Madison Elementary School District

Madison Elementary School District. Tonight's Topics. 1- Energy Usage and Savings 2- Solar Update 3- Recent Projects 4- Spring and Summer Projects. Where do we use all that energy?. Lighting KW Consumption. Rebate, Energy and Ops Savings. Historic KW Consumption at Heights Elementary.

roth-roth
Télécharger la présentation

Madison Elementary School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Madison Elementary School District

  2. Tonight's Topics 1- Energy Usage and Savings 2- Solar Update 3- Recent Projects 4- Spring and Summer Projects

  3. Where do we use all that energy?

  4. Lighting KW Consumption

  5. Rebate, Energy and Ops Savings

  6. Historic KW Consumption at Heights Elementary 09-10 18% 10-11 18% 11-12 4%

  7. Where are we? Increased enrollment, rate hikes, abnormal weather patterns and the adding of MTA square footage all increased the need for energy. With all of that factored in, Madison still reduced energy costs by approximately $100,000 between FY09 and FY12. Continuation of Bond Program - another exciting summer of improvements which will further the District’s goal to reduce KW consumption.

  8. Solar Locations at Madison # 1

  9. Solar Locations at Madison # 1

  10. Solar Locations at Rose Lane

  11. Solar Locations at Park Elementary

  12. Solar Structure Examples

  13. Next Steps on Solar • Execute PPA • Issue Notice to Proceed: June 1, 2013 • Achieve Commercial Operation: November 1, 2013 • Enjoy 20 Years of Solar Savings!

  14. Madison Meadows Café/Kitchen RenovationPhase One

  15. Madison Meadows Café/Kitchen RenovationPhase Two

  16. Madison Meadows Café/Kitchen RenovationComplete

  17. Madison Meadows Café/Kitchen RenovationComplete

  18. Madison Meadows Café/Kitchen RenovationComplete

  19. Upcoming ProjectsSpring and Summer 2013 • Café renovations at Heights, including active daylighting • Café renovations at Rose Lane, including active daylighting • Café renovations at Park, including active daylighting • Sidewalk replacement and security fencing at Meadows • Continued HVAC replacement at Park • Additional roof replacement at Heights • Non-skid surfacing replacement at Madison #1 and Meadows • Concrete replacement at Simis • Interior hallway painting at Camelview Questions