1 / 13

IDPU Ground Support Equipment Preliminary Design Review F. Harvey

IDPU Ground Support Equipment Preliminary Design Review F. Harvey University of California - Berkeley. Overview. GSE Requirements GSE Components IDPU GSE Traveling GSE Calibration GSEs “Gold Box” ETU board debug GSE Interface Board Defect Tracking Schedule Issues. Requirements.

sanne
Télécharger la présentation

IDPU Ground Support Equipment Preliminary Design Review F. Harvey

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IDPU Ground Support Equipment • Preliminary Design Review • F. Harvey • University of California - Berkeley

  2. Overview • GSE • Requirements • GSE Components • IDPU GSE • Traveling GSE • Calibration GSEs • “Gold Box” ETU board debug • GSE Interface Board • Defect Tracking • Schedule • Issues

  3. Requirements • Evolving Roles • ETU Board debug: digital test signals, instrument TLM… • Instrument calibration: analog stimulus, fixtures… • Flight Board test • IDPU GSE: STOL/ITOS/Hashii • Requirements • Robust for travel • No data loss or corruption introduced by GSE • Able to create semi-realistic input conditions for tests • Flight grade electronic and mechanical interfaces. • Safety checks (like FSW) for HV and deployment. • Longevity

  4. GSE Components • Commercial • GPIB-compatible power supplies • GPIB-compatible waveform generator • Firewire-compatible 333kSps ADC • 19” 6U VME subrack • Rugged traveling case • Altera Stratix / Nios computer • GSE computer • Locally designed and built components • GSE Interface Board, software and FPGA • Power supply connection to backplane • Motor, SMA, and load simulators. • Cabling

  5. IDPU GSE • Properties • Spacecraft-like interface to IDPU, telemetry & power • User interface is modeled on Hashii/ITOS/STOL. • Provides digital test patterns for ESA & SST • Provides analog waveforms for instrument(s)

  6. Traveling GSE • Properties • Robust enclosure • Supports full IDPU GSE abilities, board regression testing. • Does not easily support calibrations outside SSL.

  7. Calibration GSEs • Properties • Major parts • EFI “Boom Box”. 2 varieties, 2 copies each, 4 Meters long • Vacuum chamber and pumps • Ion gun • Manipulator • Manipulator controller • References • Jim Lewis’ PDR PowerPoint talks on ESA & SST • J Bonnell’s paper “Themis EFI GSE Workstation Functional Requirements”, 9/30/2003

  8. “Gold Box” ETU board debug • Properties • Can supply digital “test patterns” for missing parts: FGE, SST, ESA • Usually sends DUT’s telemetry to PC, not S/C telemetry. • Small VME backplane. Shares boards with larger GSEs.

  9. GSE Interface Board • Overview • Altera Stratix Board, mounted as daughter board • 6U parent has simple non-FPGA circuits borrowed from DCB design. • FPGA has CDI transmit / receive, test pattern generation, TLM receive, UART, Spin Sync logic, S/C time circuit. • Tristate logic and 100 ohm resistors allow test patterns when certain boards are missing.

  10. Defect Tracking • NASA-compliant Defect Tracking • Themis PFR (Problem Failure Report) • Template file supplied with GSE software • Email front end. • Tracks suspected problems with Themis, FSW, GSE, interface boards, ITOS, MOC… • Prioritized • Cognizant Engineer is always assigned to an entry (until it’s resolved) • Mission Assurance Holds Original & Tracks to Closure

  11. Schedule • GSE-related target dates • DFB breadboard 10/27/03 (no UCB GSE planned) • EFI boom calibration 11/03 • PCB ETU 12/08 • DCB ETU 12/15 • ETC ETU 12/15 • BEB (actel) ETU 1/2/04 • FGE ETU 1/20/04 (no UCB GSE planned) • LVPS 1/23/04 • IDPU ETU 4/13/04

  12. Schedule • I&T Flow

  13. Issues • Shared Facilities • Configuration control • Upstairs Vacuum chamber • Downstairs Vacuum chamber • Tight resources for building GSEs • Layout personnel • Technicians • FPGA engineers • GSE programmers

More Related