1 / 49

VALUE ENGINEERING

VALUE ENGINEERING. REFINERY FACILITY. Mohammed A. Us Shan Saleh H. Al-Mutairi Sagar M. Al-Anazi Samir A. Sulaiman Saleh S. Al-Abbas. VE is an intelligent option, when ?. Existing part/product cost is high Existing technology is complex/old though simpler means are available

rona
Télécharger la présentation

VALUE ENGINEERING

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VALUE ENGINEERING REFINERY FACILITY Mohammed A. Us Shan Saleh H. Al-Mutairi Sagar M. Al-Anazi Samir A. Sulaiman Saleh S. Al-Abbas

  2. VE is an intelligent option, when ? • Existing part/product cost is high • Existing technology is complex/old though simpler means are available • There is a need to release a cheaper product by cutting down some of the existing feature • The existing customer demands a minimal increment in product features that are in use • There is a need to cut down the manufacturing cycle time/cost

  3. BENEFITS OF VE • Decreasing costs • Increasing profits • Improving quality • Expanding market share • Saving time • Solving problems • Using resources more effectively

  4. OUTLINE • INTRODUCTION • FAST DIAGRAMS • COST/WORTH MODEL • RECOMMENDATIONS • Layout • Process • Mech/Elec/Piping • RESULTS

  5. PROJECT OVERVIEW • In 1993 a value engineering study was performed at a refinery facility in California. • Three teams comprised of 15 professionals: • Layout • Process • Electrical/Piping/Mechanical • On final implementation • 60% (approximately $ 35,000,000) in savings were realized, representing an 11% reduction. • Follow-on annual savings were $ 500,000/year.

  6. TEAMS Team1: Project Layout • FAST diagram to understand the present design • 4 out of 64 ideas • 12 design suggestions • The principal proposals were to • Consolidate the site to reduce interface cost and reduce the size. • Consolidate buildings to reflect required rather than desired future requirements. • $ 8.5 million

  7. TEAMS Team2: Process • FAST diagram to review the process flow • 4 proposals and 5 design suggestions out of 44 ideas • $ 38 million life cycle present worth savings • An additional $ 1 million • The principal proposals were to • Combine or delete the excessively redundant type tanks • Use seawater for process cooling • Reduce the number of seawater pumps • Eliminate pipeline scrapers

  8. TEAMS Team3: Electrical/Piping/Mechanical • FAST analysis • Focus on piping and electrical as well • 5 out of 32 ideas, estimated savings of $ 7.6 million • 24 mechanical and electrical design suggestions, estimated at $ 2.2 million • Among the principal proposals the most crucial were to • Install the main electrical distribution line aboveground. • Eliminate the 15% over design for tanks.

  9. <<< Why? How? >>> Ship Products Load Ship Transport Product Manufacture Products Transport Feedstock Receive Feedstock Avoid Demurrage Store Products Ship Products Transport Product # 1 Store Off-Test Transport Product # 2 Store Product # 1 Transport Product # 3 Store Product # 3 Store Product # 2 Team 1-Layout

  10. <<< Why? How? >>> Recycle Liquid Process Liquid Convey Liquid Project People, Plant, & Environment Handle Vapor Relief Load Meet Regulations Burn Vapor Separate Lads Accumulate Loads Collect Loads Ignite Vapor Maintain Seal Promote Clean Combustion Add Fuel Team 2-Process

  11. <<< Why? How? >>> Reconfigure Power System Energize Substations Improve Operation Reduce Risk Improve Distribution System Optimize Transformer Capacity Stepdown Voltage Receive 220 KV Power Distribute Power Co-generate Power Install Equipment Meter Usage Size Equipment Economically Increase Circuit Bar Bus Capacity Support Conductors Team 3a-Electrical Distribution

  12. Cost/Worth Model Item Cost Worth Seawater/Cooling water 9,520,000 9,520,000 Treated Water 514,000 14,000 UTILITIES Recommendation: Use seawater for process cooling Eliminate/Reduce seawater pumps Raw Water 1,097,000 1,097,000 Fire Water 3,000 3,000 Nitrogen Supply 284,000 284,000 Natural Gas System 296,000 296,000 Flare System 1,638,000 1,200,000 TOTAL 13,352,000 12,414,000

  13. Cost/Worth Model Item Cost Worth Recommendation: Combine Waste water and Off-plot Tank-feed Electrical 20,947,000 10,000,000 Communications 0 0 ELECTRICAL Tank & Spheres 14,496,000 10,000,000 Interconnecting Rack 5,403,000 4,000,000 Underground Piping 3,724,000 2,600,000 Storm Water System 123,000 123,000 Wastewater System 2,060,000 1,600,000 Plant Infrastructure 4,703,000 3,500,000 TOTAL 20,947,000 10,000,000

  14. Cost/Worth Model Item Cost Worth Administration 4,947,000 2,500,000 Recommendation: Reduce Size of Admin Building Cafeteria/Training 1,500,000 1,500,000 BUILDINGS Prayer Shelter 155,000 155,000 Security/Firehouse 556,000 556,000 Warehouse 3,092,000 2,300,000 Gatehouse 124,000 124,000 Main Substation 464,000 464,000 Port Substation 46,000 46,000 TOTAL 11,007,000 7,768,000

  15. Cost/Worth Model Construction 167,041,000 93,542,960 Overhead 312,927,030 7,242,000 International Transportation 45,101,070 Escalation & Contingency

  16. LAYOUT CASE ITEM : Revise Layout of Site • Original Layout • Feed enters the plant. • Goes to Tank • Back to Refinery • Product flow from Refinery to Mixing area. • The products flow from Mixing area to shipping area. • The Utilities facilities located in east.

  17. Refinery Feed Shipment area Mixing Area ORIGINAL LAYOUT Tank Personnel an Utility Facilities

  18. LAYOUT CASE ITEM : Revise Layout of Site • Proposed Layout • Move the tanks to the south of Refinery. • Moving all hydrocarbon products facilities to the east. • Moving most of personnel and utility facilities to the west near the site center. • All the future siting is moved to the far west.

  19. Refinery Shipment area Mixing Area ORIGINAL LAYOUT Feed Personnel an Utility Facilities Tank

  20. DISCUSSION • The primary drive for this proposal was to minimize the piping to carry the back and forth flow sequences. • The result was Reduction in on-site piping from 7,847 m to 4,499 m.

  21. Advantage of new idea • More safety layout. • Less piping in the project. • Reliable operation.

  22. PROCESS CASE ITEM : Combine/Reduce Size Storage / Port Tanks • Original process flow design • FEED STORAGE TANKS • INTRIM TANKS • SHIPMENT TANKS

  23. 1 2 3 FEED Loading Arm FEED STOCK TANKS INTRIM TANKS PRODUCT SHIPMENT TANKS FUNCTION: CHECK QUALITY FUNCTION: FEED PROCESS FUNCTION: SHIP PRODUCT

  24. PROCESS CASE ITEM : Combine/Reduce Size Storage / Port Tanks • Proposed process flow design • FEED STORAGE TANKS (Multi functions) • ONLINE SAMPLING • DIRECT PIPELINES

  25. 1 2 3 ONLINE SAMPLING FEED Loading Arm FEED STOCK TANKS FUNCTION: 1-Keep plant online 2-Provide surge in case plant offline 3- Catch off spec for rerun INTRIM TANKS PRODUCT SHIPMENT TANKS FUNCTION: CHECK QUALITY FUNCTION: SHIP PRODUCT

  26. ADVANTAGE OF NEW IDEA • Reduce excess tanks, pumps, and large piping diameter • Improve reliability • Low initial cost * • Less maintenance * (Pumps, Instrumentation, tanks, Monitoring wells) • Less energy cost

  27. COST WORKSHEET Savings = 25,183,000

  28. LIFE CYCLE COST WORKSHEET Savings = 39,629,000

  29. ORIGINAL LAYOUT

  30. PROPOSED LAYOUT

  31. WEIGHTED EVALUATION

  32. VE Recommendation 3 Revise 115 KV Plant Feed from Underground to Above Ground (No. E-3) • Original design: install plant feed underground at a distance of 4.3 kms from main substation. • Proposed design: install plant feed above ground. • Discussion: VE team feels above ground would be less expensive and is suitable for an industrial area.

  33. Original Design 2 feeders, 3” cable each (use $25/lf/cable x 6 units) 84,624 lf 25.00 $ 2,115,600 Installation (use $ 100/lf) 14,104 lf 100.00 $ 1,410,400 Subtotal markup indirects (.8) 3,526,000 $ .8 $ 3,526,000 $ 2,820,800 Total $ 6,346,800 Proposed Design 2 feeders, 3” cable each (use $10/lf/cable x 6 units) 84,624 lf 10.00 $ 846,240 Tower at 500’ spacing 30 ea 5000.00 $ 150,000 Installation (use $ 10/lf) 14,104 lf 10.00 $ 141,040 Subtotal markup indirects (.8) 1,137,280 $ .8 $ 1,137,280 $ 909,824 Total $ 2,047,104 Savings $ 4,299,696 VE Recommendation 3 Item Quantity Measure Unit Cost Total

  34. SUMMARY OF RESULTS • 13 VE proposals and 41 design suggestions. • Initial cost savings $60 mil & PW LCC savings $68 mil. • Proposal (P-44)1 not included in totals. An alternate not fully developed & affects ROI. 1 Reconfigure plant to make no Benzene

  35. SUMMARY OF RESULTS SUMMARY OF RESULTS VE PROPOSALS Process 38,700,000 47,177,000 74.3 VE savings = 92.5% Grand Total PW Cost Savings

  36. SUMMARY OF RESULTS DESIGN SUGGESTIONS Layout 2,900,000 2,900,000 56.5 Mech/Elec 2,180,0002,180,000 42.5 Design Suggestions savings = 7.5% Grand Total PW Cost Savings

  37. SUMMARY OF RESULTS LAYOUT TEAM

  38. SUMMARY OF RESULTS PROCESS TEAM

  39. SUMMARY OF RESULTS PROCESS TEAM (CONT.) 1 Idea is not fully evaluated, needs further study, and is not included in the totals

  40. SUMMARY OF RESULTS MECHANICAL/PIPING TEAM

  41. SUMMARY OF RESULTS MECHANICAL/PIPING TEAM (CONT.) GRAND TOTALS $60,007,000 $913,000 $68,598,800

  42. SUMMARY Total Impact of VE • Potential savings were identified in initial costs of about $ 55 million which reduced 17% of the planned investment. • Another $ 1 million in annual operation and maintenance savings if all ideas were implemented. • Careful follow-on study should be given to the design suggestions that have a potential additional savings in excess of $ 2 million.

  43. THANK YOU

More Related