This case study explores the application of Unadjusted Technical Complexity Factor (UTV) and Environmental Complexity Factor (UEV) within software development use cases, specifically UUCW and UAW. It calculates the Technical Complexity Factor (TCF) and the Environmental Complexity Factor (ECF), providing a comprehensive formula to derive Unadjusted Use Case Points (UCP). The analysis includes detailed calculations and results, demonstrating the impact of complexity factors on project timelines, ultimately leading to a total of 1094.24 hours or approximately 136.78 days.
E N D
UUCW 23 Use cases
UAW 4 actors
Factor • Unadjusted TCF value (UTV) 19,5 • TCF Weighting (TWF) 0,01 • TCF Constant (TC) 0,60 • Technical Complexity Factor (TCF) = TC + (UTV * TWF) 0,795 • Αποτέλεσμα: 0,6 + 0,195 = 0,795
Factor • Unadjusted ECF value (UEV)26 • ECF Weighting (EWF)-0,03 • ECF Constant (EC)1,40 • Environmental Complexity Factor (ECF) = EC + (UEV * EWF)0.62 • Αποτέλεσμα: 1,40 + (26 * -0,03) = 0,62
UCP = (UUCW + UAW) * TCF * ECF * PF • UCP = (210 + 12) * 0,795 * 0,62 * 10 • UCP = 1094,24ώρες / 8 ώ.η = 136,78 ημέρες