SR 50 Projects

SR 50 Projects. Overview of SR 50 (West). West SR 50 Corridor From US 27 in Lake County to Pine Hills Road in Orange County

sen
Télécharger la présentation

SR 50 Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SR 50 Projects

  2. Overview of SR 50 (West) West SR 50 Corridor From US 27 in Lake County to Pine Hills Road in Orange County Existing Four Lane Rural Roadway Widened and Re-constructed to a Six Lane Urban Roadway with Raised Medians, Bike Lanes, Curb & Gutter, and Sidewalks, includes new Interchange at US 27 and new bridges at Lake Bennett, Lake Lotta and Lake Sherwood

  3. Overview of SR 50 (East) East SR 50 Corridor From SR 436 to Old Cheney Highway in East Orange County Existing Four Lane Rural Roadway Widened and Re-constructed to a Six Lane Urban Roadway with Raised Medians, Bike Lanes, Curb & Gutter, and Sidewalks, includes new Urban Interchange at SR 436

  4. State Road 50 (West) Projects

  5. US 27 Interchange with SR 50 Project 238429-3 1.724 Miles • Design Build Project • Advertises March 17, 2011 • Bid Opening : July 14, 2011 • Anticipated Notice to Proceed: Sept. 2011 • The Interchange will be Lighted

  6. East of Grand Hwy to West of Hancock (1.080 Miles) Project 238429-7 • Currently under construction • Completion expected Winter 2012 • This segment does not include lighting • because it was not justified • City of Clermont is a stakeholder

  7. West of Hancock to East Ramps of Turnpike Project 238429-4 (5.464 Miles) • This Project is in Construction • Expected Early completion date: • Late Summer 2011 • Originally FY 2008 Deferred to FY • 2009 • Project contains 1 mile of • exception (Plaza Collina) completed • prior to this contract • Contractor on schedule to earn all • bonuses & incentives • Involves realigning Oakland Ave. • connection at SR 50 in Town of • Oakland

  8. East Ramps of Turnpike to Avalon Rd Project 239535-2 (1.269 Miles) • Updated Plans are currently in review • Utility Coordination is ongoing • Production Date: February 1, 2012 • This segment does not include lighting • because it is not justified • Originally FY 2010 Deferred to FY 2012. In • tentative Work Program (Not yet adopted) • Town of Oakland & City of Winter Garden • are Stakeholders

  9. West of Avalon Rd. to SR 429 Project 410983-1 (3.056 Miles) • Design Build ARRA Stimulus Project • Currently in construction • Relocation/Construction of 12 Utility • Facilities • City of Winter Garden to relocate water & • sewer Lines • Estimated completion summer 2011 • Lighting is not included in this segment • because it is not justified • Originally FY 2012 Deferred to FY 2014. • Advanced to FY 2010 Letting using ARRA • Funds • Transportation Outreach Program • Agreement on this segment for design

  10. SR 429 to East of West Oaks Mall Project 239535-3 (2.560 Miles) • Plans update is scheduled to • begin February 1, 2012 • Production Date: April 1, 2014 • This segment includes Lighting • in the plans • Future LFA’s for Mast Arm & • Lighting with the City of • Ocoee • Traffic Study for City of Ocoee in • process

  11. East of West Oaks Mall to West of Good Homes Road Project 239535-5 (0.445 Miles) • Updated Plans are currently in • review • Utility Coordination is on going • Utility & Mast Arm JPA’s with Ocoee pending • Production Date: March 1, 2012 • This segment includes lighting In the plans • Originally FY 2012 Deferred to FY 2013 • Advanced to FY 2012 in Tentative Work • Program

  12. Good Homes Rd. to Pine Hills Rd Project 239535-4 (3.631 Miles) • Currently under construction • Originally programmed FY 2008 • deferred to FY 2009 • Anticipated completion: March 2011 • LFA’s (Local Funding Agreements) to • assist funding the design and cost for • Mast Arm upgrades • Initiating lighting agreements with • utility owners • 7 months minimum to design & construct once agreements are in place.

  13. Good Homes Rd. SR 408 to 1000’ N OF SR 50 Project 420086-1 (1.520 Miles) • Currently under construction • This project is being constructed • with 239535-4 • Anticipated completion: March 2011 • LFA contributed funding for right of way acquisition & construction of Good Homes Rd. connecting to SR 408

  14. State Road 50 (East) Projects

  15. West of SR 436 to .2 Miles West of SR 417 Project 239203-2 (3.628 Miles) • Project is complete • Roadway Lighting is under • construction by agreement with • OUC • Originally FY 2009, advanced to • FY 2007 deferred to FY 2008 • LFA’s for Mast Arm Upgrades for • the SR 50/SR 436 Interchange • JPA (Joint Project Agreement )for • Landscaping Improvement • (FY 2012)

  16. 0.3Miles East of SR 417 to Dean Rd. Project 239203-3 (SIB) (1.041 Miles) • John Carlo Inc. defaulted April 16, • 2010 • Safety Interim Contractor: Lane • Construction from April 2010 to June • 2010 • Prince Construction took over • project June 1, 2010 • Current anticipated completion • date: April 14, 2011 • Lighting is not included in this • segment because it was not justified • LFA’s for side street improvements; • for the relocation of a lift station & a • joint use pond; Mast Arm upgrades • & for the design of this segment

  17. East of CR 425 (Dean Rd.) to East of Old Cheney Hwy Project 239203-4 (5.200 Miles) • Plans update underway • Utility Coordination is • ongoing • Production Date: May 1, 2012 • This segment does not include • lighting because it is not • justified • Originally FY 2010, deferred to • FY 2013 • LFA’s for funding of Mast Arm • Upgrades & for design of this • segment

  18. East of Old Cheney to SR 520 Project 239203-7 (5.266 Miles) New Candidate Project - Anticipated Approval July 2011

  19. Challenges & Opportunities • Driveway Connections • Pedestrian and Transit Access during Construction •  Median Openings- Full Opening and Directional Openings • Elimination of Existing Right Turn Lanes

  20. What Challenges & Opportunities do you see in the future?