1 / 29

Deep Draft Composite Fender Lessons Learned

Carderock. Deep Draft Composite Fender Lessons Learned. Jeff Green NSWCCD 2-9-05. Carderock. Problem. Existing ship-to-lighter fenders not SS3 capable Failures Interface issues due to different lighter shapes & sizes. Carderock. Carderock. Project Goals. Develop new fender concept

sally
Télécharger la présentation

Deep Draft Composite Fender Lessons Learned

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Carderock Deep Draft Composite FenderLessons Learned Jeff Green NSWCCD 2-9-05

  2. Carderock Problem • Existing ship-to-lighter fenders not SS3 capable • Failures • Interface issues due to different lighter shapes & sizes

  3. Carderock

  4. Carderock Project Goals • Develop new fender concept • Work with all current lighters • Improved capacity • Low maintenance • SS3 deployment & operation

  5. Carderock Design Requirements • Compatible with common JLOTS ships, lighters, and platforms • Transportable, ISO compatible • Deployment & recovery with common lift equipment • Sufficient standoff

  6. Carderock Deep Draft Composite Fender Principal Characteristics, Transport & Stowed Length…...….38’ Width…..……..6’ Height…….…..8’ Weight…12.3 LT

  7. Carderock Deep Draft Composite Fender Principal Characteristics, Deployed Length…..….17’ Width….……..6’ Height………18’ Draft………...13’ Weight…..15 LT

  8. Carderock Testing • Fall ‘02 • Handling & deployment • HSV X-1 Joint Venture

  9. Carderock Testing video

  10. Carderock Testing

  11. Carderock Results • Deployment & mooring methods unsatisfactory • Difficult deployment • Mooring line rigging • Spreader bar

  12. Carderock Design Changes • New lifting, securing, & mooring system

  13. Carderock Testing • Fall ‘03 • At-Sea test • LCU-2000, LCM-8

  14. Carderock Testing

  15. Carderock Testing

  16. Carderock Results • Mooring method successful • Deployment time consuming but acceptable • Interface w/lighters successful • Locking mechanism damaged

  17. Carderock Design Changes • Improved locking system

  18. Carderock Testing • Spring ‘04 • At-Sea test at JLOTS 04 in Honduras

  19. Carderock Testing

  20. Carderock Testing

  21. Carderock Testing • Video

  22. Carderock Results • Sea state problems • Erratic motions in SS3 • Personnel transfer complicated • 6’ standoff

  23. Carderock Were Goals Met? • Work with all current lighters? • Tested with LCU-2000, LCM-9, NL CWF • Rub rails • CWF bolts & corners • Improved capacity? • Cushion elements sufficiently sized

  24. Carderock Were Goals Met? • Low maintenance? • No corrosion problems • Localized composite & cushion damage • Missing bolts • SS3 operation? • Erratic motions • Related mooring issue

  25. Carderock Were Goals Met? • Transportable? • Transported by truck & ship • Handled with forklifts, cranes • ISO compatible? • Fit ISO 8x8x40 size

  26. Carderock Were Goals Met? • Deployment & recovery with common lift equipment? • Cargo crane & standard lifting gear • Sufficient standoff? • ~6 out of 8 ain’t bad, but room for improvement

  27. Carderock Improvements & Future Considerations • Motions • Restraints • Design • Cushion height • Composite protection • Cushion resilience

  28. Carderock Key Lessons Learned • Reconsider requirements • Ship mods • SS3 deployment & recovery • Early user input

  29. Carderock Questions?

More Related