1 / 11

Annual Conference 2014

Annual Conference 2014. Maternal and Child Health System Project. Denis Wilson Manager Information Technology Moreland City Council. M&CH System Issues. Concern about M&CH data management Growing risk of using outdated systems Difficulty in aggregating data in decentralised model

sharla
Télécharger la présentation

Annual Conference 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Annual Conference2014 Maternal and Child Health System Project Denis WilsonManager Information TechnologyMoreland City Council

  2. M&CH System Issues • Concern about M&CH data management • Growing risk of using outdated systems • Difficulty in aggregating data in decentralised model • Ancillary systems for vulnerable children • Lack of support for mobile and off-line access • Lack of integration to other systems • National eHealth changes – PCEHR services

  3. Way forward • Identified as major project for MAV Technology to support with resourcing and funding and act as a catalyst • MCH IT Steering Committee formed and workshops organised • EOI released in October 2013 to ascertain vendor interest • 65 Councils identified interest at first stage • Shared State-wide system to deliver a standardised approach across Victoria • Key stakeholders- Councils- Department of Education & Early Childhood Development (DEECD)- State Government- Federal Government

  4. Expected Benefits • Provide enhanced capabilities to better monitor vulnerable children • Better data to support family assistance, factual reporting and completion of all ages and stages visits • More relevant health referrals • Higher quality reporting to better support future demand planning • Reduction in disadvantage in health and education • Higher quality aggregated population health data • Higher nurse productivity with mobility and off-line access • Victorian MCH service to continue to be regarded as a world leader in children’s health and development

  5. Post EOI Activities • EOI identified a short list of vendors who could feasibly deliver a fully functional system for the likely funding that could be available • Project Manager appointed - Karen Darling from ROI Solutions • MCH Project Control Board formed in April 2014 • Business Case completed in April 2014 – needed to source formal funding commitment from State Govt • Minister Wendy Lovell announces $2m funding for the project in June 2014 • Business Analyst appointed to develop detailed requirements specification document with key input from MCH reps at Council and State levels and IT reps from Councils

  6. Project Control Board • Project Sponsor – Rob Spence, MAV CEO • Project Manager – Karen Darling, ROI Solutions • Senior User Rep – Clare Hargreaves, MAV Manager Social Policy • MCH User Rep – Joanne Fittock, MAV Policy Advisor • State Govt Supplier Rep – Pippa Proctor, DEECD • MAV Supplier Rep – Cameron Spence, MAV Commercial Manager • MAV Supplier Rep – Jo Cross, MAV Procurement • ICT Rep – Denis Wilson, IT Manager

  7. M&CH IT Infrastructure Survey • Background data needed on IT Infrastructure in Councils supporting MCH Service to confirm content in requirements document • Distributed to managers responsible for IT on July 29 with one week to respond • 41 responses - 26 Rural- 15 Metro- 52% was an excellent response at short notice

  8. M&CH Survey Results • Ave per Council of 16 MCH staff/admin- 11 have mobile phones- 12 desktop PCs, 3 laptops, 1 tablet • Mobile phones – 50% are smartphones (55% iPhones) • Browsers – 98% IE, 30% Chrome, 20% Firefox, 19% Safari • MCH system used – 78% MaCHS, 20% Xpedite • 50% of Xpedite users have integration to other modules • Very little integration of MaCHS to other systems (SMS only) • 80% have support agreements in place

  9. M&CH Survey Results • 95% use IRIS – enhanced MCH system • 15% use the Birth Notice database • 7% of MCH Centres do not have internet access • eDMS – 40% TRIM, 15% TechOne ECM, 15% RecFind • 25% planning on changing eDMS • Email/calendar – 84% Exchange, 14% Lotus Notes • 32% use SMS messaging to clients • Business Continuity – Maximum Allowable DowntimeVaried from 2 hours to 2 weeks

  10. Next Steps • Complete detailed requirements specification mid Aug 2014 • Release tender (open for 4 weeks) end Aug 2014 • Select preferred vendor Oct 2014 • Commence system build/configuration Nov 2014 • Data load and system testing Mar 2015 • Pilot implementation May 2015 • Post-pilot review Jun 2015 • Commence limited selective rollout July 2015 • Comprehensive rollout Q4 2015 / 2016

  11. Questions?