PIM from sector 3-4. Under analysis. • The nozzle allows to remove 90 to 99 % of the MLI debris • The remaining MLI debris are located in « corners » … probably for ever ! • We can expect the same situation for the beam screen / cold bore case • A MLI particle will probably find its place for ever in the coaxial space V. Baglin - Chamonix 2009

  28. Tunnel Work V. Baglin - Chamonix 2009

  29. Organisation • Two fronts : removal of MLI, removal of soot • Two teams • Cleaning activities started beginning of January • Procedure for MLI and soot removal have been set up • All QQBI interconnects have been open to allow MLI removal and perform PIM’s consolidation in the meantime V. Baglin - Chamonix 2009

  30. Procedure • Soot front : • - mechanical cleanning • - aspiration/ venting for 30 min • - 5 to 10 passages of aspiration under nozzle perturbation • - final endoscopy for qualification • MLI front : • - aspiration/ venting for 30 min • - 5 to 10 passages of aspiration under nozzle perturbation • - final endoscopy for qualification • All steps are documented V. Baglin - Chamonix 2009

  31. Status • The 6 magnets with soot have been sweeped • MLI 1st step : • DFBAR3 => Q16R3 is done • Q27L4 => DFBAR4 is done • 30 % remain to be done • MLI 2nd step : • A8L4 => Q8L4 is done • 99 % remain to be done • Still to be defined if 5, 10 or 15 passages are required • Rate of progress : • - < 1h per passage and per beam line and half-cell • - about 4 (2) half-cell per week and per team for 5 (10) passages V. Baglin - Chamonix 2009

  32. Vacuum Sectors at Room Temperature (A7R3, A7L4) V. Baglin - Chamonix 2009

  33. Recovery of room temperature vacuum sectors • Sectors A7R3.R and A7R3.B were at 1 mbar after the incident • Sectors A7L4.R and A7L4.B were at 5 10-2 mbar • After 3 days of pumping down, the sector A7R3.B is at 6 10-11 mbar • So, these vacuum sectors are under pure He atmosphere (as expected) V. Baglin - Chamonix 2009

  34. Inspections • Opening parts of the vacuum sector A7R3.R&B and the sectors A7L4.R&B did not revealed any traces of debris, only normal contamination could be identified by electron microscopy (EDMS 974970, 985095) • Endoscopy of magnet Q6R3 and Q6L4 did not show any traces of debris Vacuum sectors A7L4.R&B are activated this week and ready for operation Vacuum sectors A7R3.R&B will be activated in two weeks V. Baglin - Chamonix 2009

  35. Magnets at the surface V. Baglin - Chamonix 2009

  36. Surface Front • Some magnets to be installed in sector 3-4 are « new » • - Insertion of new beam screens • Other magnets are « re-used » • - Cutting and insertion of new beam screen • - Soot sweeping and cleanning with the SMI2 washing machine Give very good results for the inner beam screen Inspection of the outer coaxial space is under way V. Baglin - Chamonix 2009

  37. Conclusions • Systematic inpections revealed debris of soot and MLI all along the arc • Soot is removed by a mechanical action with a foam-plug • MLI is removed first by a pumping/venting mechanism and second by a combination of a nozzle and pumping mechanism • No traces of debris have been found outside the arc • Room temperature vacuum sectors are under commissioning • On the MLI front : still a lot of work to do in the tunnel • The objective of the coming weeks is to release sectors for PIMs interconnection V. Baglin - Chamonix 2009

  38. Acknowledgments • A. Mongelluzzo; M. Thiebert; L. Leggiero; I. Wevers; J-F Ecarnot; H. Neupert; J. Cave; W. Vollenberg; B. Teissandier; M. Malabaila; H. Kos for the endoscopic inspections • B. Jenninger, A. Sinturel, E. Mahner for the design, procurement and validation of the pumping/venting systems and nozzle systems • B. Henrist, A Vidal, G. Schneider, E. Page, J. Finelle for their comittement to the repair of sector 3-4 • Industrial support : FSU and AL43 teams • HNINP collaboration for the endoscopies after cleanning • J-M Jimenez for his constant support V. Baglin - Chamonix 2009