240 likes | 593 Vues
. . A Review of the Deliverables:. These are the guideline deliverables. You may want to refine for your project.Also, remember to refine your Charter as you progress through your project.. DMAIC Steps. Phase. Deliverables. Define. SIPOCCustomers and CTQs establishedProblem Statement, Business
E N D
1. CASE STUDY Manufacturing Organization
Project Name: Wastage Reduction in Manufacturing process of XYZ Ltd
Process : Manufacturing
Green Belt : Mr ABC
2. DMAIC Steps
3. Define Phase-
Project Charter
Business Case
SIPOC
Voice of Customer (VOC)
Critical To Quality (CTQ)
4. DMAIC Project Charter
5. Define the problem statement-Project charter Background/problem description: Current process wastage is very high as close to 20%hence process becomes sub-optimal and high resource is required to do inspection of final output.
Project objective/goal: High wastage leads to pressure on COGS. Hence it is essential to reduce the wastage to less than 10%.
Project deliverables: identify the reduce the High wastage leads to pressure on COGS.
6. BUSSINESS CASE AND IMPACT- XYZ is the first product XYZ Ltd, India is exporting to US market
This product is very critical as it is new product in the Kids range in US
Based on success of this product J&J India can get other new products from
US and from other franchises like Neutrogena
The process of pouching soap in to bi-layered tredegar film(aperatured
plastic film) is developed by XYZ Ltd India team
Current process wastage is very high as close to 20% hence process becomes
sub-optimal and high resource is required to do inspection of final output
Due to limitation in manual checking a rejected soap can go to the market
and can lead to serious market complaint
High wastage leads to pressure on COGS
Tredegar film contributes around 18% to total COGS
Hence it is essential to reduce the wastage to less than 10%
Business Impact
USD 10101 or Rs. 505,050 PER ANNUM
7. High Level Improvement Timeline
8. SIPOC
9. .
10. .
11. voice of Customer by Kano Model
12. Analyze Phase- Multi-Vari Analysis
Operator
Shift
Machine
Hypothesis testing using ANOVA
Cause & Effect diagram
Improper sealing
Uneven cutting
13. Analyze Phase- Multi-vari analysis out put.
Shift is having slight impact on rejection. In the A
shift rejection is less which is mainly due to more
supervision.
In case of operator unskilled operator showed high
amount of wastage
Machine 3 & 4 showed less wastage, so concentrate
on machine no. 2
14. Identify the y to be improved-
Y= reduce the High wastage leads to pressure on COGS.
15. Fish Bone Diagram/Cause & Effect/Ishikawa Diagram
16. Cause & Effect analysis:-
17. .
18. Fish Bone Diagram/Cause & Effect/Ishikawa Diagram
19. .
20. . Improper sealing and uneven cutting are two major
reasons for generating high amount of wastage.
Out timing was noticed to be main cause of shifting
the position of soap in sealing and cutting station
Group discussed to concentrate on reasons for out
timing
21. Cause & effect analysis-
22. . Innovative
Improvement-
Solution prioritization matrix
FMEA of defects
Cost Benefit Analysis
23. Control Phase- Process capability & sigma
Process yield improves from 61% to 88%
Sigma improves from 1.9 to 2.7
System modification
Tredegar machine maintenance SOP revised to include
schedule for replacing soap feed conveyor links to quarterly
basis
Suction system implemented for trim collection
Key Learning's
Use of PE methodology to systematically analyze the
process which gives opportunity for process improvements