An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sun Tracking Solar ArrayTeam Peacock Lane Team Members: Elise King, Caitlin Greeney, Beverly Raposa & Julius Raposa Advisor: Dr. Yamayee Secondary Advisor: Dr. Albright Industrial Advisor:Jeff Cook (BPA) Client:Dr. Dillon

  2. Project Overview • Why solar? • Why tracking? • Demonstration for Dr. Dillon

  3. Project Overview

  4. Project Overview

  5. Milestones completed Minor: • Functional Specification v0.95 Sept 27 • Project Webpage launched Sept 27 • Acquire Solar Panels Oct 11 Major: • Functional Specifications v1.0 Oct 4 • Component Selection Completed Oct 25

  6. Additional Accomplishments • Dr. Albright’s concern regarding use of photoresistors addressed. • Design Decisions: 4 panels to 1 panel • Only Arduino UNO • Aluminum framing

  7. The Near Future Minor Milestones: • Design Document v0.9 Nov 1 • Design Document v0.95 Nov 8 • November Program Review Nov 22 Major Milestones: • Design Document v1.0 Nov 15 • Final Budget Nov 15 • All Parts Ordered Nov 29

  8. Design Component

  9. Issues/Concerns • Wire tangling • Reposition the base motor upside down • Which photoresistor design? • Test both configurations and select the most accurate

  10. Summary • Project Recap • Milestones Completed • Additional Accomplishments • Future Milestones • Design Component • Issues/Concerns • http://wordpress.up.edu/egr13peacocklane/ Questions???